5160 N VELOZ AVE 91356

Certificate Information: 5160 N VELOZ AVE 91356

Application / Permit
23014-20000-03134
Plan Check / Job No.
B23VN10525
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
12'-11" X 16'-7" COVERED PATIO ADDITION, 31'-4" X 16'-7" TRELLIS AND 9'-0" X 20'-10" ADDITION TO EXISTING SINGLE FAMILY DWELLING - PER ENGINEER
Permit Issued
Issued on 10/31/2023
Issuing Office
Current Status
CofO Issued on 1/16/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/7/2023 APPLICANT
Assigned to Plan Check Engineer 8/11/2023 DANIEL ABRAMYAN
Corrections Issued 8/14/2023 DANIEL ABRAMYAN
Applicant returned to address corrections 8/29/2023 DANIEL ABRAMYAN
Plan Check Approved 9/14/2023 DANIEL ABRAMYAN
Issued 10/31/2023 APPLICANT
CofO in Progress 9/3/2024 MORRIS JACKSON
Permit Finaled 1/16/2025 JOHN JANSON
CofO Issued 1/16/2025 JOHN JANSON
Permit Finaled 1/16/2025 JOHN JANSON

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 8/16/2023 ROMAN GUTIERREZ
Grading Pre-Inspection Cleared 8/16/2023 SERGIO VALENZUELA
Roof/Waste drainage to street Cleared 8/16/2023 ROMAN GUTIERREZ
GPI Written Notices Cleared 9/14/2023 DANIEL ABRAMYAN

Contact Information

Contractor Mary Construction; Lic. No.: 852310-B       ,
Engineer Mezey,, Steven William; Lic. No.: NA2665       ,

Inspector Information

JOHN KIDWELL, (818) 774-4314 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 11/22/2023 Partial Approval JOHN KIDWELL
Footing/Foundation/Slab 11/22/2023 Partial Approval JOHN KIDWELL
Deputy Drilled-In Anchors 1/8/2024 Approved SEAN HAUPT
Footing/Foundation/Slab 1/11/2024 Approved JEFFREY PARD
BUILDING-Rough-Frame 2/20/2024 Partial Approval JOHN KIDWELL
Floor/Roof Diaphrgm/Shear Wall 2/20/2024 Partial Approval JOHN KIDWELL
Rough-Elec/Plmb/HVAC 2/20/2024 Partial Approval JOHN KIDWELL
SGSOV-Seismic Gas S/O Valve 2/20/2024 SGSOV Not Ready JOHN KIDWELL
HVAC-Rough 3/5/2024 Approved JOHN KIDWELL
Interior/Exterior Lathing 3/5/2024 Partial Approval JOHN KIDWELL
Shower Pan 3/5/2024 Approved JOHN KIDWELL
BUILDING-Rough-Frame 3/12/2024 Approved JOHN KIDWELL
Green Building Rough 3/12/2024 Approved JOHN KIDWELL
Insulation 3/12/2024 Approved JOHN KIDWELL
Drywall Nailing 3/19/2024 Approved JOHN KIDWELL
Gas Test 4/29/2024 Approved JEFFREY HARTLINE
Final 8/28/2024 Corrections Issued JOHN KIDWELL
Green Building Final 8/28/2024 Not Ready for Inspection JOHN KIDWELL
SGSOV-Seismic Gas S/O Valve 8/28/2024 SGSOV Not Ready JOHN KIDWELL
Smoke Detectors 8/28/2024 Approved JOHN KIDWELL
ELECTRICAL-Final 9/3/2024 Approved MORRIS JACKSON
Final 9/3/2024 OK to Issue CofO MORRIS JACKSON
Green Building Final 9/3/2024 Approved MORRIS JACKSON
HVAC-Final 9/3/2024 Approved MORRIS JACKSON
PLUMBING-Final 9/3/2024 Approved MORRIS JACKSON
SGSOV-Seismic Gas S/O Valve 9/3/2024 SGSOV Approved MORRIS JACKSON