9411 W KIRKSIDE ROAD 90035
Certificate Information: 9411 W KIRKSIDE ROAD 90035
- Application / Permit
- 23014-20000-03133
- Plan Check / Job No.
- B23VN10521
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- REMOVE (E) 1632 SF SFD EXCEPT FOR 4' OF WALL AND FOUNDATION AT WESTERN PORTION. REBUILD 38' X 67'-6" IRREGULAR SHAPED 2-STORY SFD OVER BASEMENT W/ 2-CAR GARAGE. NFPA 13D FIRE SPRINKLERS THROUGHOUT. ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 4/15/2024
- Issuing Office
- Valley
- Current Status
- Issued on 4/15/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 8/7/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 8/24/2023 | RAPHAEL ROSAS |
| Corrections Issued | 8/30/2023 | RAPHAEL ROSAS |
| Quality Review Completed | 9/8/2023 | STEVEN KIM |
| Applicant returned to address corrections | 1/22/2024 | RAPHAEL ROSAS |
| Applicant returned to address corrections | 3/8/2024 | RAPHAEL ROSAS |
| Applicant returned to address corrections | 3/14/2024 | RAPHAEL ROSAS |
| Building Plans Picked Up | 3/21/2024 | APPLICANT |
| Applicant returned to address corrections | 3/28/2024 | RAPHAEL ROSAS |
| Applicant returned to address corrections | 4/3/2024 | RAPHAEL ROSAS |
| Plan Check Approved | 4/15/2024 | RAPHAEL ROSAS |
| Issued | 4/15/2024 | APPLICANT |
Permit Application Clearance Information
| Low Impact Development (LID) | Cleared | 9/20/2023 | MELINEH AGHAKHABIAN |
| Trees in Parkway | Cleared | 10/17/2023 | ADALBERTO VERA |
| Hydrant and Access approval | Cleared | 10/22/2023 | JOHN CONNEALLY |
| Roof/Waste drainage to street | Cleared | 10/22/2023 | AHMED AMARRAGY |
| Address approval | Cleared | 2/7/2024 | HISASHI KOBAYAKAWA |
| Permit | Cleared | 2/7/2024 | HISASHI KOBAYAKAWA |
| GPI Written Notices | Cleared | 4/3/2024 | RAPHAEL ROSAS |
| Grading Pre-Inspection | Cleared | 4/3/2024 | RAPHAEL ROSAS |
| Eng Process Fee Ord 176,300 | Cleared | 4/8/2024 | ANTHONY MAINEZ |
| Sewer availability | Cleared | 4/8/2024 | ANTHONY MAINEZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Smith,, Melvin Bruce; Lic. No.: GE2673 | 2165 N MARVEL AVE SIMI VALLEY, CA 93065 |
| Engineer | Yuzon,, Benigno Sari; Lic. No.: S3454 | 2511 PEACHWOOD PLACE WESTLAKE VILLAGE, CA 91361 |
Inspector Information
| ASHLEY THOMPSON, (310) 914-3897 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| Service/Power Release | 7/24/2026 Time Frame: 7-9 |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 5/3/2024 | Partial Approval | MEL KHACHATOURIAN |
| Piling/Pier/Caisson | 5/3/2024 | Partial Approval | MEL KHACHATOURIAN |
| Deputy Reinf. Concrete | 5/6/2024 | Conditional Approval | MICHAEL PELHAM |
| Piling/Pier/Caisson | 5/8/2024 | Partial Approval | OGANES TARAKHCHYAN |
| Excavation/Setback/Form/Re-Bar | 5/13/2024 | Partial Approval | JESUS RODRIGUEZ |
| Piling/Pier/Caisson | 5/13/2024 | Partial Approval | JESUS RODRIGUEZ |
| PLUMBING-Rough | 5/17/2024 | Partial Approval | MEL KHACHATOURIAN |
| METHANE-Subgrade | 7/10/2024 | Partial Approval | ASHLEY THOMPSON |
| METHANE-Barrier | 8/8/2024 | Approved | MEL KHACHATOURIAN |
| Excavation/Setback/Form/Re-Bar | 8/30/2024 | Corrections Issued | ASHLEY THOMPSON |
| Footing/Foundation/Slab | 8/30/2024 | Not Ready for Inspection | ASHLEY THOMPSON |
| METHANE-Subgrade | 8/30/2024 | Not Ready for Inspection | ASHLEY THOMPSON |
| Excavation/Setback/Form/Re-Bar | 9/5/2024 | Corrections Issued | ARAM AVEDISIAN |
| Excavation/Setback/Form/Re-Bar | 9/6/2024 | Corrections Issued | ARAM AVEDISIAN |
| METHANE-Subgrade | 9/6/2024 | Corrections Issued | ARAM AVEDISIAN |
| Excavation/Setback/Form/Re-Bar | 9/9/2024 | Partial Approval | ARAM AVEDISIAN |
| METHANE-Subgrade | 9/9/2024 | Approved | ARAM AVEDISIAN |
| Excavation/Setback/Form/Re-Bar | 9/17/2024 | Partial Approval | ASHLEY THOMPSON |
| Deputy Shotcrete | 9/20/2024 | Conditional Approval | MICHAEL PELHAM |
| Floor/Roof Diaphrgm/Shear Wall | 11/25/2024 | Partial Approval | SEAN HAUPT |
| Floor/Roof Diaphrgm/Shear Wall | 12/10/2024 | Partial Approval | ARAM AVEDISIAN |
| Floor/Roof Diaphrgm/Shear Wall | 1/2/2025 | Corrections Issued | ASHLEY THOMPSON |
| Deputy Steel/Welding | 1/6/2025 | No Access for Inspection | KENNETH NAGLE |
| Sewer | 1/17/2025 | Approved | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 1/22/2025 | Corrections Issued | ARAM AVEDISIAN |
| Deputy Wood Construction | 1/24/2025 | Conditional Approval | MICHAEL PELHAM |
| Floor/Roof Diaphrgm/Shear Wall | 2/3/2025 | Conditional Approval | EVAN COOPER |
| ELECTRICAL-Rough | 3/17/2025 | Corrections Issued | ASHLEY THOMPSON |
| METHANE-Rough | 3/25/2025 | Approved | ARAM AVEDISIAN |
| PLUMBING-Rough | 3/25/2025 | Corrections Issued | ARAM AVEDISIAN |
| ELECTRICAL-Rough | 4/23/2025 | Not Ready for Inspection | EVAN COOPER |
| HVAC-Rough | 4/30/2025 | Corrections Issued | EVAN COOPER |
| ELECTRICAL-Rough | 5/1/2025 | Approved | MEL KHACHATOURIAN |
| HVAC-Rough | 5/6/2025 | Approved | MEL KHACHATOURIAN |
| PLUMBING-Rough | 6/2/2025 | Approved | EVAN COOPER |
| BUILDING-Rough-Frame | 7/3/2025 | Not Ready for Inspection | ASHLEY THOMPSON |
| Green Building Rough | 7/3/2025 | Not Ready for Inspection | ASHLEY THOMPSON |
| Interior/Exterior Lathing | 7/3/2025 | Partial Approval | ASHLEY THOMPSON |
| Shower Pan | 7/3/2025 | Not Ready for Inspection | ASHLEY THOMPSON |
| Verify Sprinkler Sign Off | 7/3/2025 | Approved | ASHLEY THOMPSON |
| BUILDING-Rough-Frame | 7/17/2025 | Approved | EVAN COOPER |
| Green Building Rough | 7/17/2025 | Approved | EVAN COOPER |
| Shower Pan | 7/28/2025 | Corrections Issued | ASHLEY THOMPSON |
| Insulation | 8/19/2025 | Corrections Issued | ASHLEY THOMPSON |
| Shower Pan | 8/19/2025 | Not Ready for Inspection | ASHLEY THOMPSON |
| Insulation | 8/21/2025 | Approved | ASHLEY THOMPSON |
| Shower Pan | 8/21/2025 | Approved | ASHLEY THOMPSON |
| Drywall Nailing | 9/2/2025 | Approved | ASHLEY THOMPSON |
| Interior/Exterior Lathing | 9/8/2025 | Approved | ASHLEY THOMPSON |
| HVAC-Final | 6/24/2026 | Corrections Issued | ASHLEY THOMPSON |
| HVAC-Final | 7/6/2026 | Approved | ASHLEY THOMPSON |
| ELECTRICAL-Final | 7/7/2026 | Corrections Issued | MORRIS JACKSON |
| ELECTRICAL-Final | 7/15/2026 | Approved | ASHLEY THOMPSON |
| PLUMBING-Final | 7/15/2026 | Approved | ASHLEY THOMPSON |