9411 W KIRKSIDE ROAD 90035

Certificate Information: 9411 W KIRKSIDE ROAD 90035

Application / Permit
23014-20000-03133
Plan Check / Job No.
B23VN10521
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
REMOVE (E) 1632 SF SFD EXCEPT FOR 4' OF WALL AND FOUNDATION AT WESTERN PORTION. REBUILD 38' X 67'-6" IRREGULAR SHAPED 2-STORY SFD OVER BASEMENT W/ 2-CAR GARAGE. NFPA 13D FIRE SPRINKLERS THROUGHOUT. ALL WORK PER ENGINEERING.
Permit Issued
Issued on 4/15/2024
Issuing Office
Valley
Current Status
Issued on 4/15/2024
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 8/7/2023 APPLICANT
Assigned to Plan Check Engineer 8/24/2023 RAPHAEL ROSAS
Corrections Issued 8/30/2023 RAPHAEL ROSAS
Quality Review Completed 9/8/2023 STEVEN KIM
Applicant returned to address corrections 1/22/2024 RAPHAEL ROSAS
Applicant returned to address corrections 3/8/2024 RAPHAEL ROSAS
Applicant returned to address corrections 3/14/2024 RAPHAEL ROSAS
Building Plans Picked Up 3/21/2024 APPLICANT
Applicant returned to address corrections 3/28/2024 RAPHAEL ROSAS
Applicant returned to address corrections 4/3/2024 RAPHAEL ROSAS
Plan Check Approved 4/15/2024 RAPHAEL ROSAS
Issued 4/15/2024 APPLICANT

Permit Application Clearance Information

Low Impact Development (LID) Cleared 9/20/2023 MELINEH AGHAKHABIAN
Trees in Parkway Cleared 10/17/2023 ADALBERTO VERA
Hydrant and Access approval Cleared 10/22/2023 JOHN CONNEALLY
Roof/Waste drainage to street Cleared 10/22/2023 AHMED AMARRAGY
Address approval Cleared 2/7/2024 HISASHI KOBAYAKAWA
Permit Cleared 2/7/2024 HISASHI KOBAYAKAWA
GPI Written Notices Cleared 4/3/2024 RAPHAEL ROSAS
Grading Pre-Inspection Cleared 4/3/2024 RAPHAEL ROSAS
Eng Process Fee Ord 176,300 Cleared 4/8/2024 ANTHONY MAINEZ
Sewer availability Cleared 4/8/2024 ANTHONY MAINEZ

Contact Information

Contractor Owner-Builder       ,
Engineer Smith,, Melvin Bruce; Lic. No.: GE2673 2165 N MARVEL AVE      SIMI VALLEY, CA 93065
Engineer Yuzon,, Benigno Sari; Lic. No.: S3454 2511 PEACHWOOD PLACE      WESTLAKE VILLAGE, CA 91361

Inspector Information

ASHLEY THOMPSON, (310) 914-3897 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

Service/Power Release 7/24/2026    Time Frame: 7-9

Inspection Request History

Excavation/Setback/Form/Re-Bar 5/3/2024 Partial Approval MEL KHACHATOURIAN
Piling/Pier/Caisson 5/3/2024 Partial Approval MEL KHACHATOURIAN
Deputy Reinf. Concrete 5/6/2024 Conditional Approval MICHAEL PELHAM
Piling/Pier/Caisson 5/8/2024 Partial Approval OGANES TARAKHCHYAN
Excavation/Setback/Form/Re-Bar 5/13/2024 Partial Approval JESUS RODRIGUEZ
Piling/Pier/Caisson 5/13/2024 Partial Approval JESUS RODRIGUEZ
PLUMBING-Rough 5/17/2024 Partial Approval MEL KHACHATOURIAN
METHANE-Subgrade 7/10/2024 Partial Approval ASHLEY THOMPSON
METHANE-Barrier 8/8/2024 Approved MEL KHACHATOURIAN
Excavation/Setback/Form/Re-Bar 8/30/2024 Corrections Issued ASHLEY THOMPSON
Footing/Foundation/Slab 8/30/2024 Not Ready for Inspection ASHLEY THOMPSON
METHANE-Subgrade 8/30/2024 Not Ready for Inspection ASHLEY THOMPSON
Excavation/Setback/Form/Re-Bar 9/5/2024 Corrections Issued ARAM AVEDISIAN
Excavation/Setback/Form/Re-Bar 9/6/2024 Corrections Issued ARAM AVEDISIAN
METHANE-Subgrade 9/6/2024 Corrections Issued ARAM AVEDISIAN
Excavation/Setback/Form/Re-Bar 9/9/2024 Partial Approval ARAM AVEDISIAN
METHANE-Subgrade 9/9/2024 Approved ARAM AVEDISIAN
Excavation/Setback/Form/Re-Bar 9/17/2024 Partial Approval ASHLEY THOMPSON
Deputy Shotcrete 9/20/2024 Conditional Approval MICHAEL PELHAM
Floor/Roof Diaphrgm/Shear Wall 11/25/2024 Partial Approval SEAN HAUPT
Floor/Roof Diaphrgm/Shear Wall 12/10/2024 Partial Approval ARAM AVEDISIAN
Floor/Roof Diaphrgm/Shear Wall 1/2/2025 Corrections Issued ASHLEY THOMPSON
Deputy Steel/Welding 1/6/2025 No Access for Inspection KENNETH NAGLE
Sewer 1/17/2025 Approved BOBBY KEY
Floor/Roof Diaphrgm/Shear Wall 1/22/2025 Corrections Issued ARAM AVEDISIAN
Deputy Wood Construction 1/24/2025 Conditional Approval MICHAEL PELHAM
Floor/Roof Diaphrgm/Shear Wall 2/3/2025 Conditional Approval EVAN COOPER
ELECTRICAL-Rough 3/17/2025 Corrections Issued ASHLEY THOMPSON
METHANE-Rough 3/25/2025 Approved ARAM AVEDISIAN
PLUMBING-Rough 3/25/2025 Corrections Issued ARAM AVEDISIAN
ELECTRICAL-Rough 4/23/2025 Not Ready for Inspection EVAN COOPER
HVAC-Rough 4/30/2025 Corrections Issued EVAN COOPER
ELECTRICAL-Rough 5/1/2025 Approved MEL KHACHATOURIAN
HVAC-Rough 5/6/2025 Approved MEL KHACHATOURIAN
PLUMBING-Rough 6/2/2025 Approved EVAN COOPER
BUILDING-Rough-Frame 7/3/2025 Not Ready for Inspection ASHLEY THOMPSON
Green Building Rough 7/3/2025 Not Ready for Inspection ASHLEY THOMPSON
Interior/Exterior Lathing 7/3/2025 Partial Approval ASHLEY THOMPSON
Shower Pan 7/3/2025 Not Ready for Inspection ASHLEY THOMPSON
Verify Sprinkler Sign Off 7/3/2025 Approved ASHLEY THOMPSON
BUILDING-Rough-Frame 7/17/2025 Approved EVAN COOPER
Green Building Rough 7/17/2025 Approved EVAN COOPER
Shower Pan 7/28/2025 Corrections Issued ASHLEY THOMPSON
Insulation 8/19/2025 Corrections Issued ASHLEY THOMPSON
Shower Pan 8/19/2025 Not Ready for Inspection ASHLEY THOMPSON
Insulation 8/21/2025 Approved ASHLEY THOMPSON
Shower Pan 8/21/2025 Approved ASHLEY THOMPSON
Drywall Nailing 9/2/2025 Approved ASHLEY THOMPSON
Interior/Exterior Lathing 9/8/2025 Approved ASHLEY THOMPSON
HVAC-Final 6/24/2026 Corrections Issued ASHLEY THOMPSON
HVAC-Final 7/6/2026 Approved ASHLEY THOMPSON
ELECTRICAL-Final 7/7/2026 Corrections Issued MORRIS JACKSON
ELECTRICAL-Final 7/15/2026 Approved ASHLEY THOMPSON
PLUMBING-Final 7/15/2026 Approved ASHLEY THOMPSON