Work Description
Eplan. Convert (E) Detached garage into an ADU and addition to ADU to build a 617 sf ADU. PER CA Govt. Code 65852.2(e)(1)(B) and applicable part2 of LAMC 12.22 A.33(c)-(d), (g)
Permit Issued
Issued on 11/21/2023
Issuing Office
Current Status
CofO Issued on 7/19/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/16/2023 APPLICANT
Assigned to Plan Check Engineer 8/21/2023 ALFREDO JARA
Corrections Issued 8/21/2023 ALFREDO JARA
Plan Check Approved 10/29/2023 ALFREDO JARA
Issued 11/21/2023 APPLICANT
CofO in Progress 7/10/2024 JENNIFER RABUCHIN
Permit Finaled 7/19/2024 RUBEN SALAS
Permit Finaled 7/19/2024 RUBEN SALAS
CofO Issued 7/19/2024 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 9/28/2023 COLIN LOREDO
Eng Process Fee Ord 176,300 Cleared 9/28/2023 COLIN LOREDO
Roof/Waste drainage to street Cleared 9/28/2023 COLIN LOREDO
Sewer availability Cleared 9/28/2023 COLIN LOREDO

Contact Information

Contractor Owner-Builder       ,
Engineer Babapirzadeh,, Ghazal; Lic. No.: C90480 7270 HILLSIDE AVE   APT 306    LOS ANGELES, CA 90046

Inspector Information

JOHN COLEMAN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI
JENNIFER RABUCHIN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 3/28/2024 Partial Inspection JENNIFER RABUCHIN
Pre-Inspection 3/28/2024 Approved JENNIFER RABUCHIN
Deputy Drilled-In Anchors 4/2/2024 Partial Approval JENNIFER RABUCHIN
PLUMBING-Rough 4/2/2024 Partial Approval JENNIFER RABUCHIN
Excavation/Setback/Form/Re-Bar 4/4/2024 Approved JENNIFER RABUCHIN
Footing/Foundation/Slab 4/4/2024 Approved JENNIFER RABUCHIN
BUILDING-Rough-Frame 4/25/2024 Approved JENNIFER RABUCHIN
ELECTRICAL-Rough 4/25/2024 Approved JENNIFER RABUCHIN
HVAC-Rough 4/25/2024 Not Ready for Inspection JENNIFER RABUCHIN
PLUMBING-Rough 4/25/2024 Partial Approval JENNIFER RABUCHIN
HVAC-Rough 4/30/2024 Partial Approval JENNIFER RABUCHIN
Interior/Exterior Lathing 4/30/2024 Approved JENNIFER RABUCHIN
Insulation 5/3/2024 Approved LEONARD ROSS II
Drywall Nailing 5/23/2024 Approved SALVADOR MARTINEZ
Shower Pan 5/23/2024 Not Ready for Inspection SALVADOR MARTINEZ
Interior/Exterior Lathing 6/24/2024 Approved JENNIFER RABUCHIN
Sewer 6/24/2024 Approved JENNIFER RABUCHIN
Underground Mechanical 6/24/2024 Corrections Issued JENNIFER RABUCHIN
ELECTRICAL-Final 7/3/2024 Approved JENNIFER RABUCHIN
Final 7/3/2024 OK to Issue CofO JENNIFER RABUCHIN
Green Building Final 7/3/2024 Approved JENNIFER RABUCHIN
HVAC-Final 7/3/2024 Approved JENNIFER RABUCHIN
PLUMBING-Final 7/3/2024 Approved JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 7/3/2024 SGSOV Approved JENNIFER RABUCHIN
Service/Power Release 7/3/2024 Approved JENNIFER RABUCHIN
Smoke Detectors 7/3/2024 Approved JENNIFER RABUCHIN