14813 W HART ST 91405

Certificate Information: 14813 W HART ST 91405

Application / Permit
23014-20000-03113
Plan Check / Job No.
B23VN10467
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) 18' X 20' DETACHED GARAGE WITH 18' X 14' ATTACHED STORAGE AND (N) 18' X 6' ADDITION TO (N) ACCESSORY DWELLING UNIT PER LAMC 12.22.A.33(c) AND (d). WORK TO BE DONE PER ENGINEER DESIGN.
Permit Issued
Issued on 5/6/2024
Issuing Office
Current Status
CofO Issued on 1/15/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/6/2023 APPLICANT
Assigned to Plan Check Engineer 9/12/2023 MADISON ODELL
Corrections Issued 9/13/2023 MADISON ODELL
Applicant returned to address corrections 4/18/2024 ALEC MOUSAKHANIAN
Applicant returned to address corrections 4/24/2024 MADISON ODELL
Plan Check Approved 5/3/2024 ALEC MOUSAKHANIAN
Issued 5/6/2024 APPLICANT
CofO in Progress 12/2/2024 RYAN SALAZAR
Permit Finaled 1/15/2025 RUBEN SALAS
CofO Issued 1/15/2025 RUBEN SALAS
Permit Finaled 1/15/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 3/4/2024 EDGAR ALCARAZ
Roof/Waste drainage to street Cleared 3/4/2024 EDGAR ALCARAZ
Sewer availability Cleared 3/13/2024 EDGAR ALCARAZ
Construction near power lines Cleared 3/15/2024 TINA MIRANDA
Construction within easement Cleared 3/15/2024 TINA MIRANDA
Eng Process Fee Ord 176,300 Cleared 3/20/2024 EDGAR ALCARAZ

Contact Information

Contractor Owner-Builder       ,
Engineer Pinzon,, Eduardo Andres; Lic. No.: NA74869       ,

Inspector Information

JOSE AVILA, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI
VINCENT HANLEY, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 5/7/2024 Conditional Approval ROBERT GOLD
Footing/Foundation/Slab 5/9/2024 Corrections Issued CHRISTOPHE COCHRAN
Deputy Drilled-In Anchors 6/13/2024 Conditional Approval ROBERT GOLD
Footing/Foundation/Slab 6/20/2024 Approved RYAN SALAZAR
Floor/Roof Diaphrgm/Shear Wall 6/27/2024 Partial Approval RYAN SALAZAR
PLUMBING-Rough 6/27/2024 Partial Approval RYAN SALAZAR
Floor/Roof Diaphrgm/Shear Wall 6/28/2024 Partial Approval RYAN SALAZAR
Insulation 6/28/2024 Partial Approval RYAN SALAZAR
BUILDING-Rough-Frame 7/8/2024 Approved RYAN SALAZAR
ELECTRICAL-Rough 7/8/2024 Approved RYAN SALAZAR
Floor/Roof Diaphrgm/Shear Wall 7/8/2024 Approved RYAN SALAZAR
HVAC-Rough 7/8/2024 Approved RYAN SALAZAR
PLUMBING-Rough 7/8/2024 Approved RYAN SALAZAR
Floor/Roof Diaphrgm/Shear Wall 7/15/2024 Approved RYAN SALAZAR
Insulation 7/15/2024 Approved RYAN SALAZAR
Drywall Nailing 7/19/2024 Approved DAVID ANDERSON
Interior/Exterior Lathing 7/19/2024 Approved DAVID ANDERSON
Final 11/26/2024 OK to Issue CofO RYAN SALAZAR
SGSOV-Seismic Gas S/O Valve 11/26/2024 SGSOV Approved RYAN SALAZAR
Service/Power Release 11/26/2024 Approved RYAN SALAZAR
Smoke Detectors 11/26/2024 Approved RYAN SALAZAR
Special/Order Compliance 12/30/2024 Corrections Issued RYAN SALAZAR