16826-16828 W BIRCHER ST 91344

Certificate Information: 16826-16828 W BIRCHER ST 91344

Application / Permit
23014-20000-03052
Plan Check / Job No.
B23VN10201
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
*EPLAN* ADD NEW ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d) ON SECOND FLOOR; ADD NEW BEDROOM TO REAR OF EXISTING DWELLING; INTERIOR REMODEL
Permit Issued
Issued on 5/8/2024
Issuing Office
Current Status
Issued on 5/8/2024
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 8/1/2023 APPLICANT
Assigned to Plan Check Engineer 8/17/2023 SELLA BENYAMIN
Corrections Issued 8/22/2023 SELLA BENYAMIN
Quality Review Completed 8/25/2023 STEVEN KIM
Plan Check Approved 4/19/2024 SELLA BENYAMIN
Issued 5/8/2024 APPLICANT

Permit Application Clearance Information

Address approval Cleared 11/16/2023 CARLOS RAMIREZ
Eng Process Fee Ord 176,300 Cleared 11/20/2023 CARLOS RAMIREZ
Sewer availability Cleared 11/20/2023 CARLOS RAMIREZ
Low Impact Development (LID) Cleared 2/15/2024 PATRICK LOPEZ
Grading Pre-Inspection Cleared 2/16/2024 MICHAEL TEMPLE
Roof/Waste drainage to street Cleared 2/29/2024 CARLOS RAMIREZ
GPI Written Notices Cleared 4/19/2024 SELLA BENYAMIN

Contact Information

Contractor Owner-Builder       ,
Engineer Santos,, Michael; Lic. No.: C77657 16202 ORION AVE      CHINO, CA 91708

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 6/21/2024 Conditional Approval JAVIER RAMOS JR
Excavation/Setback/Form/Re-Bar 6/25/2024 Partial Approval JAVIER RAMOS JR
Pre-Inspection 6/25/2024 Approved JAVIER RAMOS JR
Floor/Roof Diaphrgm/Shear Wall 8/5/2024 Partial Approval JAVIER RAMOS JR
BUILDING-Rough-Frame 10/28/2024 Partial Approval KEVIN BERBERYAN
ELECTRICAL-Rough 10/28/2024 Corrections Issued KEVIN BERBERYAN
HVAC-Rough 10/28/2024 Corrections Issued KEVIN BERBERYAN
PLUMBING-Rough 10/28/2024 Corrections Issued KEVIN BERBERYAN
ELECTRICAL-Rough 11/6/2024 Corrections Issued JAVIER RAMOS JR
HVAC-Rough 11/6/2024 Corrections Issued JAVIER RAMOS JR
PLUMBING-Rough 11/6/2024 Not Ready for Inspection JAVIER RAMOS JR
ELECTRICAL-Rough 11/13/2024 Approved JAVIER RAMOS JR
Floor/Roof Diaphrgm/Shear Wall 11/13/2024 Approved JAVIER RAMOS JR
Interior/Exterior Lathing 11/13/2024 Partial Approval JAVIER RAMOS JR
PLUMBING-Rough 11/13/2024 Approved JAVIER RAMOS JR
Shower Pan 11/13/2024 Approved JAVIER RAMOS JR
Insulation 11/19/2024 Corrections Issued JAVIER RAMOS JR
Insulation 11/25/2024 Approved LOUIS ESCOTO
Drywall Nailing 12/4/2024 Approved LOUIS ESCOTO
BUILDING-Rough-Frame 4/23/2025 Not Ready for Inspection CHRISTOPHER ROJAS
Final 4/23/2025 Corrections Issued CHRISTOPHER ROJAS
Footing/Foundation/Slab 4/23/2025 Corrections Issued CHRISTOPHER ROJAS
SGSOV-Seismic Gas S/O Valve 4/23/2025 SGSOV Not Ready CHRISTOPHER ROJAS
Smoke Detectors 4/23/2025 Not Ready for Inspection CHRISTOPHER ROJAS
BUILDING-Rough-Frame 4/30/2025 Not Ready for Inspection CHRISTOPHER ROJAS
Final 4/30/2025 Corrections Issued CHRISTOPHER ROJAS
Footing/Foundation/Slab 4/30/2025 Approved CHRISTOPHER ROJAS
SGSOV-Seismic Gas S/O Valve 4/30/2025 SGSOV Not Ready CHRISTOPHER ROJAS
Smoke Detectors 4/30/2025 Approved CHRISTOPHER ROJAS
ELECTRICAL-Final 6/2/2025 Corrections Issued JAVIER RAMOS JR
Final 6/2/2025 Corrections Issued JAVIER RAMOS JR
Green Building Final 6/2/2025 Approved JAVIER RAMOS JR
HVAC-Final 6/2/2025 Approved JAVIER RAMOS JR
PLUMBING-Final 6/2/2025 Approved JAVIER RAMOS JR
SGSOV-Seismic Gas S/O Valve 6/2/2025 SGSOV Approved JAVIER RAMOS JR
ELECTRICAL-Final 6/6/2025 Approved CHRISTOPHER ROJAS