8222 W OSWEGO ST 91040

Certificate Information: 8222 W OSWEGO ST 91040

Application / Permit
23014-20000-03048
Plan Check / Job No.
B23VN10185
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
19'-6" x 9'-3" ADDITION TO THE (E) SFD. WORK DONE PER WFPP.
Permit Issued
Issued on 10/10/2023
Issuing Office
Valley
Current Status
CofO Issued on 5/10/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/31/2023 APPLICANT
Assigned to Plan Check Engineer 8/4/2023 SERGIO MUNIZ
Corrections Issued 8/5/2023 SERGIO MUNIZ
Building Plans Picked Up 9/8/2023 APPLICANT
Plan Check Approved 9/27/2023 MIROOSH KHACHATOORIAN
Issued 10/10/2023 APPLICANT
CofO in Progress 5/8/2024 WILLIAM WREN
Permit Finaled 5/10/2024 RUBEN SALAS
Permit Finaled 5/10/2024 RUBEN SALAS
CofO Issued 5/10/2024 RUBEN SALAS

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 9/11/2023 DAGOVERTO GUERRERO
Sewer availability Cleared 9/11/2023 DAGOVERTO GUERRERO
Eng Process Fee Ord 176,300 Cleared 9/13/2023 DAGOVERTO GUERRERO
Grading Pre-Inspection Cleared 9/25/2023 ROBERT HUGHES

Contact Information

Contractor Dhs Ventures Inc; Lic. No.: 1047699-B 18425 BURBANK BLVD STE 713      LOS ANGELES, CA 91356

Inspector Information

NICHOLAS TROWBRIDGE, (818) 374-1174 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 10/23/2023 Conditional Approval JUAN VALENZUELA
Footing/Foundation/Slab 10/23/2023 No Access for Inspection WILLIAM WREN
Footing/Foundation/Slab 10/27/2023 Approved WILLIAM WREN
Floor/Roof Diaphrgm/Shear Wall 11/14/2023 Corrections Issued DAVID MATSON
PLUMBING-Rough 11/14/2023 Partial Approval DAVID MATSON
BUILDING-Rough-Frame 11/28/2023 Partial Approval WILLIAM WREN
Floor/Roof Diaphrgm/Shear Wall 12/4/2023 Corrections Issued WILLIAM WREN
Insulation 12/4/2023 Partial Approval WILLIAM WREN
Deputy Wood Construction 12/6/2023 Conditional Approval DAVID MATSON
Floor/Roof Diaphrgm/Shear Wall 12/6/2023 Partial Approval WILLIAM WREN
Floor/Roof Diaphrgm/Shear Wall 12/20/2023 Approved WILLIAM WREN
ELECTRICAL-Rough 12/27/2023 Approved WILLIAM WREN
PLUMBING-Rough 12/27/2023 Approved WILLIAM WREN
BUILDING-Rough-Frame 12/29/2023 Approved WILLIAM WREN
Insulation 12/29/2023 Approved WILLIAM WREN
Drywall Nailing 1/12/2024 Approved WILLIAM WREN
Interior/Exterior Lathing 1/29/2024 Approved MATTHEW NELSON
Shower Pan 1/29/2024 Approved MATTHEW NELSON
BUILDING-Rough-Frame 3/7/2024 Approved WILLIAM WREN
Final 3/7/2024 Corrections Issued WILLIAM WREN
Green Building Final 3/7/2024 Not Ready for Inspection WILLIAM WREN
Green Building Rough 3/7/2024 Approved WILLIAM WREN
SGSOV-Seismic Gas S/O Valve 3/7/2024 SGSOV Approved WILLIAM WREN
Smoke Detectors 3/7/2024 Not Ready for Inspection WILLIAM WREN
Final 3/22/2024 Corrections Issued WILLIAM WREN
Green Building Final 3/22/2024 Not Ready for Inspection WILLIAM WREN
Smoke Detectors 3/22/2024 Approved WILLIAM WREN
Final 4/12/2024 OK to Issue CofO WILLIAM WREN
Green Building Final 4/12/2024 Approved WILLIAM WREN