7469-7471 N POMELO DR 91304

Certificate Information: 7469-7471 N POMELO DR 91304

Application / Permit
23014-20000-03030
Plan Check / Job No.
B23VN10141
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
EPLAN NEW 24' 6 " X 22' 10 " ADDITION TO THE EXISTING SFD, AND NEW SECOND STORY ADU 20' 1" X 24' 6" ABOVE (E) GARAGE PER LAMC 12.22 A.33 (c) AND (e). ALL WORK DONE PER ENGINEERING.
Permit Issued
Issued on 10/23/2023
Issuing Office
Current Status
CofO Issued on 10/4/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/31/2023 APPLICANT
Assigned to Plan Check Engineer 8/17/2023 NAREG ATARIAN
Corrections Issued 8/23/2023 NAREG ATARIAN
Quality Review Completed 8/24/2023 OMID HEDAYAT
Applicant returned to address corrections 10/10/2023 NAREG ATARIAN
Applicant returned to address corrections 10/19/2023 NAREG ATARIAN
Plan Check Approved 10/23/2023 NAREG ATARIAN
Issued 10/23/2023 APPLICANT
CofO in Progress 8/27/2024 CHRIS CHRISTENSEN
Permit Finaled 10/4/2024 JOHN JANSON
CofO Issued 10/4/2024 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 9/7/2023 ROMAN GUTIERREZ
Eng Process Fee Ord 176,300 Cleared 9/11/2023 ROMAN GUTIERREZ
Sewer availability Cleared 9/12/2023 ROMAN GUTIERREZ
Low Impact Development (LID) Cleared 9/15/2023 ROGELIO CORTES
Roof/Waste drainage to street Cleared 9/21/2023 ROMAN GUTIERREZ
GPI Written Notices Cleared 10/10/2023 NAREG ATARIAN
Grading Pre-Inspection Cleared 10/10/2023 NAREG ATARIAN

Contact Information

Contractor Flip It Homes Inc; Lic. No.: 1043456-B       ,
Engineer Nagovitsyn,, Evgeny; Lic. No.: C93527 17436 ARMINTA ST      NORTHRIDGE, CA 91325

Inspector Information

JEFFREY HARTLINE, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI
CHRIS CHRISTENSEN, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 11/22/2023 Not Ready for Inspection CHRIS CHRISTENSEN
Underground Mechanical 11/22/2023 Partial Approval CHRIS CHRISTENSEN
Footing/Foundation/Slab 11/29/2023 Approved JEFFREY HARTLINE
Excavation/Setback/Form/Re-Bar 12/14/2023 Approved JEFFREY HARTLINE
Deputy Wood Construction 1/10/2024 Conditional Approval CHRIS CHRISTENSEN
Floor/Roof Diaphrgm/Shear Wall 1/18/2024 Partial Approval JEFFREY HARTLINE
Pre-Inspection 1/30/2024 Partial Approval JEFFREY HARTLINE
BUILDING-Rough-Frame 2/26/2024 Approved JEFFREY HARTLINE
ELECTRICAL-Rough 2/26/2024 Partial Approval JEFFREY HARTLINE
Green Building Rough 2/26/2024 Approved JEFFREY HARTLINE
HVAC-Rough 2/26/2024 Approved JEFFREY HARTLINE
Interior/Exterior Lathing 2/26/2024 Partial Approval JEFFREY HARTLINE
PLUMBING-Rough 2/26/2024 Approved JEFFREY HARTLINE
Insulation 3/1/2024 Corrections Issued JEFFREY HARTLINE
Shower Pan 3/1/2024 Approved JEFFREY HARTLINE
Insulation 3/5/2024 Approved JEFFREY HARTLINE
Drywall Nailing 3/19/2024 Partial Approval JEFFREY HARTLINE
Interior/Exterior Lathing 3/19/2024 Partial Approval JEFFREY HARTLINE
Drywall Nailing 7/23/2024 Approved CHRIS CHRISTENSEN
ELECTRICAL-Final 7/23/2024 Approved CHRIS CHRISTENSEN
Final 7/23/2024 Corrections Issued CHRIS CHRISTENSEN
Green Building Final 7/23/2024 Not Ready for Inspection CHRIS CHRISTENSEN
HVAC-Final 7/23/2024 Approved CHRIS CHRISTENSEN
PLUMBING-Final 7/23/2024 Approved CHRIS CHRISTENSEN
SGSOV-Seismic Gas S/O Valve 7/23/2024 SGSOV Approved CHRIS CHRISTENSEN
Smoke Detectors 7/23/2024 Corrections Issued CHRIS CHRISTENSEN
Final 7/31/2024 Not Ready for Inspection CHRIS CHRISTENSEN
Green Building Final 7/31/2024 Approved CHRIS CHRISTENSEN
Smoke Detectors 7/31/2024 Approved CHRIS CHRISTENSEN
Final 8/26/2024 OK to Issue CofO CHRIS CHRISTENSEN