15437 W LEMAC ST 91406
Certificate Information: 15437 W LEMAC ST 91406
- Application / Permit
- 23014-20000-03027
- Plan Check / Job No.
- B23VN10138
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- EPLAN NEW ADDITION AND MAJOR REMODELING TO (E) 1-STORY SFD
- Permit Issued
- Issued on 1/4/2024
- Issuing Office
- Current Status
- Issued on 1/4/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 8/3/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 8/17/2023 | MAHNAZ NOURHASHEMI |
| Corrections Issued | 8/25/2023 | MAHNAZ NOURHASHEMI |
| Quality Review Completed | 8/29/2023 | TU HUA |
| Plan Check Approved | 10/19/2023 | MAHNAZ NOURHASHEMI |
| Issued | 1/4/2024 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 9/6/2023 | COLIN LOREDO |
| Eng Process Fee Ord 176,300 | Cleared | 9/6/2023 | COLIN LOREDO |
| Low Impact Development (LID) | Cleared | 10/6/2023 | MELINEH AGHAKHABIAN |
| Roof/Waste drainage to street | Cleared | 10/7/2023 | COLIN LOREDO |
| Sewer availability | Cleared | 10/11/2023 | COLIN LOREDO |
Contact Information
| Architect | Hefner,, Charles David; Lic. No.: C23963 | 6320 VAN NUYS BOULEVARD #225 VAN NUYS, CA 91401 |
| Contractor | South Cal Construction Inc; Lic. No.: 756435-B | , |
Inspector Information
| OGANES TARAKHCHYAN, (818) 374-1162 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 1/5/2024 | Corrections Issued | CHRISTOPHER ROJAS |
| Footing/Foundation/Slab | 1/12/2024 | Approved | CHRISTOPHER ROJAS |
| PLUMBING-Rough | 2/22/2024 | Partial Approval | CHRISTOPHER ROJAS |
| Deputy Drilled-In Anchors | 5/2/2024 | Conditional Approval | DAVID MATSON |
| Floor/Roof Diaphrgm/Shear Wall | 5/17/2024 | Partial Approval | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 6/11/2024 | Approved | VINCENT HANLEY |
| HVAC-Rough | 6/11/2024 | Approved | VINCENT HANLEY |
| BUILDING-Rough-Frame | 6/18/2024 | Approved | VINCENT HANLEY |
| ELECTRICAL-Rough | 6/18/2024 | Approved | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 6/18/2024 | Approved | VINCENT HANLEY |
| Gas Test | 6/18/2024 | Approved | VINCENT HANLEY |
| Green Building Rough | 6/18/2024 | Approved | VINCENT HANLEY |
| Interior/Exterior Lathing | 6/18/2024 | Partial Approval | VINCENT HANLEY |
| PLUMBING-Rough | 6/18/2024 | Approved | VINCENT HANLEY |
| Verify Sprinkler Sign Off | 6/18/2024 | Approved | VINCENT HANLEY |
| Insulation | 6/27/2024 | Approved | VINCENT HANLEY |
| Drywall Nailing | 7/8/2024 | Approved | VINCENT HANLEY |
| Interior/Exterior Lathing | 7/8/2024 | Approved | VINCENT HANLEY |
| Shower Pan | 7/8/2024 | Approved | VINCENT HANLEY |
| Gas Test | 1/5/2026 | Approved | OGANES TARAKHCHYAN |