8836-8838 N KATHERINE AVE 91402
Certificate Information: 8836-8838 N KATHERINE AVE 91402
- Application / Permit
- 23014-20000-03021
- Plan Check / Job No.
- B23VN10112
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 14'-11" X 18' ADDITION TO AND CONVERT ATTACHED GARAGE TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (e). COMPLY WITH DEPARTMENT ORDER effective date 08/05/2022. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE
- Permit Issued
- Issued on 8/30/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 4/17/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/28/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 8/4/2023 | JEROME MAGAT PALMA |
| Corrections Issued | 8/5/2023 | JEROME MAGAT PALMA |
| Building Plans Picked Up | 8/14/2023 | APPLICANT |
| Plan Check Approved | 8/28/2023 | MIROOSH KHACHATOORIAN |
| Issued | 8/30/2023 | APPLICANT |
| CofO in Progress | 4/9/2024 | KIRK SANDERS |
| Permit Finaled | 4/17/2024 | RUBEN SALAS |
| CofO Issued | 4/17/2024 | RUBEN SALAS |
| Permit Finaled | 4/17/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 8/23/2023 | MEGAN GODINEZ |
| Eng Process Fee Ord 176,300 | Cleared | 8/23/2023 | MEGAN GODINEZ |
| Sewer availability | Cleared | 8/23/2023 | MEGAN GODINEZ |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| OGANES TARAKHCHYAN, (818) 374-1162 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 9/12/2023 | Partial Inspection | DAVID MATSON |
| PLUMBING-Rough | 9/25/2023 | Partial Approval | GREGG CUMMINGS |
| Underground Mechanical | 9/25/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| Excavation/Setback/Form/Re-Bar | 9/28/2023 | Corrections Issued | GREGG CUMMINGS |
| Reinforced Concrete Frame | 9/28/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| Excavation/Setback/Form/Re-Bar | 10/3/2023 | Approved | GREGG CUMMINGS |
| Footing/Foundation/Slab | 10/3/2023 | Approved | GREGG CUMMINGS |
| ELECTRICAL-Rough | 10/16/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| Floor/Roof Diaphrgm/Shear Wall | 10/16/2023 | Partial Approval | GREGG CUMMINGS |
| PLUMBING-Rough | 10/16/2023 | Approved | GREGG CUMMINGS |
| ELECTRICAL-Rough | 10/25/2023 | Approved | JUAN VALENZUELA |
| HVAC-Rough | 10/25/2023 | Approved | JUAN VALENZUELA |
| Interior/Exterior Lathing | 10/25/2023 | Partial Approval | JUAN VALENZUELA |
| Shower Pan | 10/25/2023 | Not Ready for Inspection | JUAN VALENZUELA |
| Insulation | 10/31/2023 | Corrections Issued | GREGG CUMMINGS |
| Sewer | 11/13/2023 | Approved | GREGG CUMMINGS |
| Underground Mechanical | 11/13/2023 | Partial Approval | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 11/20/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| Green Building Rough | 11/20/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| Reinforced Concrete Frame | 11/20/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 11/27/2023 | Approved | DAVID ANDERSON |
| Green Building Rough | 11/27/2023 | Approved | DAVID ANDERSON |
| Insulation | 11/27/2023 | Approved | DAVID ANDERSON |
| Shower Pan | 11/27/2023 | Approved | DAVID ANDERSON |
| Drywall Nailing | 11/28/2023 | Approved | GREGG CUMMINGS |
| Interior/Exterior Lathing | 11/28/2023 | Partial Approval | GREGG CUMMINGS |
| Final | 1/25/2024 | No Access for Inspection | GREGG CUMMINGS |
| Green Building Final | 1/25/2024 | No Access for Inspection | GREGG CUMMINGS |
| SGSOV-Seismic Gas S/O Valve | 1/25/2024 | SGSOV Not Ready | GREGG CUMMINGS |
| Smoke Detectors | 1/25/2024 | No Access for Inspection | GREGG CUMMINGS |
| Final | 1/29/2024 | Not Ready for Inspection | GREGG CUMMINGS |
| Green Building Final | 1/29/2024 | Not Ready for Inspection | GREGG CUMMINGS |
| SGSOV-Seismic Gas S/O Valve | 1/29/2024 | SGSOV Not Ready | GREGG CUMMINGS |
| Smoke Detectors | 1/29/2024 | Not Ready for Inspection | GREGG CUMMINGS |
| SGSOV-Seismic Gas S/O Valve | 2/7/2024 | SGSOV Not Ready | GREGG CUMMINGS |
| Final | 2/8/2024 | Corrections Issued | GREGG CUMMINGS |
| Final | 3/26/2024 | Not Ready for Inspection | GREGG CUMMINGS |
| Green Building Final | 3/26/2024 | Not Ready for Inspection | GREGG CUMMINGS |
| SGSOV-Seismic Gas S/O Valve | 3/26/2024 | SGSOV Not Ready | GREGG CUMMINGS |
| Smoke Detectors | 3/26/2024 | Not Ready for Inspection | GREGG CUMMINGS |
| Final | 4/8/2024 | OK to Issue CofO | KIRK SANDERS |
| Green Building Final | 4/8/2024 | Approved | KIRK SANDERS |
| SGSOV-Seismic Gas S/O Valve | 4/8/2024 | SGSOV Approved | KIRK SANDERS |
| Service/Power Release | 4/8/2024 | Approved | KIRK SANDERS |
| Smoke Detectors | 4/8/2024 | Approved | KIRK SANDERS |