5501 N SIMPSON AVE 91607

Certificate Information: 5501 N SIMPSON AVE 91607

Application / Permit
23014-20000-03016
Plan Check / Job No.
B23VN10085
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
eplan: INTERIOR REMODEL AND (N) 499 SQ.FT. ADDITION TO AN (E) SFR, ALL WORK PER ENG.
Permit Issued
Issued on 1/9/2024
Issuing Office
Current Status
CofO Issued on 2/4/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/2/2023 APPLICANT
Assigned to Plan Check Engineer 8/8/2023 LUISANGEL VALENZUELA
Corrections Issued 8/8/2023 LUISANGEL VALENZUELA
Applicant returned to address corrections 12/13/2023 LUISANGEL VALENZUELA
Applicant returned to address corrections 12/19/2023 LUISANGEL VALENZUELA
Plan Check Approved 12/22/2023 LUISANGEL VALENZUELA
Issued 1/9/2024 APPLICANT
CofO in Progress 1/22/2025 CHRISTOPHER ROJAS
Permit Finaled 2/4/2025 RUBEN SALAS
CofO Issued 2/4/2025 RUBEN SALAS
Permit Finaled 2/4/2025 RUBEN SALAS

Permit Application Clearance Information

Specific Plan Cleared 8/20/2023 JOANNA MARROQUIN
Specific Plan Cleared 8/20/2023 JOANNA MARROQUIN
ZI Cleared 8/20/2023 JOANNA MARROQUIN
ZI Cleared 8/20/2023 JOANNA MARROQUIN
Sewer availability Cleared 8/22/2023 NIKKI ZULUETA
Eng Process Fee Ord 176,300 Cleared 8/25/2023 NIKKI ZULUETA
Low Impact Development (LID) Cleared 11/29/2023 MELINEH AGHAKHABIAN
Roof/Waste drainage to street Cleared 12/11/2023 NIKKI ZULUETA

Contact Information

Contractor California Construction Center Inc; Lic. No.: 891847-B 99 SOUTH ALMADEN BOULEVARD   SUITE 600    SAN JOSE, CA 95113
Engineer Sivushenka,, Mikita; Lic. No.: C87698 22814 DOLOROSA ST      WOODLAND HILLS, CA 91367

Inspector Information

JAVIER RAMOS JR, (818) 374-1163 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 2/23/2024 Approved KIRK SANDERS
Floor/Roof Diaphrgm/Shear Wall 3/29/2024 Corrections Issued CHRISTOPHER ROJAS
PLUMBING-Rough 3/29/2024 Partial Approval CHRISTOPHER ROJAS
BUILDING-Rough-Frame 4/2/2024 Partial Approval CHRISTOPHER ROJAS
Floor/Roof Diaphrgm/Shear Wall 4/4/2024 Partial Approval CHRISTOPHER ROJAS
BUILDING-Rough-Frame 5/9/2024 Corrections Issued CHRISTOPHER ROJAS
Floor/Roof Diaphrgm/Shear Wall 5/9/2024 Partial Approval CHRISTOPHER ROJAS
Deputy Wood Construction 5/28/2024 Conditional Approval DAVID MATSON
ELECTRICAL-Final 6/28/2024 Corrections Issued VINCENT HANLEY
ELECTRICAL-Rough 6/28/2024 Approved VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 6/28/2024 Approved VINCENT HANLEY
HVAC-Rough 6/28/2024 Corrections Issued VINCENT HANLEY
MERV13>=Rough 6/28/2024 Corrections Issued VINCENT HANLEY
PLUMBING-Rough 6/28/2024 Corrections Issued VINCENT HANLEY
BUILDING-Rough-Frame 7/9/2024 Corrections Issued CHRISTOPHER ROJAS
ELECTRICAL-Rough 7/9/2024 Not Ready for Inspection CHRISTOPHER ROJAS
HVAC-Rough 7/9/2024 Not Ready for Inspection CHRISTOPHER ROJAS
MERV13>=Rough 7/9/2024 Approved CHRISTOPHER ROJAS
PLUMBING-Rough 7/9/2024 Approved CHRISTOPHER ROJAS
BUILDING-Rough-Frame 7/12/2024 Approved CHRISTOPHER ROJAS
ELECTRICAL-Rough 7/12/2024 Approved CHRISTOPHER ROJAS
HVAC-Rough 7/12/2024 Approved CHRISTOPHER ROJAS
Interior/Exterior Lathing 7/12/2024 Partial Approval CHRISTOPHER ROJAS
Insulation 7/19/2024 Approved CHRISTOPHER ROJAS
Shower Pan 7/19/2024 Approved CHRISTOPHER ROJAS
Drywall Nailing 7/30/2024 Approved CHRISTOPHER ROJAS
Interior/Exterior Lathing 7/30/2024 Corrections Issued CHRISTOPHER ROJAS
Interior/Exterior Lathing 9/6/2024 Approved CHRISTOPHER ROJAS
ELECTRICAL-Final 12/20/2024 Not Ready for Inspection CHRISTOPHER ROJAS
Final 12/20/2024 Corrections Issued CHRISTOPHER ROJAS
HVAC-Final 12/20/2024 Partial Inspection CHRISTOPHER ROJAS
MERV13>=Final 12/20/2024 Approved CHRISTOPHER ROJAS
PLUMBING-Final 12/20/2024 Partial Inspection CHRISTOPHER ROJAS
SGSOV-Seismic Gas S/O Valve 12/20/2024 SGSOV Not Ready CHRISTOPHER ROJAS
Smoke Detectors 12/20/2024 Partial Inspection CHRISTOPHER ROJAS
ELECTRICAL-Final 12/26/2024 Partial Inspection CHRISTOPHER ROJAS
Final 12/26/2024 Corrections Issued CHRISTOPHER ROJAS
HVAC-Final 12/26/2024 Approved CHRISTOPHER ROJAS
PLUMBING-Final 12/26/2024 Approved CHRISTOPHER ROJAS
SGSOV-Seismic Gas S/O Valve 12/26/2024 SGSOV Approved CHRISTOPHER ROJAS
Smoke Detectors 12/26/2024 Approved CHRISTOPHER ROJAS
Final 1/22/2025 OK to Issue CofO CHRISTOPHER ROJAS