5501 N SIMPSON AVE 91607
Certificate Information: 5501 N SIMPSON AVE 91607
- Application / Permit
- 23014-20000-03016
- Plan Check / Job No.
- B23VN10085
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- eplan: INTERIOR REMODEL AND (N) 499 SQ.FT. ADDITION TO AN (E) SFR, ALL WORK PER ENG.
- Permit Issued
- Issued on 1/9/2024
- Issuing Office
- Current Status
- CofO Issued on 2/4/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/2/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 8/8/2023 | LUISANGEL VALENZUELA |
| Corrections Issued | 8/8/2023 | LUISANGEL VALENZUELA |
| Applicant returned to address corrections | 12/13/2023 | LUISANGEL VALENZUELA |
| Applicant returned to address corrections | 12/19/2023 | LUISANGEL VALENZUELA |
| Plan Check Approved | 12/22/2023 | LUISANGEL VALENZUELA |
| Issued | 1/9/2024 | APPLICANT |
| CofO in Progress | 1/22/2025 | CHRISTOPHER ROJAS |
| Permit Finaled | 2/4/2025 | RUBEN SALAS |
| CofO Issued | 2/4/2025 | RUBEN SALAS |
| Permit Finaled | 2/4/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Specific Plan | Cleared | 8/20/2023 | JOANNA MARROQUIN |
| Specific Plan | Cleared | 8/20/2023 | JOANNA MARROQUIN |
| ZI | Cleared | 8/20/2023 | JOANNA MARROQUIN |
| ZI | Cleared | 8/20/2023 | JOANNA MARROQUIN |
| Sewer availability | Cleared | 8/22/2023 | NIKKI ZULUETA |
| Eng Process Fee Ord 176,300 | Cleared | 8/25/2023 | NIKKI ZULUETA |
| Low Impact Development (LID) | Cleared | 11/29/2023 | MELINEH AGHAKHABIAN |
| Roof/Waste drainage to street | Cleared | 12/11/2023 | NIKKI ZULUETA |
Contact Information
| Contractor | California Construction Center Inc; Lic. No.: 891847-B | 99 SOUTH ALMADEN BOULEVARD SUITE 600 SAN JOSE, CA 95113 |
| Engineer | Sivushenka,, Mikita; Lic. No.: C87698 | 22814 DOLOROSA ST WOODLAND HILLS, CA 91367 |
Inspector Information
| JAVIER RAMOS JR, (818) 374-1163 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 2/23/2024 | Approved | KIRK SANDERS |
| Floor/Roof Diaphrgm/Shear Wall | 3/29/2024 | Corrections Issued | CHRISTOPHER ROJAS |
| PLUMBING-Rough | 3/29/2024 | Partial Approval | CHRISTOPHER ROJAS |
| BUILDING-Rough-Frame | 4/2/2024 | Partial Approval | CHRISTOPHER ROJAS |
| Floor/Roof Diaphrgm/Shear Wall | 4/4/2024 | Partial Approval | CHRISTOPHER ROJAS |
| BUILDING-Rough-Frame | 5/9/2024 | Corrections Issued | CHRISTOPHER ROJAS |
| Floor/Roof Diaphrgm/Shear Wall | 5/9/2024 | Partial Approval | CHRISTOPHER ROJAS |
| Deputy Wood Construction | 5/28/2024 | Conditional Approval | DAVID MATSON |
| ELECTRICAL-Final | 6/28/2024 | Corrections Issued | VINCENT HANLEY |
| ELECTRICAL-Rough | 6/28/2024 | Approved | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 6/28/2024 | Approved | VINCENT HANLEY |
| HVAC-Rough | 6/28/2024 | Corrections Issued | VINCENT HANLEY |
| MERV13>=Rough | 6/28/2024 | Corrections Issued | VINCENT HANLEY |
| PLUMBING-Rough | 6/28/2024 | Corrections Issued | VINCENT HANLEY |
| BUILDING-Rough-Frame | 7/9/2024 | Corrections Issued | CHRISTOPHER ROJAS |
| ELECTRICAL-Rough | 7/9/2024 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| HVAC-Rough | 7/9/2024 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| MERV13>=Rough | 7/9/2024 | Approved | CHRISTOPHER ROJAS |
| PLUMBING-Rough | 7/9/2024 | Approved | CHRISTOPHER ROJAS |
| BUILDING-Rough-Frame | 7/12/2024 | Approved | CHRISTOPHER ROJAS |
| ELECTRICAL-Rough | 7/12/2024 | Approved | CHRISTOPHER ROJAS |
| HVAC-Rough | 7/12/2024 | Approved | CHRISTOPHER ROJAS |
| Interior/Exterior Lathing | 7/12/2024 | Partial Approval | CHRISTOPHER ROJAS |
| Insulation | 7/19/2024 | Approved | CHRISTOPHER ROJAS |
| Shower Pan | 7/19/2024 | Approved | CHRISTOPHER ROJAS |
| Drywall Nailing | 7/30/2024 | Approved | CHRISTOPHER ROJAS |
| Interior/Exterior Lathing | 7/30/2024 | Corrections Issued | CHRISTOPHER ROJAS |
| Interior/Exterior Lathing | 9/6/2024 | Approved | CHRISTOPHER ROJAS |
| ELECTRICAL-Final | 12/20/2024 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| Final | 12/20/2024 | Corrections Issued | CHRISTOPHER ROJAS |
| HVAC-Final | 12/20/2024 | Partial Inspection | CHRISTOPHER ROJAS |
| MERV13>=Final | 12/20/2024 | Approved | CHRISTOPHER ROJAS |
| PLUMBING-Final | 12/20/2024 | Partial Inspection | CHRISTOPHER ROJAS |
| SGSOV-Seismic Gas S/O Valve | 12/20/2024 | SGSOV Not Ready | CHRISTOPHER ROJAS |
| Smoke Detectors | 12/20/2024 | Partial Inspection | CHRISTOPHER ROJAS |
| ELECTRICAL-Final | 12/26/2024 | Partial Inspection | CHRISTOPHER ROJAS |
| Final | 12/26/2024 | Corrections Issued | CHRISTOPHER ROJAS |
| HVAC-Final | 12/26/2024 | Approved | CHRISTOPHER ROJAS |
| PLUMBING-Final | 12/26/2024 | Approved | CHRISTOPHER ROJAS |
| SGSOV-Seismic Gas S/O Valve | 12/26/2024 | SGSOV Approved | CHRISTOPHER ROJAS |
| Smoke Detectors | 12/26/2024 | Approved | CHRISTOPHER ROJAS |
| Final | 1/22/2025 | OK to Issue CofO | CHRISTOPHER ROJAS |