8233 N QUARTZ AVE 91306
Certificate Information: 8233 N QUARTZ AVE 91306
- Application / Permit
- 23014-20000-03008
- Plan Check / Job No.
- B23VN10057
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- PROPOSED IRREGULAR SHAPED 29'X37'ADDITION TO EXPAND EXISTING LIVING/DINING/KITCHEN, TWO NEW BEDROOMS & 1 BATHROOM. AND 19'X20' TWO CAR GARAGE ADDITION. CONSTRUCTION DESIGN PER ENGR. <NFPA 13-D FIRE SPRINKLER SYSTEM THRU-OUT>
- Permit Issued
- Issued on 11/28/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 8/29/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/27/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 8/2/2023 | HAYATO TSUCHIYA |
| Corrections Issued | 8/2/2023 | HAYATO TSUCHIYA |
| Building Plans Picked Up | 8/3/2023 | APPLICANT |
| Applicant returned to address corrections | 11/17/2023 | ANGELICA DAVE |
| Issued | 11/28/2023 | APPLICANT |
| CofO in Progress | 7/29/2025 | ALEXANDER HANDY |
| Permit Finaled | 8/29/2025 | JOHN JANSON |
| CofO Issued | 8/29/2025 | JOHN JANSON |
| Permit Finaled | 8/29/2025 | JOHN JANSON |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 10/30/2023 | NIKKI ZULUETA |
| Sewer availability | Cleared | 10/30/2023 | NIKKI ZULUETA |
| Low Impact Development (LID) | Cleared | 11/8/2023 | MARCO SANCHEZ |
| Roof/Waste drainage to street | Cleared | 11/15/2023 | NIKKI ZULUETA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Morales,, Carlos Alberto; Lic. No.: C69972 | 38100 SAN MATEO AVE PALMDALE, CA 93551 |
Inspector Information
| DAVID FASTIGGI, (818) 774-4317 | Office Hours: 7:00-8:00 AM MON-FRI |
| ALEXANDER HANDY, (818) 774-4317 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 5/30/2024 | Conditional Approval | ALEXANDER HANDY |
| Excavation/Setback/Form/Re-Bar | 6/3/2024 | Approved | ALEXANDER HANDY |
| Excavation/Setback/Form/Re-Bar | 6/10/2024 | Approved | ALEXANDER HANDY |
| BUILDING-Rough-Frame | 6/14/2024 | Partial Approval | ALEXANDER HANDY |
| PLUMBING-Rough | 6/14/2024 | Partial Approval | ALEXANDER HANDY |
| Floor/Roof Diaphrgm/Shear Wall | 6/20/2024 | Partial Approval | ALEXANDER HANDY |
| Insulation | 6/20/2024 | Partial Approval | ALEXANDER HANDY |
| ELECTRICAL-Rough | 9/23/2024 | Approved | ALEXANDER HANDY |
| Floor/Roof Diaphrgm/Shear Wall | 9/23/2024 | Conditional Approval | ALEXANDER HANDY |
| HVAC-Rough | 9/23/2024 | Approved | ALEXANDER HANDY |
| PLUMBING-Rough | 9/23/2024 | Conditional Approval | ALEXANDER HANDY |
| Interior/Exterior Lathing | 10/17/2024 | Partial Approval | ALEXANDER HANDY |
| Shower Pan | 10/17/2024 | Approved | ALEXANDER HANDY |
| Insulation | 10/24/2024 | Approved | ALEXANDER HANDY |
| Interior/Exterior Lathing | 11/4/2024 | Approved | ALEXANDER HANDY |
| Sewer | 11/4/2024 | Approved | ALEXANDER HANDY |
| Drywall Nailing | 11/7/2024 | Approved | SCOTT SOBEL |
| Green Building Rough | 11/7/2024 | Approved | SCOTT SOBEL |
| BUILDING-Rough-Frame | 7/15/2025 | Not Ready for Inspection | ARUTYUN MADATYAN |
| Final | 7/15/2025 | Corrections Issued | ARUTYUN MADATYAN |
| Footing/Foundation/Slab | 7/15/2025 | Not Ready for Inspection | ARUTYUN MADATYAN |
| Green Building Final | 7/15/2025 | Approved | ARUTYUN MADATYAN |
| SGSOV-Seismic Gas S/O Valve | 7/15/2025 | SGSOV Approved | ARUTYUN MADATYAN |
| Smoke Detectors | 7/15/2025 | Approved | ARUTYUN MADATYAN |
| BUILDING-Rough-Frame | 7/23/2025 | Approved | ALEXANDER HANDY |
| ELECTRICAL-Final | 7/23/2025 | Approved | ALEXANDER HANDY |
| Final | 7/23/2025 | OK to Issue CofO | ALEXANDER HANDY |
| Footing/Foundation/Slab | 7/23/2025 | Approved | ALEXANDER HANDY |
| HVAC-Final | 7/23/2025 | Approved | ALEXANDER HANDY |
| PLUMBING-Final | 7/23/2025 | Approved | ALEXANDER HANDY |
| Service/Power Release | 7/23/2025 | Not Required | ALEXANDER HANDY |