14955 W HARTSOOK ST 91403

Certificate Information: 14955 W HARTSOOK ST 91403

Application / Permit
23014-20000-03003
Plan Check / Job No.
B23VN10040
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 38'11" X 26'11" IRREGULAR SHAPED ADDITION TO (E) SFD TO ENLARGE KITCHEN , RELOCATE LIVING ROOM , ENLARGE MASTER BEDROOM , NEW 12'2" X 4' ADDITION TO (E) SFD TO ENLAGRE THE ENTRY, REMODEL TO (E) SFD TO CONVERT LIVING ROOM TO BEDROOM, , NFPA-13D FIRE SPRINKLERS REQUIRED THROUGHOUT, ALL WORK PER ENGINEERING
Permit Issued
Issued on 5/8/2024
Issuing Office
Valley
Current Status
CofO Issued on 1/27/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/27/2023 APPLICANT
Assigned to Plan Check Engineer 8/3/2023 RARES BODEA
Corrections Issued 8/7/2023 RARES BODEA
Quality Review Completed 8/9/2023 STEVEN KIM
Building Plans Picked Up 8/10/2023 APPLICANT
Applicant returned to address corrections 11/9/2023 RARES BODEA
Plan Check Approved 5/7/2024 RARES BODEA
Issued 5/8/2024 APPLICANT
CofO in Progress 12/15/2025 JACK KARGODORIAN
No Progress 12/24/2025 RAUL OLAGI
CofO in Progress 12/24/2025 RAUL OLAGI
Permit Finaled 1/27/2026 RUBEN SALAS
CofO Issued 1/27/2026 RUBEN SALAS
Permit Finaled 1/27/2026 RUBEN SALAS

Permit Application Clearance Information

Sewer availability Cleared 8/29/2023 GABRIELLA TORRES
Low Impact Development (LID) Cleared 4/11/2024 MELINEH AGHAKHABIAN
ZI Cleared 4/19/2024 RUBEN VASQUEZ
Roof/Waste drainage to street Cleared 4/22/2024 EDGAR ALCARAZ
Eng Process Fee Ord 176,300 Cleared 5/7/2024 GABRIELLA TORRES

Contact Information

Contractor Owner-Builder       ,
Engineer Shahbaz,, Shant Pierre; Lic. No.: C93079 15445 VENTURA BLVD #63      SHERMAN OAKS, CA 91403

Inspector Information

DAVID ANDERSON, (818) 374-1166 Office Hours: 7:00-8:00 AM MON-FRI
RAUL OLAGI, (818) 374-1166 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 5/15/2024 Not Ready for Inspection JACK KARGODORIAN
Deputy Drilled-In Anchors 7/31/2024 Conditional Approval DAVID MATSON
Footing/Foundation/Slab 8/1/2024 Corrections Issued JACK KARGODORIAN
PLUMBING-Rough 8/1/2024 Partial Approval JACK KARGODORIAN
Footing/Foundation/Slab 8/2/2024 Approved JACK KARGODORIAN
Floor/Roof Diaphrgm/Shear Wall 10/29/2024 Partial Approval JACK KARGODORIAN
Floor/Roof Diaphrgm/Shear Wall 11/6/2024 Partial Approval JACK KARGODORIAN
Floor/Roof Diaphrgm/Shear Wall 12/12/2024 Partial Approval JACK KARGODORIAN
Floor/Roof Diaphrgm/Shear Wall 1/29/2025 Partial Approval JACK KARGODORIAN
Floor/Roof Diaphrgm/Shear Wall 2/10/2025 Partial Approval JACK KARGODORIAN
Wood Frame 2/10/2025 Not Ready for Inspection JACK KARGODORIAN
ELECTRICAL-Rough 3/7/2025 Approved CHRISTOPHE COCHRAN
HVAC-Rough 3/7/2025 Approved CHRISTOPHE COCHRAN
PLUMBING-Rough 3/7/2025 Corrections Issued CHRISTOPHE COCHRAN
Wood Frame 3/7/2025 Corrections Issued CHRISTOPHE COCHRAN
PLUMBING-Rough 3/10/2025 Approved JACK KARGODORIAN
Wood Frame 3/10/2025 Approved JACK KARGODORIAN
Insulation 3/12/2025 Approved JACK KARGODORIAN
Interior/Exterior Lathing 3/12/2025 Partial Approval JACK KARGODORIAN
Drywall Nailing 3/24/2025 Approved ROBERTO PALACIOS-LOPEZ
Gas Test 3/24/2025 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
Green Building Rough 3/24/2025 Approved ROBERTO PALACIOS-LOPEZ
Interior/Exterior Lathing 3/24/2025 Approved ROBERTO PALACIOS-LOPEZ
Shower Pan 3/24/2025 Approved ROBERTO PALACIOS-LOPEZ
Deputy Drilled-In Anchors 5/7/2025 Conditional Approval JUAN VALENZUELA
ELECTRICAL-Final 9/10/2025 Corrections Issued JACK KARGODORIAN
Gas Test 9/10/2025 Approved JACK KARGODORIAN
HVAC-Final 9/10/2025 Approved JACK KARGODORIAN
PLUMBING-Final 9/10/2025 Approved JACK KARGODORIAN
Smoke Detectors 9/10/2025 Approved JACK KARGODORIAN
ELECTRICAL-Final 9/18/2025 Approved JACK KARGODORIAN
BUILDING-Rough-Frame 12/8/2025 Approved JACK KARGODORIAN
Final 12/8/2025 Corrections Issued JACK KARGODORIAN
Green Building Final 12/8/2025 Approved JACK KARGODORIAN
SGSOV-Seismic Gas S/O Valve 12/8/2025 SGSOV Approved JACK KARGODORIAN
Final 12/12/2025 OK to Issue CofO JACK KARGODORIAN
Service/Power Release 12/12/2025 Approved JACK KARGODORIAN