14955 W HARTSOOK ST 91403
Certificate Information: 14955 W HARTSOOK ST 91403
- Application / Permit
- 23014-20000-03003
- Plan Check / Job No.
- B23VN10040
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 38'11" X 26'11" IRREGULAR SHAPED ADDITION TO (E) SFD TO ENLARGE KITCHEN , RELOCATE LIVING ROOM , ENLARGE MASTER BEDROOM , NEW 12'2" X 4' ADDITION TO (E) SFD TO ENLAGRE THE ENTRY, REMODEL TO (E) SFD TO CONVERT LIVING ROOM TO BEDROOM, , NFPA-13D FIRE SPRINKLERS REQUIRED THROUGHOUT, ALL WORK PER ENGINEERING
- Permit Issued
- Issued on 5/8/2024
- Issuing Office
- Valley
- Current Status
- CofO Issued on 1/27/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/27/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 8/3/2023 | RARES BODEA |
| Corrections Issued | 8/7/2023 | RARES BODEA |
| Quality Review Completed | 8/9/2023 | STEVEN KIM |
| Building Plans Picked Up | 8/10/2023 | APPLICANT |
| Applicant returned to address corrections | 11/9/2023 | RARES BODEA |
| Plan Check Approved | 5/7/2024 | RARES BODEA |
| Issued | 5/8/2024 | APPLICANT |
| CofO in Progress | 12/15/2025 | JACK KARGODORIAN |
| No Progress | 12/24/2025 | RAUL OLAGI |
| CofO in Progress | 12/24/2025 | RAUL OLAGI |
| Permit Finaled | 1/27/2026 | RUBEN SALAS |
| CofO Issued | 1/27/2026 | RUBEN SALAS |
| Permit Finaled | 1/27/2026 | RUBEN SALAS |
Permit Application Clearance Information
| Sewer availability | Cleared | 8/29/2023 | GABRIELLA TORRES |
| Low Impact Development (LID) | Cleared | 4/11/2024 | MELINEH AGHAKHABIAN |
| ZI | Cleared | 4/19/2024 | RUBEN VASQUEZ |
| Roof/Waste drainage to street | Cleared | 4/22/2024 | EDGAR ALCARAZ |
| Eng Process Fee Ord 176,300 | Cleared | 5/7/2024 | GABRIELLA TORRES |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Shahbaz,, Shant Pierre; Lic. No.: C93079 | 15445 VENTURA BLVD #63 SHERMAN OAKS, CA 91403 |
Inspector Information
| DAVID ANDERSON, (818) 374-1166 | Office Hours: 7:00-8:00 AM MON-FRI |
| RAUL OLAGI, (818) 374-1166 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 5/15/2024 | Not Ready for Inspection | JACK KARGODORIAN |
| Deputy Drilled-In Anchors | 7/31/2024 | Conditional Approval | DAVID MATSON |
| Footing/Foundation/Slab | 8/1/2024 | Corrections Issued | JACK KARGODORIAN |
| PLUMBING-Rough | 8/1/2024 | Partial Approval | JACK KARGODORIAN |
| Footing/Foundation/Slab | 8/2/2024 | Approved | JACK KARGODORIAN |
| Floor/Roof Diaphrgm/Shear Wall | 10/29/2024 | Partial Approval | JACK KARGODORIAN |
| Floor/Roof Diaphrgm/Shear Wall | 11/6/2024 | Partial Approval | JACK KARGODORIAN |
| Floor/Roof Diaphrgm/Shear Wall | 12/12/2024 | Partial Approval | JACK KARGODORIAN |
| Floor/Roof Diaphrgm/Shear Wall | 1/29/2025 | Partial Approval | JACK KARGODORIAN |
| Floor/Roof Diaphrgm/Shear Wall | 2/10/2025 | Partial Approval | JACK KARGODORIAN |
| Wood Frame | 2/10/2025 | Not Ready for Inspection | JACK KARGODORIAN |
| ELECTRICAL-Rough | 3/7/2025 | Approved | CHRISTOPHE COCHRAN |
| HVAC-Rough | 3/7/2025 | Approved | CHRISTOPHE COCHRAN |
| PLUMBING-Rough | 3/7/2025 | Corrections Issued | CHRISTOPHE COCHRAN |
| Wood Frame | 3/7/2025 | Corrections Issued | CHRISTOPHE COCHRAN |
| PLUMBING-Rough | 3/10/2025 | Approved | JACK KARGODORIAN |
| Wood Frame | 3/10/2025 | Approved | JACK KARGODORIAN |
| Insulation | 3/12/2025 | Approved | JACK KARGODORIAN |
| Interior/Exterior Lathing | 3/12/2025 | Partial Approval | JACK KARGODORIAN |
| Drywall Nailing | 3/24/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| Gas Test | 3/24/2025 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| Green Building Rough | 3/24/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| Interior/Exterior Lathing | 3/24/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| Shower Pan | 3/24/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| Deputy Drilled-In Anchors | 5/7/2025 | Conditional Approval | JUAN VALENZUELA |
| ELECTRICAL-Final | 9/10/2025 | Corrections Issued | JACK KARGODORIAN |
| Gas Test | 9/10/2025 | Approved | JACK KARGODORIAN |
| HVAC-Final | 9/10/2025 | Approved | JACK KARGODORIAN |
| PLUMBING-Final | 9/10/2025 | Approved | JACK KARGODORIAN |
| Smoke Detectors | 9/10/2025 | Approved | JACK KARGODORIAN |
| ELECTRICAL-Final | 9/18/2025 | Approved | JACK KARGODORIAN |
| BUILDING-Rough-Frame | 12/8/2025 | Approved | JACK KARGODORIAN |
| Final | 12/8/2025 | Corrections Issued | JACK KARGODORIAN |
| Green Building Final | 12/8/2025 | Approved | JACK KARGODORIAN |
| SGSOV-Seismic Gas S/O Valve | 12/8/2025 | SGSOV Approved | JACK KARGODORIAN |
| Final | 12/12/2025 | OK to Issue CofO | JACK KARGODORIAN |
| Service/Power Release | 12/12/2025 | Approved | JACK KARGODORIAN |