2515 S WESTGATE AVE 90064
Certificate Information: 2515 S WESTGATE AVE 90064
- Application / Permit
- 23014-20000-03001
- Plan Check / Job No.
- B23VN10032
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- REMODEL ON THE FIRST FLOOR AND 2ND FLOOR ADDITION OF 26' 2" X 41' X 11" WITH NFPA 13D SPRINKLERED REQUIREMENT THROUGHOUT. ALL WORK DONE PER ENGINEERING
- Permit Issued
- Issued on 9/19/2023
- Issuing Office
- Current Status
- CofO Issued on 7/17/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/27/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 8/3/2023 | NAREG ATARIAN |
| Corrections Issued | 8/8/2023 | NAREG ATARIAN |
| Quality Review Completed | 8/9/2023 | OMID HEDAYAT |
| Building Plans Picked Up | 8/17/2023 | APPLICANT |
| Plan Check Approved | 9/19/2023 | NAREG ATARIAN |
| Issued | 9/19/2023 | APPLICANT |
| CofO in Progress | 7/11/2025 | WILBER ROSALES |
| Permit Finaled | 7/17/2025 | RICHARD STEINBACH |
| CofO Issued | 7/17/2025 | RICHARD STEINBACH |
| Permit Finaled | 7/17/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| ZI | Cleared | 8/22/2023 | MAYELA VILLA |
| Eng Process Fee Ord 176,300 | Cleared | 8/23/2023 | DARIN LAM |
| Sewer availability | Cleared | 8/23/2023 | DARIN LAM |
| ZI | Cleared | 8/29/2023 | MAYELA VILLA |
| Roof/Waste drainage to street | Cleared | 9/18/2023 | DARIN LAM |
Contact Information
| Contractor | Pacific Home Renovation Inc; Lic. No.: 1087072-B | 18960 VENTURA BLVD #484 TARZANA, CA 91356 |
| Engineer | Rahman,, Moksudur; Lic. No.: C69263 | 14616 MCKENDREE AVE CHINO, CA 91708 |
Inspector Information
| KIRK SANDERS, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARAM AVEDISIAN, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 11/3/2023 | Corrections Issued | JESUS PINEDA |
| BUILDING-Rough-Frame | 11/9/2023 | Corrections Issued | JESUS RODRIGUEZ |
| Excavation/Setback/Form/Re-Bar | 11/9/2023 | Approved | JESUS RODRIGUEZ |
| Footing/Foundation/Slab | 11/9/2023 | Approved | JESUS RODRIGUEZ |
| Deputy Wood Construction | 3/18/2024 | Conditional Approval | JESUS PINEDA |
| Floor/Roof Diaphrgm/Shear Wall | 3/19/2024 | Corrections Issued | JESUS PINEDA |
| Special/Order Compliance | 3/19/2024 | Corrections Issued | JESUS PINEDA |
| Floor/Roof Diaphrgm/Shear Wall | 3/22/2024 | Approved | TEMISTOCLES CAAL |
| PLUMBING-Rough | 4/22/2024 | Corrections Issued | JESUS PINEDA |
| ELECTRICAL-Rough | 5/2/2024 | Corrections Issued | JESUS PINEDA |
| HVAC-Rough | 5/2/2024 | Corrections Issued | JESUS PINEDA |
| PLUMBING-Rough | 5/2/2024 | Corrections Issued | JESUS PINEDA |
| HVAC-Rough | 5/7/2024 | Approved | JESUS PINEDA |
| PLUMBING-Rough | 5/9/2024 | Approved | HERBERT GIRON |
| BUILDING-Rough-Frame | 5/15/2024 | Corrections Issued | KIRK SANDERS |
| ELECTRICAL-Rough | 5/15/2024 | Not Ready for Inspection | KIRK SANDERS |
| Verify Sprinkler Sign Off | 5/15/2024 | Approved | KIRK SANDERS |
| BUILDING-Rough-Frame | 5/16/2024 | Not Ready for Inspection | JESUS PINEDA |
| ELECTRICAL-Rough | 5/16/2024 | Approved | JESUS PINEDA |
| Green Building Rough | 5/16/2024 | Approved | JESUS PINEDA |
| Interior/Exterior Lathing | 5/16/2024 | Partial Approval | JESUS PINEDA |
| MERV13>=Rough | 5/16/2024 | Approved | JESUS PINEDA |
| Verify Sprinkler Sign Off | 5/16/2024 | Approved | JESUS PINEDA |
| BUILDING-Rough-Frame | 5/20/2024 | Conditional Approval | KIRK SANDERS |
| Insulation | 5/24/2024 | Approved | TEMISTOCLES CAAL |
| Drywall Nailing | 6/4/2024 | Approved | JESUS PINEDA |
| Shower Pan | 6/27/2024 | Approved | KIRK SANDERS |
| Interior/Exterior Lathing | 7/15/2024 | Approved | JESUS PINEDA |
| PLUMBING-Final | 10/29/2024 | Corrections Issued | ARAM AVEDISIAN |
| BUILDING-Rough-Frame | 11/18/2024 | Not Ready for Inspection | DANIEL VERA |
| Final | 11/18/2024 | Not Ready for Inspection | DANIEL VERA |
| Green Building Final | 11/18/2024 | Corrections Issued | DANIEL VERA |
| MERV13>=Final | 11/18/2024 | Not Ready for Inspection | DANIEL VERA |
| SGSOV-Seismic Gas S/O Valve | 11/18/2024 | SGSOV Approved | DANIEL VERA |
| Smoke Detectors | 11/18/2024 | Not Ready for Inspection | DANIEL VERA |
| BUILDING-Rough-Frame | 2/11/2025 | Approved | DANIEL VERA |
| Final | 2/11/2025 | Corrections Issued | DANIEL VERA |
| Green Building Final | 2/11/2025 | Not Ready for Inspection | DANIEL VERA |
| MERV13>=Final | 2/11/2025 | Approved | DANIEL VERA |
| PLUMBING-Final | 2/11/2025 | Approved | DANIEL VERA |
| Smoke Detectors | 2/11/2025 | Approved | DANIEL VERA |
| Final | 2/21/2025 | Not Ready for Inspection | DANIEL VERA |
| Green Building Final | 2/21/2025 | Approved | DANIEL VERA |
| HVAC-Final | 2/21/2025 | Approved | DANIEL VERA |
| Final | 2/25/2025 | Corrections Issued | JESUS RODRIGUEZ |
| Final | 4/1/2025 | Corrections Issued | ARAM AVEDISIAN |
| Pre-Inspection | 5/1/2025 | Partial Inspection | TEMISTOCLES CAAL |
| Final | 6/24/2025 | Not Ready for Inspection | TEMISTOCLES CAAL |
| Service/Power Release | 6/24/2025 | Not Ready for Inspection | TEMISTOCLES CAAL |
| Wood Frame | 6/30/2025 | Partial Approval | WILBER ROSALES |
| ELECTRICAL-Final | 7/10/2025 | Approved | WILBER ROSALES |
| Final | 7/10/2025 | OK to Issue CofO | WILBER ROSALES |
| Service/Power Release | 7/10/2025 | Approved | WILBER ROSALES |