6231 N CARTWRIGHT AVE 91606
Certificate Information: 6231 N CARTWRIGHT AVE 91606
- Application / Permit
- 23014-20000-02992
- Plan Check / Job No.
- B23VN09994
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- EPLAN: 1-story addition to (E) SFD.
- Permit Issued
- Issued on 11/1/2023
- Issuing Office
- Current Status
- CofO Issued on 8/23/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/27/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 8/4/2023 | JOHNPAUL ISIP |
| Corrections Issued | 8/7/2023 | JOHNPAUL ISIP |
| Applicant returned to address corrections | 8/23/2023 | CAROLEAN BASMA |
| Plan Check Approved | 8/25/2023 | SAMUEL GONZALEZ |
| Issued | 11/1/2023 | APPLICANT |
| CofO in Progress | 7/19/2024 | ROBERTO PALACIOS-LOPEZ |
| Permit Finaled | 8/23/2024 | DANIEL ORRANTE |
| CofO Issued | 8/23/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 8/24/2023 | TAL SHEMEN |
| Roof/Waste drainage to street | Cleared | 8/24/2023 | TAL SHEMEN |
| Sewer availability | Cleared | 8/24/2023 | TAL SHEMEN |
Contact Information
| Architect | Chung,, Jooyoung; Lic. No.: C40060 | 2340 YOSEMITE DR LOS ANGELES, CA 90041 |
| Contractor | Owner-Builder | , |
| Engineer | Park,, Juntae; Lic. No.: C65104 | 3055 WILSHIRE BLVD 880 LOS ANGELES, CA 90010 |
Inspector Information
| GAREN HAYRAPETYAN, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERTO PALACIOS-LOPEZ, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 12/4/2023 | Partial Approval | CHRISTOPHER ROJAS |
| Deputy Drilled-In Anchors | 12/11/2023 | Partial Approval | JOHN HAYES |
| Footing/Foundation/Slab | 12/11/2023 | Corrections Issued | JOHN HAYES |
| Excavation/Setback/Form/Re-Bar | 12/13/2023 | Approved | JOHN HAYES |
| Floor/Roof Diaphrgm/Shear Wall | 2/15/2024 | Partial Approval | MISAEL ESPARZA |
| ELECTRICAL-Rough | 3/14/2024 | Corrections Issued | JOHN HAYES |
| PLUMBING-Rough | 3/14/2024 | Not Ready for Inspection | JOHN HAYES |
| BUILDING-Rough-Frame | 3/18/2024 | Corrections Issued | JOHN HAYES |
| Rough-Elec/Plmb/HVAC | 3/18/2024 | Not Ready for Inspection | JOHN HAYES |
| ELECTRICAL-Rough | 4/8/2024 | Approved | JOSE AVILA |
| PLUMBING-Rough | 4/8/2024 | Approved | JOSE AVILA |
| Insulation | 5/1/2024 | Approved | JACK KARGODORIAN |
| Interior/Exterior Lathing | 5/1/2024 | Partial Approval | JACK KARGODORIAN |
| Drywall Nailing | 5/8/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Green Building Rough | 5/8/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| Interior/Exterior Lathing | 5/8/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| BUILDING-Rough-Frame | 5/13/2024 | Corrections Issued | JOSE AVILA |
| BUILDING-Rough-Frame | 6/6/2024 | Approved | JOSE AVILA |
| Drywall Nailing | 6/6/2024 | Approved | JOSE AVILA |
| HVAC-Rough | 6/6/2024 | Approved | JOSE AVILA |
| Final | 7/12/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Footing/Foundation/Slab | 7/12/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| Green Building Final | 7/12/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 7/12/2024 | SGSOV Approved | ROBERTO PALACIOS-LOPEZ |
| Smoke Detectors | 7/12/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| ELECTRICAL-Final | 7/18/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| Final | 7/18/2024 | OK to Issue CofO | ROBERTO PALACIOS-LOPEZ |
| Green Building Final | 7/18/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| HVAC-Final | 7/18/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| PLUMBING-Final | 7/18/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| Smoke Detectors | 7/18/2024 | Approved | ROBERTO PALACIOS-LOPEZ |