10550-10552 N COLLETT AVE 91344

Certificate Information: 10550-10552 N COLLETT AVE 91344

Application / Permit
23014-20000-02991
Plan Check / Job No.
B23VN09988
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan: NEW 22' 4 " X 22' ADU ADDITION ON TOP OF EXISTING GARAGE PER LAMC 12.22 A.33 (c) AND (e). ALL WORK PER ENGINEER
Permit Issued
Issued on 1/15/2024
Issuing Office
Current Status
CofO Issued on 5/23/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/1/2023 APPLICANT
Assigned to Plan Check Engineer 8/17/2023 NAREG ATARIAN
Corrections Issued 8/24/2023 NAREG ATARIAN
Quality Review Completed 8/24/2023 OMID HEDAYAT
Applicant returned to address corrections 12/5/2023 NAREG ATARIAN
Plan Check Approved 12/7/2023 NAREG ATARIAN
Issued 1/15/2024 APPLICANT
CofO in Progress 5/22/2025 CHRISTOPHER ROJAS
Permit Finaled 5/23/2025 RUBEN SALAS
CofO Issued 5/23/2025 RUBEN SALAS
Permit Finaled 5/23/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 10/10/2023 GABRIELLA TORRES
Roof/Waste drainage to street Cleared 10/10/2023 GABRIELLA TORRES
Eng Process Fee Ord 176,300 Cleared 10/24/2023 GABRIELLA TORRES
Sewer availability Cleared 10/24/2023 GABRIELLA TORRES

Contact Information

Contractor Lilirob General Construction Inc; Lic. No.: 1065100-B       ,
Engineer Shagirian,, Ashot; Lic. No.: C79415 11337 RUNNYMEDE ST      SUN VALLEY, CA 91352
Engineer Shagirian,, Ashot; Lic. No.: NA79415       ,

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 7/2/2024 Conditional Approval ROBERT GOLD
Excavation/Setback/Form/Re-Bar 7/3/2024 Not Ready for Inspection RAUL OLAGI
Footing/Foundation/Slab 7/3/2024 Not Ready for Inspection RAUL OLAGI
Special/Order Compliance 7/3/2024 Corrections Issued RAUL OLAGI
Footing/Foundation/Slab 1/16/2025 Approved MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 1/27/2025 Partial Approval MISAEL ESPARZA
Pre-Inspection 1/27/2025 Approved MISAEL ESPARZA
Deputy Wood Construction 2/3/2025 Conditional Approval RAUL OLAGI
Deputy Wood Construction 2/11/2025 Conditional Approval ROBERT GOLD
BUILDING-Rough-Frame 2/25/2025 Partial Inspection JAVIER RAMOS JR
ELECTRICAL-Rough 2/25/2025 Approved JAVIER RAMOS JR
Floor/Roof Diaphrgm/Shear Wall 2/25/2025 Approved JAVIER RAMOS JR
Footing/Foundation/Slab 2/25/2025 Approved JAVIER RAMOS JR
PLUMBING-Rough 2/25/2025 Corrections Issued JAVIER RAMOS JR
Sewer 2/25/2025 Partial Approval JAVIER RAMOS JR
Underground Mechanical 2/25/2025 Partial Approval JAVIER RAMOS JR
Insulation 3/5/2025 Approved LOUIS ESCOTO
Interior/Exterior Lathing 3/5/2025 Approved LOUIS ESCOTO
PLUMBING-Rough 3/5/2025 Approved LOUIS ESCOTO
Sewer 3/5/2025 Approved LOUIS ESCOTO
Drywall Nailing 3/12/2025 Corrections Issued SALVADOR MARTINEZ
HVAC-Rough 3/14/2025 Corrections Issued JAVIER RAMOS JR
Gas Test 4/18/2025 Not Ready for Inspection CHRISTOPHER ROJAS
HVAC-Rough 4/18/2025 Approved CHRISTOPHER ROJAS
Service/Power Release 4/18/2025 Not Ready for Inspection CHRISTOPHER ROJAS
ELECTRICAL-Final 4/30/2025 Not Ready for Inspection CHRISTOPHER ROJAS
Final 4/30/2025 Corrections Issued CHRISTOPHER ROJAS
HVAC-Final 4/30/2025 Not Ready for Inspection CHRISTOPHER ROJAS
PLUMBING-Final 4/30/2025 Not Ready for Inspection CHRISTOPHER ROJAS
Service/Power Release 4/30/2025 Not Ready for Inspection CHRISTOPHER ROJAS
BUILDING-Rough-Frame 5/5/2025 Approved CHRISTOPHER ROJAS
Drywall Nailing 5/5/2025 Approved CHRISTOPHER ROJAS
Final 5/5/2025 Corrections Issued CHRISTOPHER ROJAS
SGSOV-Seismic Gas S/O Valve 5/5/2025 SGSOV Approved CHRISTOPHER ROJAS
Smoke Detectors 5/5/2025 Approved CHRISTOPHER ROJAS
Final 5/8/2025 Partial Approval CHRISTOPHER ROJAS
Final 5/12/2025 Corrections Issued CHRISTOPHER ROJAS
Final 5/21/2025 Partial Approval CHRISTOPHER ROJAS
Final 5/22/2025 OK to Issue CofO CHRISTOPHER ROJAS
Service/Power Release 5/22/2025 Approved CHRISTOPHER ROJAS