12302 W TIARA ST 91607
Certificate Information: 12302 W TIARA ST 91607
- Application / Permit
- 23014-20000-02990
- Plan Check / Job No.
- B23VN09983
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- MAJOR INTERIOR REMODELINCLUDE RE-ROOF ENTIRE ROOF,REMOVE MOST INTERIOR WALLS. TO THE EXISTING 2-STORY SINGLE FAMILY DWELLING W/NEW 494 SQFT ADDITION W/ NEW ATTACHED OPEN TRELLIS W/NFPA 13D SPRINKLERS REQUIRED THROUGHOUT.
- Permit Issued
- Issued on 9/18/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 8/31/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/26/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 8/3/2023 | PETER MOSESIAN |
| Corrections Issued | 8/8/2023 | PETER MOSESIAN |
| Quality Review Completed | 8/15/2023 | OMID HEDAYAT |
| Building Plans Picked Up | 8/17/2023 | APPLICANT |
| Plan Check Approved | 9/15/2023 | PETER MOSESIAN |
| Issued | 9/18/2023 | APPLICANT |
| CofO in Progress | 8/12/2024 | OGANES TARAKHCHYAN |
| Permit Finaled | 8/31/2024 | DANIEL ORRANTE |
| CofO Issued | 8/31/2024 | DANIEL ORRANTE |
| Permit Finaled | 8/31/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 8/23/2023 | TAL SHEMEN |
| Eng Process Fee Ord 176,300 | Cleared | 9/13/2023 | TAL SHEMEN |
Contact Information
| Contractor | Landmark Remodeling Company; Lic. No.: 1053170-B | 369 S DOHENY DR SUITE 174 BEVERLY HILLS, CA 90211 |
| Engineer | Grigoryan,, Souren; Lic. No.: C93320 | 6506 TEESDALE AVE NORTH HOLLYWOOD, CA 91606 |
Inspector Information
| WAYNE REGESTER, (818) 374-1164 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 10/13/2023 | Corrections Issued | KIRK SANDERS |
| BUILDING-Rough-Frame | 10/23/2023 | Corrections Issued | CHRISTOPHER ROJAS |
| Green Building Rough | 10/23/2023 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| Grounding or Bonding | 10/26/2023 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| Pool Piping | 10/26/2023 | Approved | CHRISTOPHER ROJAS |
| Pre-Gunite | 10/26/2023 | Approved | CHRISTOPHER ROJAS |
| Wood Frame | 10/26/2023 | Partial Approval | CHRISTOPHER ROJAS |
| Deputy Drilled-In Anchors | 10/27/2023 | Conditional Approval | ROBERT GOLD |
| Insulation | 10/30/2023 | Approved | CHRISTOPHER ROJAS |
| Pre-Inspection | 10/30/2023 | Approved | CHRISTOPHER ROJAS |
| Deputy Drilled-In Anchors | 11/1/2023 | Conditional Approval | JUAN VALENZUELA |
| Floor/Roof Diaphrgm/Shear Wall | 11/3/2023 | Partial Approval | JUAN VALENZUELA |
| PLUMBING-Rough | 12/6/2023 | Partial Approval | JOSE AVILA |
| Sewer | 12/6/2023 | Approved | JOSE AVILA |
| Floor/Roof Diaphrgm/Shear Wall | 12/12/2023 | Corrections Issued | JOSE AVILA |
| Deputy Wood Construction | 12/14/2023 | Conditional Approval | JUAN VALENZUELA |
| PLUMBING-Rough | 12/27/2023 | Not Ready for Inspection | MISAEL ESPARZA |
| Wood Frame | 12/27/2023 | Not Ready for Inspection | MISAEL ESPARZA |
| Deputy Drilled-In Anchors | 1/16/2024 | Conditional Approval | CRAIG DAVIS |
| ELECTRICAL-Rough | 1/16/2024 | Corrections Issued | CRAIG DAVIS |
| Floor/Roof Diaphrgm/Shear Wall | 1/16/2024 | Partial Approval | CRAIG DAVIS |
| Gas Test | 1/16/2024 | Not Ready for Inspection | CRAIG DAVIS |
| HVAC-Rough | 1/16/2024 | Corrections Issued | CRAIG DAVIS |
| PLUMBING-Rough | 1/16/2024 | Not Ready for Inspection | CRAIG DAVIS |
| Rough-Elec/Plmb/HVAC | 1/16/2024 | Corrections Issued | CRAIG DAVIS |
| ELECTRICAL-Rough | 1/31/2024 | Approved | JOSE AVILA |
| HVAC-Rough | 1/31/2024 | Approved | JOSE AVILA |
| PLUMBING-Rough | 1/31/2024 | Approved | JOSE AVILA |
| Interior/Exterior Lathing | 2/7/2024 | Corrections Issued | CRAIG DAVIS |
| Interior/Exterior Lathing | 2/12/2024 | Not Ready for Inspection | CRAIG DAVIS |
| Wood Frame | 2/12/2024 | Approved | CRAIG DAVIS |
| Insulation | 2/20/2024 | Corrections Issued | SALVADOR MARTINEZ |
| Interior/Exterior Lathing | 2/20/2024 | Partial Approval | SALVADOR MARTINEZ |
| Insulation | 2/22/2024 | Corrections Issued | KIRK SANDERS |
| Interior/Exterior Lathing | 2/22/2024 | Partial Approval | KIRK SANDERS |
| Insulation | 2/26/2024 | Partial Approval | SALVADOR MARTINEZ |
| BUILDING-Rough-Frame | 3/13/2024 | Approved | JOSE AVILA |
| Drywall Nailing | 3/13/2024 | Approved | JOSE AVILA |
| Green Building Rough | 3/13/2024 | Approved | JOSE AVILA |
| Interior/Exterior Lathing | 3/13/2024 | Approved | JOSE AVILA |
| Shower Pan | 3/13/2024 | Approved | JOSE AVILA |
| Deck | 5/3/2024 | Partial Inspection | MISAEL ESPARZA |
| SGSOV-Seismic Gas S/O Valve | 7/3/2024 | SGSOV Not Ready | OGANES TARAKHCHYAN |
| Final | 7/29/2024 | Corrections Issued | OGANES TARAKHCHYAN |
| Footing/Foundation/Slab | 7/29/2024 | Approved | OGANES TARAKHCHYAN |
| SGSOV-Seismic Gas S/O Valve | 7/29/2024 | SGSOV Not Ready | OGANES TARAKHCHYAN |
| Service/Power Release | 7/29/2024 | Approved | OGANES TARAKHCHYAN |
| Smoke Detectors | 7/29/2024 | Approved | OGANES TARAKHCHYAN |
| Final | 8/2/2024 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Final | 8/7/2024 | OK to Issue CofO | OGANES TARAKHCHYAN |
| Green Building Final | 8/7/2024 | Approved | OGANES TARAKHCHYAN |
| SGSOV-Seismic Gas S/O Valve | 8/7/2024 | SGSOV Approved | OGANES TARAKHCHYAN |