12302 W TIARA ST 91607

Certificate Information: 12302 W TIARA ST 91607

Application / Permit
23014-20000-02990
Plan Check / Job No.
B23VN09983
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
MAJOR INTERIOR REMODELINCLUDE RE-ROOF ENTIRE ROOF,REMOVE MOST INTERIOR WALLS. TO THE EXISTING 2-STORY SINGLE FAMILY DWELLING W/NEW 494 SQFT ADDITION W/ NEW ATTACHED OPEN TRELLIS W/NFPA 13D SPRINKLERS REQUIRED THROUGHOUT.
Permit Issued
Issued on 9/18/2023
Issuing Office
Valley
Current Status
CofO Issued on 8/31/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/26/2023 APPLICANT
Assigned to Plan Check Engineer 8/3/2023 PETER MOSESIAN
Corrections Issued 8/8/2023 PETER MOSESIAN
Quality Review Completed 8/15/2023 OMID HEDAYAT
Building Plans Picked Up 8/17/2023 APPLICANT
Plan Check Approved 9/15/2023 PETER MOSESIAN
Issued 9/18/2023 APPLICANT
CofO in Progress 8/12/2024 OGANES TARAKHCHYAN
Permit Finaled 8/31/2024 DANIEL ORRANTE
CofO Issued 8/31/2024 DANIEL ORRANTE
Permit Finaled 8/31/2024 DANIEL ORRANTE

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 8/23/2023 TAL SHEMEN
Eng Process Fee Ord 176,300 Cleared 9/13/2023 TAL SHEMEN

Contact Information

Contractor Landmark Remodeling Company; Lic. No.: 1053170-B 369 S DOHENY DR SUITE 174      BEVERLY HILLS, CA 90211
Engineer Grigoryan,, Souren; Lic. No.: C93320 6506 TEESDALE AVE      NORTH HOLLYWOOD, CA 91606

Inspector Information

WAYNE REGESTER, (818) 374-1164 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 10/13/2023 Corrections Issued KIRK SANDERS
BUILDING-Rough-Frame 10/23/2023 Corrections Issued CHRISTOPHER ROJAS
Green Building Rough 10/23/2023 Not Ready for Inspection CHRISTOPHER ROJAS
Grounding or Bonding 10/26/2023 Not Ready for Inspection CHRISTOPHER ROJAS
Pool Piping 10/26/2023 Approved CHRISTOPHER ROJAS
Pre-Gunite 10/26/2023 Approved CHRISTOPHER ROJAS
Wood Frame 10/26/2023 Partial Approval CHRISTOPHER ROJAS
Deputy Drilled-In Anchors 10/27/2023 Conditional Approval ROBERT GOLD
Insulation 10/30/2023 Approved CHRISTOPHER ROJAS
Pre-Inspection 10/30/2023 Approved CHRISTOPHER ROJAS
Deputy Drilled-In Anchors 11/1/2023 Conditional Approval JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 11/3/2023 Partial Approval JUAN VALENZUELA
PLUMBING-Rough 12/6/2023 Partial Approval JOSE AVILA
Sewer 12/6/2023 Approved JOSE AVILA
Floor/Roof Diaphrgm/Shear Wall 12/12/2023 Corrections Issued JOSE AVILA
Deputy Wood Construction 12/14/2023 Conditional Approval JUAN VALENZUELA
PLUMBING-Rough 12/27/2023 Not Ready for Inspection MISAEL ESPARZA
Wood Frame 12/27/2023 Not Ready for Inspection MISAEL ESPARZA
Deputy Drilled-In Anchors 1/16/2024 Conditional Approval CRAIG DAVIS
ELECTRICAL-Rough 1/16/2024 Corrections Issued CRAIG DAVIS
Floor/Roof Diaphrgm/Shear Wall 1/16/2024 Partial Approval CRAIG DAVIS
Gas Test 1/16/2024 Not Ready for Inspection CRAIG DAVIS
HVAC-Rough 1/16/2024 Corrections Issued CRAIG DAVIS
PLUMBING-Rough 1/16/2024 Not Ready for Inspection CRAIG DAVIS
Rough-Elec/Plmb/HVAC 1/16/2024 Corrections Issued CRAIG DAVIS
ELECTRICAL-Rough 1/31/2024 Approved JOSE AVILA
HVAC-Rough 1/31/2024 Approved JOSE AVILA
PLUMBING-Rough 1/31/2024 Approved JOSE AVILA
Interior/Exterior Lathing 2/7/2024 Corrections Issued CRAIG DAVIS
Interior/Exterior Lathing 2/12/2024 Not Ready for Inspection CRAIG DAVIS
Wood Frame 2/12/2024 Approved CRAIG DAVIS
Insulation 2/20/2024 Corrections Issued SALVADOR MARTINEZ
Interior/Exterior Lathing 2/20/2024 Partial Approval SALVADOR MARTINEZ
Insulation 2/22/2024 Corrections Issued KIRK SANDERS
Interior/Exterior Lathing 2/22/2024 Partial Approval KIRK SANDERS
Insulation 2/26/2024 Partial Approval SALVADOR MARTINEZ
BUILDING-Rough-Frame 3/13/2024 Approved JOSE AVILA
Drywall Nailing 3/13/2024 Approved JOSE AVILA
Green Building Rough 3/13/2024 Approved JOSE AVILA
Interior/Exterior Lathing 3/13/2024 Approved JOSE AVILA
Shower Pan 3/13/2024 Approved JOSE AVILA
Deck 5/3/2024 Partial Inspection MISAEL ESPARZA
SGSOV-Seismic Gas S/O Valve 7/3/2024 SGSOV Not Ready OGANES TARAKHCHYAN
Final 7/29/2024 Corrections Issued OGANES TARAKHCHYAN
Footing/Foundation/Slab 7/29/2024 Approved OGANES TARAKHCHYAN
SGSOV-Seismic Gas S/O Valve 7/29/2024 SGSOV Not Ready OGANES TARAKHCHYAN
Service/Power Release 7/29/2024 Approved OGANES TARAKHCHYAN
Smoke Detectors 7/29/2024 Approved OGANES TARAKHCHYAN
Final 8/2/2024 Not Ready for Inspection OGANES TARAKHCHYAN
Final 8/7/2024 OK to Issue CofO OGANES TARAKHCHYAN
Green Building Final 8/7/2024 Approved OGANES TARAKHCHYAN
SGSOV-Seismic Gas S/O Valve 8/7/2024 SGSOV Approved OGANES TARAKHCHYAN