23269 W GONZALES DR 91367

Certificate Information: 23269 W GONZALES DR 91367

Application / Permit
23014-20000-02982
Plan Check / Job No.
B23VN09965
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT EXISTING DETACHED GARAGE (365 SQFT) INTO ADU W/2ND STORY ADDITION (328 SQFT) AND ATTACH (e) DETACHED TRELLIS TO ADU PER LAMC 12.22 A.33 (c) (d)
Permit Issued
Issued on 9/26/2023
Issuing Office
Valley
Current Status
CofO Issued on 8/30/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/26/2023 APPLICANT
Assigned to Plan Check Engineer 8/3/2023 PETER MOSESIAN
Corrections Issued 8/5/2023 PETER MOSESIAN
Quality Review Completed 8/10/2023 OMID HEDAYAT
Building Plans Picked Up 8/11/2023 APPLICANT
Plan Check Approved 9/26/2023 PETER MOSESIAN
Issued 9/26/2023 APPLICANT
CofO in Progress 7/15/2024 TROY SANDERS
No Progress 1/17/2025 HENRY KIM
CofO in Progress 1/17/2025 HENRY KIM
Permit Finaled 8/30/2025 RUBEN SALAS
CofO Issued 8/30/2025 RUBEN SALAS
Permit Finaled 8/30/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 8/15/2023 ROMAN GUTIERREZ
Eng Process Fee Ord 176,300 Cleared 8/15/2023 ROMAN GUTIERREZ
Sewer availability Cleared 8/15/2023 ROMAN GUTIERREZ
ZA Case Cleared 8/21/2023 BRENNEN OBETO
Low Impact Development (LID) Cleared 8/30/2023 MELINEH AGHAKHABIAN
Roof/Waste drainage to street Cleared 9/5/2023 DAGOVERTO GUERRERO
Grading Pre-Inspection Cleared 9/20/2023 PETER MOSESIAN

Contact Information

Contractor Pure Builders Inc; Lic. No.: 757470-B 23966 CRAFTSMAN RD      CALABASAS, CA 91302
Engineer Aronianpour,, Eilan; Lic. No.: C88101 7242 JELLICO AVE      LAKE BALBOA, CA 91406

Inspector Information

GEVORK IPCHYAN, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI
TROY SANDERS, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 1/16/2024 Partial Approval TROY SANDERS
ELECTRICAL-Rough 1/18/2024 Not Ready for Inspection TROY SANDERS
PLUMBING-Rough 1/18/2024 Partial Approval TROY SANDERS
Footing/Foundation/Slab 1/23/2024 Approved TROY SANDERS
Floor/Roof Diaphrgm/Shear Wall 1/31/2024 Partial Approval TROY SANDERS
Wood Frame 1/31/2024 Approved TROY SANDERS
BUILDING-Rough-Frame 2/28/2024 Corrections Issued GEVORK IPCHYAN
ELECTRICAL-Rough 2/28/2024 Partial Approval GEVORK IPCHYAN
Floor/Roof Diaphrgm/Shear Wall 2/28/2024 Not Ready for Inspection GEVORK IPCHYAN
Gas Test 2/28/2024 Approved GEVORK IPCHYAN
PLUMBING-Rough 2/28/2024 Approved GEVORK IPCHYAN
Interior/Exterior Lathing 3/8/2024 Approved GEVORK IPCHYAN
Shower Pan 3/8/2024 Approved GEVORK IPCHYAN
Interior/Exterior Lathing 3/18/2024 Approved GEVORK IPCHYAN
Insulation 3/26/2024 Approved GEVORK IPCHYAN
Drywall Nailing 4/2/2024 Approved GEVORK IPCHYAN
Green Building Rough 4/2/2024 Approved GEVORK IPCHYAN
BUILDING-Rough-Frame 6/6/2024 Approved GEVORK IPCHYAN
ELECTRICAL-Final 6/6/2024 Not Ready for Inspection GEVORK IPCHYAN
Final 6/6/2024 Not Ready for Inspection GEVORK IPCHYAN
Green Building Final 6/6/2024 Not Ready for Inspection GEVORK IPCHYAN
HVAC-Final 6/6/2024 Not Ready for Inspection GEVORK IPCHYAN
PLUMBING-Final 6/6/2024 Not Ready for Inspection GEVORK IPCHYAN
SGSOV-Seismic Gas S/O Valve 6/6/2024 SGSOV Not Ready GEVORK IPCHYAN
Smoke Detectors 6/6/2024 Not Ready for Inspection GEVORK IPCHYAN
ELECTRICAL-Final 6/7/2024 Approved GEVORK IPCHYAN
Final 6/7/2024 Corrections Issued GEVORK IPCHYAN
HVAC-Final 6/7/2024 Partial Approval GEVORK IPCHYAN
PLUMBING-Final 6/7/2024 Approved GEVORK IPCHYAN
Final 7/1/2024 Not Ready for Inspection ARUTYUN MADATYAN
Green Building Final 7/1/2024 Not Ready for Inspection ARUTYUN MADATYAN
HVAC-Final 7/1/2024 Approved ARUTYUN MADATYAN
SGSOV-Seismic Gas S/O Valve 7/1/2024 SGSOV Approved ARUTYUN MADATYAN
Smoke Detectors 7/1/2024 Approved ARUTYUN MADATYAN
Final 7/11/2024 OK to Issue CofO TROY SANDERS
Green Building Final 7/11/2024 Approved TROY SANDERS