10418-10420 N DEMPSEY AVE 91344

Certificate Information: 10418-10420 N DEMPSEY AVE 91344

Application / Permit
23014-20000-02943
Plan Check / Job No.
B23VN09831
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
EPLAN: NEW ATTACHED ADU TO EXISTING S.F.D. PER LAMC 12.22 A.33(c) AND (e). DESIGN PER WFPP.
Permit Issued
Issued on 4/19/2024
Issuing Office
Current Status
CofO Issued on 10/16/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/28/2023 APPLICANT
Assigned to Plan Check Engineer 8/31/2023 JOHNPAUL ISIP
Corrections Issued 9/1/2023 JOHNPAUL ISIP
Applicant returned to address corrections 3/19/2024 CAROLEAN BASMA
Plan Check Approved 3/24/2024 CAROLEAN BASMA
Issued 4/19/2024 APPLICANT
CofO in Progress 10/9/2024 JAVIER RAMOS JR
Permit Finaled 10/16/2024 DANIEL ORRANTE
CofO Issued 10/16/2024 DANIEL ORRANTE
Permit Finaled 10/16/2024 DANIEL ORRANTE

Permit Application Clearance Information

Construction near power lines Cleared 12/10/2023 RIDWAN HARDY
Low Impact Development (LID) Cleared 2/28/2024 LUIS CRUZ
Address approval Cleared 3/1/2024 CARLOS RAMIREZ
Roof/Waste drainage to street Cleared 3/1/2024 CARLOS RAMIREZ
Eng Process Fee Ord 176,300 Cleared 3/4/2024 CARLOS RAMIREZ
Sewer availability Cleared 3/4/2024 CARLOS RAMIREZ

Contact Information

Contractor Owner-Builder       ,

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 6/18/2024 Partial Approval MICHEL ABAJAN
Deputy Drilled-In Anchors 6/20/2024 Conditional Approval ROBERT GOLD
Footing/Foundation/Slab 6/24/2024 Approved ROBERT GOLD
Floor/Roof Diaphrgm/Shear Wall 7/8/2024 Partial Approval ROBERT GOLD
BUILDING-Rough-Frame 7/15/2024 Partial Approval JAVIER RAMOS JR
ELECTRICAL-Rough 7/15/2024 Partial Approval JAVIER RAMOS JR
Floor/Roof Diaphrgm/Shear Wall 7/15/2024 Partial Inspection JAVIER RAMOS JR
Green Building Rough 7/15/2024 Approved JAVIER RAMOS JR
HVAC-Rough 7/15/2024 Approved JAVIER RAMOS JR
PLUMBING-Rough 7/15/2024 Partial Approval JAVIER RAMOS JR
Floor/Roof Diaphrgm/Shear Wall 7/19/2024 Approved JAVIER RAMOS JR
Insulation 7/19/2024 Approved JAVIER RAMOS JR
PLUMBING-Rough 7/19/2024 Approved JAVIER RAMOS JR
BUILDING-Rough-Frame 7/31/2024 Approved JAVIER RAMOS JR
Drywall Nailing 7/31/2024 Approved JAVIER RAMOS JR
Interior/Exterior Lathing 7/31/2024 Partial Approval JAVIER RAMOS JR
Sewer 7/31/2024 Approved JAVIER RAMOS JR
Shower Pan 7/31/2024 Approved JAVIER RAMOS JR
Underground Mechanical 7/31/2024 Approved JAVIER RAMOS JR
Interior/Exterior Lathing 8/8/2024 Approved MATTHEW NELSON
ELECTRICAL-Final 9/6/2024 Approved KEVIN BERBERYAN
Final 9/6/2024 Partial Approval KEVIN BERBERYAN
Green Building Final 9/6/2024 Approved KEVIN BERBERYAN
HVAC-Final 9/6/2024 Approved KEVIN BERBERYAN
PLUMBING-Final 9/6/2024 Approved KEVIN BERBERYAN
SGSOV-Seismic Gas S/O Valve 9/6/2024 SGSOV Approved KEVIN BERBERYAN
Smoke Detectors 9/6/2024 Approved KEVIN BERBERYAN
Final 10/9/2024 OK to Issue CofO JAVIER RAMOS JR