6294 N PENFIELD AVE 91367
Certificate Information: 6294 N PENFIELD AVE 91367
- Application / Permit
- 23014-20000-02926
- Plan Check / Job No.
- B23VN09743
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 26' X 13' ATTACHED PATIO COVER AND INTERIOR REMODEL . ADD 2 NEW SKYLIGHTS. WORK DONE PER DESIGN.
- Permit Issued
- Issued on 12/18/2024
- Issuing Office
- Current Status
- Issued on 12/18/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 7/26/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 8/4/2023 | MIROOSH KHACHATOORIAN |
| Corrections Issued | 8/7/2023 | MIROOSH KHACHATOORIAN |
| Applicant returned to address corrections | 9/11/2023 | MIROOSH KHACHATOORIAN |
| Plan Check Approved | 9/14/2023 | MIROOSH KHACHATOORIAN |
| Issued | 12/18/2024 | APPLICANT |
Permit Application Clearance Information
| ZA Case | Cleared | 8/8/2023 | BRENNEN OBETO |
| ZA Case | Cleared | 8/8/2023 | BRENNEN OBETO |
| Roof/Waste drainage to street | Cleared | 8/9/2023 | TAL SHEMEN |
| Eng Process Fee Ord 176,300 | Cleared | 8/10/2023 | TAL SHEMEN |
| Metro Rail approval | Cleared | 8/14/2023 | JENNIFER SU |
| Tract Map conditions | Cleared | 8/29/2023 | BRENNEN OBETO |
Contact Information
| Architect | Dembsky,, Amit; Lic. No.: NA30383 | , |
| Contractor | Buildsmart Construction Inc; Lic. No.: 997887-B | , |
Inspector Information
| JON MCHUGH, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
| IVAN SARABIA, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 1/23/2025 | Not Ready for Inspection | MORRIS JACKSON |
| ELECTRICAL-Rough | 1/23/2025 | Not Ready for Inspection | MORRIS JACKSON |
| Floor/Roof Diaphrgm/Shear Wall | 1/23/2025 | Not Ready for Inspection | MORRIS JACKSON |
| Footing/Foundation/Slab | 1/23/2025 | Corrections Issued | MORRIS JACKSON |
| Interior/Exterior Lathing | 1/23/2025 | Not Ready for Inspection | MORRIS JACKSON |
| PLUMBING-Rough | 1/23/2025 | Not Ready for Inspection | MORRIS JACKSON |
| Wood Frame | 1/23/2025 | Not Ready for Inspection | MORRIS JACKSON |
| Deputy Drilled-In Anchors | 1/24/2025 | Conditional Approval | MORRIS JACKSON |
| Deputy Wood Construction | 1/24/2025 | Conditional Approval | MORRIS JACKSON |
| BUILDING-Rough-Frame | 2/5/2025 | Not Ready for Inspection | MORRIS JACKSON |
| ELECTRICAL-Rough | 2/5/2025 | Not Ready for Inspection | MORRIS JACKSON |
| Floor/Roof Diaphrgm/Shear Wall | 2/5/2025 | Not Ready for Inspection | MORRIS JACKSON |
| Footing/Foundation/Slab | 2/5/2025 | Approved | MORRIS JACKSON |
| Interior/Exterior Lathing | 2/5/2025 | Not Ready for Inspection | MORRIS JACKSON |
| PLUMBING-Rough | 2/5/2025 | Partial Approval | MORRIS JACKSON |
| Wood Frame | 2/5/2025 | Not Ready for Inspection | MORRIS JACKSON |
| BUILDING-Rough-Frame | 2/10/2025 | Partial Inspection | MORRIS JACKSON |
| Floor/Roof Diaphrgm/Shear Wall | 2/10/2025 | Partial Approval | MORRIS JACKSON |
| Interior/Exterior Lathing | 2/10/2025 | Partial Approval | MORRIS JACKSON |
| Rough-Elec/Plmb/HVAC | 2/10/2025 | Partial Approval | MORRIS JACKSON |
| Wood Frame | 2/10/2025 | Partial Approval | MORRIS JACKSON |
| BUILDING-Rough-Frame | 2/13/2025 | Partial Approval | MORRIS JACKSON |
| Drywall Nailing | 2/13/2025 | Partial Approval | MORRIS JACKSON |
| Green Building Rough | 2/13/2025 | Partial Approval | MORRIS JACKSON |
| Interior/Exterior Lathing | 2/13/2025 | Partial Approval | MORRIS JACKSON |
| Deputy Drilled-In Anchors | 5/15/2026 | Conditional Approval | HENRY KIM |
| Deputy Wood Construction | 5/15/2026 | Conditional Approval | HENRY KIM |
| ELECTRICAL-Rough | 6/4/2026 | Approved | JON MCHUGH |
| Floor/Roof Diaphrgm/Shear Wall | 6/4/2026 | Partial Approval | JON MCHUGH |
| Footing/Foundation/Slab | 6/4/2026 | Corrections Issued | JON MCHUGH |
| PLUMBING-Rough | 6/4/2026 | Partial Approval | JON MCHUGH |