7808 N WOODHALL AVE 91304
Certificate Information: 7808 N WOODHALL AVE 91304
- Application / Permit
- 23014-20000-02918
- Plan Check / Job No.
- B23VN09724
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 10' X 11'5" ADDITION TO (E) 2-STORY SINGLE FAMILY DWELLING TO EXTEND FIRST FLOOR DINING ROOM. WORK DONE PER ENGINEER.
- Permit Issued
- Issued on 10/2/2023
- Issuing Office
- Current Status
- Issued on 10/2/2023
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 8/3/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 8/9/2023 | MADISON ODELL |
| Corrections Issued | 8/11/2023 | MADISON ODELL |
| Applicant returned to address corrections | 9/22/2023 | MADISON ODELL |
| Plan Check Approved | 9/29/2023 | MADISON ODELL |
| Issued | 10/2/2023 | APPLICANT |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 9/12/2023 | SERGIO VALENZUELA |
| Roof/Waste drainage to street | Cleared | 9/15/2023 | MEGAN GODINEZ |
| Eng Process Fee Ord 176,300 | Cleared | 9/18/2023 | MEGAN GODINEZ |
| Tract Map conditions | Cleared | 9/20/2023 | DAVID URITA |
Contact Information
| Contractor | Rp Build Corp Corporation; Lic. No.: 937670-B | , |
| Engineer | Mercado,, Lizandro; Lic. No.: S4331 | 27240 TURNBERRY LN STE 200 VALENCIA, CA 91355 |
Inspector Information
| JEFFREY HARTLINE, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRIS CHRISTENSEN, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 1/23/2024 | Conditional Approval | CHRIS CHRISTENSEN |
| Deputy Reinf. Concrete | 1/25/2024 | Conditional Approval | CHRIS CHRISTENSEN |
| ELECTRICAL-Rough | 3/5/2024 | Approved | CHRIS CHRISTENSEN |
| Floor/Roof Diaphrgm/Shear Wall | 3/5/2024 | Approved | CHRIS CHRISTENSEN |
| Insulation | 3/5/2024 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Wood Frame | 3/5/2024 | Approved | CHRIS CHRISTENSEN |
| Insulation | 3/18/2024 | Approved | CHRIS CHRISTENSEN |
| Interior/Exterior Lathing | 3/18/2024 | Approved | CHRIS CHRISTENSEN |
| Drywall Nailing | 3/26/2024 | Approved | CHRIS CHRISTENSEN |