5132 N LINDLEY AVE 91316

Certificate Information: 5132 N LINDLEY AVE 91316

Application / Permit
23014-20000-02917
Plan Check / Job No.
B23VN09722
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
REMOVE 1169 SF EXCEPT FOR 3' OF WALL AND FOUNDATION TO REMAIN AT NORTH. REBUILD 38' X 64'-4" 2-STORY SFD W/ 2-CAR GARAGE W/ ADDITIONS. NFPA 13D FIRE SPRINKLERS THROUGHOUT. ALL WORK PER ENGINEERING.
Permit Issued
Issued on 10/23/2023
Issuing Office
Valley
Current Status
CofO Issued on 2/13/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/21/2023 APPLICANT
Assigned to Plan Check Engineer 8/3/2023 RAPHAEL ROSAS
Corrections Issued 8/14/2023 RAPHAEL ROSAS
Quality Review Completed 8/15/2023 STEVEN KIM
Building Plans Picked Up 8/16/2023 APPLICANT
Plan Check Approved 10/23/2023 RAPHAEL ROSAS
Issued 10/23/2023 APPLICANT
CofO in Progress 7/18/2024 JOHN KIDWELL
No Progress 1/15/2025 SEAN WIRCH
CofO in Progress 1/15/2025 SEAN WIRCH
Permit Finaled 2/13/2025 JOHN JANSON
CofO Issued 2/13/2025 JOHN JANSON
Permit Finaled 2/13/2025 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 8/26/2023 ROMAN GUTIERREZ
Permit Cleared 8/26/2023 ROMAN GUTIERREZ
Eng Process Fee Ord 176,300 Cleared 8/28/2023 ROMAN GUTIERREZ
Sewer availability Cleared 8/28/2023 ROMAN GUTIERREZ
Low Impact Development (LID) Cleared 9/5/2023 SAMUEL LINN
Roof/Waste drainage to street Cleared 9/8/2023 ROMAN GUTIERREZ
Trees in Parkway Cleared 9/12/2023 ADALBERTO VERA
Hydrant and Access approval Cleared 9/14/2023 LAVEON RIDER
GPI Written Notices Cleared 10/23/2023 RAPHAEL ROSAS
Grading Pre-Inspection Cleared 10/23/2023 RAPHAEL ROSAS

Contact Information

Contractor Owner-Builder       ,
Engineer Grigoryan,, Souren; Lic. No.: C93320 6506 TEESDALE AVE      NORTH HOLLYWOOD, CA 91606

Inspector Information

JOHN KIDWELL, (818) 774-4314 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 11/6/2023 Approved SEAN HAUPT
Deputy Drilled-In Anchors 11/14/2023 Approved SEAN HAUPT
Footing/Foundation/Slab 11/15/2023 Not Ready for Inspection SEAN HAUPT
Excavation/Setback/Form/Re-Bar 11/17/2023 Partial Approval SEAN HAUPT
Deputy Reinf. Concrete 11/27/2023 Approved SEAN HAUPT
Footing/Foundation/Slab 11/28/2023 Approved SEAN HAUPT
Deputy Reinf. Concrete 11/30/2023 Approved SEAN HAUPT
Deputy Wood Construction 12/26/2023 Approved SEAN HAUPT
Floor/Roof Diaphrgm/Shear Wall 12/27/2023 Approved SEAN HAUPT
Underground Mechanical 12/27/2023 Approved SEAN HAUPT
Deputy Reinf. Concrete 12/28/2023 Approved SEAN HAUPT
Floor/Roof Diaphrgm/Shear Wall 1/12/2024 Not Ready for Inspection MORRIS JACKSON
Floor/Roof Diaphrgm/Shear Wall 1/18/2024 Approved SEAN HAUPT
Underground Mechanical 1/18/2024 Approved SEAN HAUPT
Deputy Wood Construction 1/30/2024 Partial Approval SEAN WIRCH
ELECTRICAL-Rough 2/2/2024 Not Ready for Inspection SEAN HAUPT
Floor/Roof Diaphrgm/Shear Wall 2/2/2024 Corrections Issued SEAN HAUPT
PLUMBING-Rough 2/2/2024 Not Ready for Inspection SEAN HAUPT
Floor/Roof Diaphrgm/Shear Wall 2/7/2024 Approved SEAN HAUPT
PLUMBING-Rough 2/7/2024 Approved SEAN HAUPT
ELECTRICAL-Rough 2/8/2024 Corrections Issued SEAN HAUPT
ELECTRICAL-Rough 2/9/2024 Not Ready for Inspection JOHN KIDWELL
HVAC-Rough 2/9/2024 Not Ready for Inspection JOHN KIDWELL
Shower Pan 2/12/2024 Approved JOHN KIDWELL
Deputy Steel/Welding 2/13/2024 Partial Approval JOHN KIDWELL
ELECTRICAL-Rough 2/16/2024 Approved JOHN KIDWELL
HVAC-Rough 2/16/2024 Approved JOHN KIDWELL
Deputy Steel/Welding 2/20/2024 Partial Approval JOHN KIDWELL
BUILDING-Rough-Frame 2/22/2024 Not Ready for Inspection GEVORK IPCHYAN
Green Building Rough 2/22/2024 Not Ready for Inspection GEVORK IPCHYAN
Interior/Exterior Lathing 2/22/2024 Not Ready for Inspection GEVORK IPCHYAN
BUILDING-Rough-Frame 2/26/2024 Approved JOHN KIDWELL
Green Building Rough 2/26/2024 Approved JOHN KIDWELL
Interior/Exterior Lathing 2/26/2024 Partial Approval JOHN KIDWELL
Verify Sprinkler Sign Off 2/26/2024 Approved JOHN KIDWELL
Drywall Nailing 3/7/2024 Approved JOHN KIDWELL
Insulation 3/7/2024 Approved JOHN KIDWELL
Interior/Exterior Lathing 3/11/2024 Partial Approval JOHN KIDWELL
Gas Test 5/21/2024 Approved JOHN KIDWELL
ELECTRICAL-Final 6/13/2024 Approved JOHN KIDWELL
Final 7/12/2024 Corrections Issued JOHN KIDWELL
Green Building Final 7/12/2024 Approved JOHN KIDWELL
SGSOV-Seismic Gas S/O Valve 7/12/2024 SGSOV Approved JOHN KIDWELL
Smoke Detectors 7/12/2024 Approved JOHN KIDWELL
Final 7/17/2024 OK to Issue CofO JOHN KIDWELL
Service/Power Release 7/18/2024 Approved JOHN KIDWELL