5858 N VINELAND AVE 91601

Certificate Information: 5858 N VINELAND AVE 91601

Application / Permit
23014-20000-02892
Plan Check / Job No.
B23VN09632
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan: New two story ADU over existing garage per Ordinance LAMC 12.22 A.33 (c)-(d)
Permit Issued
Issued on 2/9/2024
Issuing Office
Current Status
CofO Issued on 7/8/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/19/2023 APPLICANT
Assigned to Plan Check Engineer 8/3/2023 YASHAR EMAMI
Corrections Issued 8/7/2023 YASHAR EMAMI
Quality Review Completed 8/15/2023 KAVIAN REFAHI
Applicant returned to address corrections 10/2/2023 YASHAR EMAMI
Applicant returned to address corrections 11/3/2023 YASHAR EMAMI
Applicant returned to address corrections 12/1/2023 YASHAR EMAMI
Applicant returned to address corrections 12/14/2023 YASHAR EMAMI
Applicant returned to address corrections 12/29/2023 YASHAR EMAMI
Applicant returned to address corrections 1/5/2024 YASHAR EMAMI
Applicant returned to address corrections 1/25/2024 YASHAR EMAMI
Plan Check Approved 2/6/2024 YASHAR EMAMI
Issued 2/9/2024 APPLICANT
CofO in Progress 6/6/2025 JOSE AVILA
Permit Finaled 7/8/2025 RUBEN SALAS
CofO Issued 7/8/2025 RUBEN SALAS
Permit Finaled 7/8/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 8/26/2023 ROMAN GUTIERREZ
Eng Process Fee Ord 176,300 Cleared 8/28/2023 ROMAN GUTIERREZ
Sewer availability Cleared 8/28/2023 ROMAN GUTIERREZ
Frnt yard landscape/Water mgmt Cleared 8/30/2023 BRENNEN OBETO
Low Impact Development (LID) Cleared 11/6/2023 SAMUEL LINN
Roof/Waste drainage to street Cleared 12/13/2023 BRYAN GODINEZ

Contact Information

Contractor Lorenzo Design Group Inc; Lic. No.: 530201-B       ,
Engineer Reith,, David Lee; Lic. No.: C72122 1319 FEATHER AVE      THOUSAND OAKS, CA 91360

Inspector Information

GAREN HAYRAPETYAN, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI
ROBERTO PALACIOS-LOPEZ, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 3/5/2024 Conditional Approval ROBERT GOLD
Footing/Foundation/Slab 3/14/2024 Corrections Issued JOHN HAYES
Footing/Foundation/Slab 3/20/2024 Partial Approval JOHN HAYES
Special/Order Compliance 3/20/2024 Corrections Issued JOHN HAYES
ELECTRICAL-Rough 4/1/2024 Not Ready for Inspection JOHN HAYES
PLUMBING-Rough 6/20/2024 Corrections Issued JOSE AVILA
Sewer 6/20/2024 Approved JOSE AVILA
Underground Mechanical 6/20/2024 Approved JOSE AVILA
Underground Mechanical 6/25/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
ELECTRICAL-Rough 7/9/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Floor/Roof Diaphrgm/Shear Wall 7/9/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
ELECTRICAL-Rough 7/11/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Underground Mechanical 7/11/2024 Approved ROBERTO PALACIOS-LOPEZ
BUILDING-Rough-Frame 7/22/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Floor/Roof Diaphrgm/Shear Wall 7/25/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Floor/Roof Diaphrgm/Shear Wall 9/3/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
ELECTRICAL-Rough 9/6/2024 Approved MISAEL ESPARZA
HVAC-Rough 9/6/2024 Corrections Issued MISAEL ESPARZA
PLUMBING-Rough 9/6/2024 Partial Approval MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 9/18/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
HVAC-Rough 9/18/2024 Not Ready for Inspection JOSE AVILA
Floor/Roof Diaphrgm/Shear Wall 9/26/2024 Partial Approval ROBERTO PALACIOS-LOPEZ
BUILDING-Rough-Frame 10/9/2024 Conditional Approval ROBERTO PALACIOS-LOPEZ
Floor/Roof Diaphrgm/Shear Wall 10/9/2024 Approved ROBERTO PALACIOS-LOPEZ
HVAC-Rough 10/9/2024 Approved ROBERTO PALACIOS-LOPEZ
Insulation 10/9/2024 Approved ROBERTO PALACIOS-LOPEZ
Interior/Exterior Lathing 10/9/2024 Partial Approval ROBERTO PALACIOS-LOPEZ
PLUMBING-Rough 10/9/2024 Approved ROBERTO PALACIOS-LOPEZ
Drywall Nailing 10/21/2024 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
Shower Pan 11/21/2024 Approved ROBERTO PALACIOS-LOPEZ
ELECTRICAL-Final 2/4/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Final 2/4/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
HVAC-Final 2/4/2025 Approved ROBERTO PALACIOS-LOPEZ
PLUMBING-Final 2/4/2025 Approved ROBERTO PALACIOS-LOPEZ
Service/Power Release 2/4/2025 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
Smoke Detectors 2/4/2025 Approved ROBERTO PALACIOS-LOPEZ
BUILDING-Rough-Frame 2/11/2025 Approved ROBERTO PALACIOS-LOPEZ
ELECTRICAL-Final 2/11/2025 Approved ROBERTO PALACIOS-LOPEZ
Footing/Foundation/Slab 2/11/2025 Approved ROBERTO PALACIOS-LOPEZ
SGSOV-Seismic Gas S/O Valve 2/11/2025 SGSOV Not Ready ROBERTO PALACIOS-LOPEZ
Final 3/17/2025 Corrections Issued JOSE AVILA
Gas Test 3/17/2025 Approved JOSE AVILA
Final 3/20/2025 Corrections Issued JOSE AVILA
SGSOV-Seismic Gas S/O Valve 3/20/2025 SGSOV Approved JOSE AVILA
Final 6/5/2025 OK to Issue CofO JOSE AVILA