5858 N VINELAND AVE 91601
Certificate Information: 5858 N VINELAND AVE 91601
- Application / Permit
- 23014-20000-02892
- Plan Check / Job No.
- B23VN09632
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan: New two story ADU over existing garage per Ordinance LAMC 12.22 A.33 (c)-(d)
- Permit Issued
- Issued on 2/9/2024
- Issuing Office
- Current Status
- CofO Issued on 7/8/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/19/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 8/3/2023 | YASHAR EMAMI |
| Corrections Issued | 8/7/2023 | YASHAR EMAMI |
| Quality Review Completed | 8/15/2023 | KAVIAN REFAHI |
| Applicant returned to address corrections | 10/2/2023 | YASHAR EMAMI |
| Applicant returned to address corrections | 11/3/2023 | YASHAR EMAMI |
| Applicant returned to address corrections | 12/1/2023 | YASHAR EMAMI |
| Applicant returned to address corrections | 12/14/2023 | YASHAR EMAMI |
| Applicant returned to address corrections | 12/29/2023 | YASHAR EMAMI |
| Applicant returned to address corrections | 1/5/2024 | YASHAR EMAMI |
| Applicant returned to address corrections | 1/25/2024 | YASHAR EMAMI |
| Plan Check Approved | 2/6/2024 | YASHAR EMAMI |
| Issued | 2/9/2024 | APPLICANT |
| CofO in Progress | 6/6/2025 | JOSE AVILA |
| Permit Finaled | 7/8/2025 | RUBEN SALAS |
| CofO Issued | 7/8/2025 | RUBEN SALAS |
| Permit Finaled | 7/8/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 8/26/2023 | ROMAN GUTIERREZ |
| Eng Process Fee Ord 176,300 | Cleared | 8/28/2023 | ROMAN GUTIERREZ |
| Sewer availability | Cleared | 8/28/2023 | ROMAN GUTIERREZ |
| Frnt yard landscape/Water mgmt | Cleared | 8/30/2023 | BRENNEN OBETO |
| Low Impact Development (LID) | Cleared | 11/6/2023 | SAMUEL LINN |
| Roof/Waste drainage to street | Cleared | 12/13/2023 | BRYAN GODINEZ |
Contact Information
| Contractor | Lorenzo Design Group Inc; Lic. No.: 530201-B | , |
| Engineer | Reith,, David Lee; Lic. No.: C72122 | 1319 FEATHER AVE THOUSAND OAKS, CA 91360 |
Inspector Information
| GAREN HAYRAPETYAN, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERTO PALACIOS-LOPEZ, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 3/5/2024 | Conditional Approval | ROBERT GOLD |
| Footing/Foundation/Slab | 3/14/2024 | Corrections Issued | JOHN HAYES |
| Footing/Foundation/Slab | 3/20/2024 | Partial Approval | JOHN HAYES |
| Special/Order Compliance | 3/20/2024 | Corrections Issued | JOHN HAYES |
| ELECTRICAL-Rough | 4/1/2024 | Not Ready for Inspection | JOHN HAYES |
| PLUMBING-Rough | 6/20/2024 | Corrections Issued | JOSE AVILA |
| Sewer | 6/20/2024 | Approved | JOSE AVILA |
| Underground Mechanical | 6/20/2024 | Approved | JOSE AVILA |
| Underground Mechanical | 6/25/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| ELECTRICAL-Rough | 7/9/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Floor/Roof Diaphrgm/Shear Wall | 7/9/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| ELECTRICAL-Rough | 7/11/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Underground Mechanical | 7/11/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| BUILDING-Rough-Frame | 7/22/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Floor/Roof Diaphrgm/Shear Wall | 7/25/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Floor/Roof Diaphrgm/Shear Wall | 9/3/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| ELECTRICAL-Rough | 9/6/2024 | Approved | MISAEL ESPARZA |
| HVAC-Rough | 9/6/2024 | Corrections Issued | MISAEL ESPARZA |
| PLUMBING-Rough | 9/6/2024 | Partial Approval | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 9/18/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| HVAC-Rough | 9/18/2024 | Not Ready for Inspection | JOSE AVILA |
| Floor/Roof Diaphrgm/Shear Wall | 9/26/2024 | Partial Approval | ROBERTO PALACIOS-LOPEZ |
| BUILDING-Rough-Frame | 10/9/2024 | Conditional Approval | ROBERTO PALACIOS-LOPEZ |
| Floor/Roof Diaphrgm/Shear Wall | 10/9/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| HVAC-Rough | 10/9/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| Insulation | 10/9/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| Interior/Exterior Lathing | 10/9/2024 | Partial Approval | ROBERTO PALACIOS-LOPEZ |
| PLUMBING-Rough | 10/9/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| Drywall Nailing | 10/21/2024 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| Shower Pan | 11/21/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| ELECTRICAL-Final | 2/4/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Final | 2/4/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| HVAC-Final | 2/4/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| PLUMBING-Final | 2/4/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| Service/Power Release | 2/4/2025 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| Smoke Detectors | 2/4/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| BUILDING-Rough-Frame | 2/11/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| ELECTRICAL-Final | 2/11/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| Footing/Foundation/Slab | 2/11/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 2/11/2025 | SGSOV Not Ready | ROBERTO PALACIOS-LOPEZ |
| Final | 3/17/2025 | Corrections Issued | JOSE AVILA |
| Gas Test | 3/17/2025 | Approved | JOSE AVILA |
| Final | 3/20/2025 | Corrections Issued | JOSE AVILA |
| SGSOV-Seismic Gas S/O Valve | 3/20/2025 | SGSOV Approved | JOSE AVILA |
| Final | 6/5/2025 | OK to Issue CofO | JOSE AVILA |