7647 W HILLROSE ST 91042
Certificate Information: 7647 W HILLROSE ST 91042
- Application / Permit
- 23014-20000-02886
- Plan Check / Job No.
- B23VN09603
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Add 21'-3" x 20'-6" irregular shape Second Story to existing attached garage and convert garage and second story to 2-story attached ADU per LAMC 12.22 A.33(c) and (e). SFD address: 7644 W Owens St, ADU address: 7647 W Hillrose St.
- Permit Issued
- Issued on 8/28/2023
- Issuing Office
- Valley
- Current Status
- CofO Corrected on 3/25/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/19/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 7/20/2023 | VAHAN JIVALAGIAN |
| Corrections Issued | 7/21/2023 | VAHAN JIVALAGIAN |
| Quality Review Completed | 7/27/2023 | OMID HEDAYAT |
| Building Plans Picked Up | 7/31/2023 | APPLICANT |
| Applicant returned to address corrections | 8/10/2023 | VAHAN JIVALAGIAN |
| Applicant returned to address corrections | 8/18/2023 | VAHAN JIVALAGIAN |
| Applicant returned to address corrections | 8/22/2023 | VAHAN JIVALAGIAN |
| Plan Check Approved | 8/22/2023 | VAHAN JIVALAGIAN |
| Issued | 8/28/2023 | APPLICANT |
| CofO in Progress | 10/29/2024 | WILLIAM WREN |
| CofO Issued-Status Void | 11/14/2024 | DANIEL ORRANTE |
| Permit Finaled-Status Void | 11/14/2024 | DANIEL ORRANTE |
| Re-Activate Permit | 3/20/2025 | RUBEN SALAS |
| Permit Finaled | 3/25/2025 | RUBEN SALAS |
| CofO Corrected | 3/25/2025 | RUBEN SALAS |
| Permit Finaled | 3/25/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 8/2/2023 | CARLOS AGUILERA |
| Roof/Waste drainage to street | Cleared | 8/2/2023 | CARLOS AGUILERA |
| Watercourse | Cleared | 8/2/2023 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 8/3/2023 | CARLOS AGUILERA |
| Sewer availability | Cleared | 8/3/2023 | CARLOS AGUILERA |
| Construction near power lines | Cleared | 8/7/2023 | NADER ISKANDER |
| GPI Written Notices | Cleared | 8/22/2023 | VAHAN JIVALAGIAN |
| Grading Pre-Inspection | Cleared | 8/22/2023 | VAHAN JIVALAGIAN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Towers,, Kevin; Lic. No.: S6625 | 6121 IROQUOIS RD WESTMINSTER, CA 92683 |
Inspector Information
| NICHOLAS TROWBRIDGE, (818) 374-1174 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 10/13/2023 | Approved | CHRISTOPHER ROJAS |
| Underground Mechanical | 10/13/2023 | Approved | CHRISTOPHER ROJAS |
| Deputy Drilled-In Anchors | 11/1/2023 | Conditional Approval | DAVID MATSON |
| Excavation/Setback/Form/Re-Bar | 11/6/2023 | Corrections Issued | WILLIAM WREN |
| Footing/Foundation/Slab | 11/6/2023 | Corrections Issued | WILLIAM WREN |
| Excavation/Setback/Form/Re-Bar | 1/19/2024 | Approved | WILLIAM WREN |
| Floor/Roof Diaphrgm/Shear Wall | 2/13/2024 | Partial Approval | CHRISTOPHER ROJAS |
| Green Building Rough | 2/13/2024 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| Underground Mechanical | 2/13/2024 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| Floor/Roof Diaphrgm/Shear Wall | 2/26/2024 | Corrections Issued | WILLIAM WREN |
| Wood Frame | 2/26/2024 | Corrections Issued | WILLIAM WREN |
| BUILDING-Rough-Frame | 3/4/2024 | Not Ready for Inspection | WILLIAM WREN |
| Floor/Roof Diaphrgm/Shear Wall | 3/4/2024 | Partial Approval | WILLIAM WREN |
| Green Building Rough | 3/4/2024 | Not Ready for Inspection | WILLIAM WREN |
| ELECTRICAL-Rough | 4/8/2024 | Corrections Issued | WILLIAM WREN |
| HVAC-Rough | 4/8/2024 | Corrections Issued | WILLIAM WREN |
| PLUMBING-Rough | 4/8/2024 | Approved | WILLIAM WREN |
| BUILDING-Rough-Frame | 4/16/2024 | Approved | WILLIAM WREN |
| Green Building Rough | 4/16/2024 | Approved | WILLIAM WREN |
| Deputy Wood Construction | 4/19/2024 | Conditional Approval | ROBERT GOLD |
| Floor/Roof Diaphrgm/Shear Wall | 4/22/2024 | Partial Approval | WILLIAM WREN |
| Insulation | 4/22/2024 | Approved | WILLIAM WREN |
| Drywall Nailing | 4/30/2024 | Approved | WILLIAM WREN |
| Interior/Exterior Lathing | 4/30/2024 | Approved | WILLIAM WREN |
| Interior/Exterior Lathing | 5/14/2024 | Approved | WILLIAM WREN |
| SGSOV-Seismic Gas S/O Valve | 8/5/2024 | SGSOV Not Ready | WILLIAM WREN |
| Final | 8/12/2024 | OK to Issue CofO | WILLIAM WREN |
| Footing/Foundation/Slab | 8/12/2024 | Approved | WILLIAM WREN |
| Green Building Final | 8/12/2024 | Approved | WILLIAM WREN |
| SGSOV-Seismic Gas S/O Valve | 8/12/2024 | SGSOV Approved | WILLIAM WREN |
| Service/Power Release | 8/12/2024 | Approved | WILLIAM WREN |
| Smoke Detectors | 8/12/2024 | Approved | WILLIAM WREN |