8150 N RANCHITO AVE 91402
Certificate Information: 8150 N RANCHITO AVE 91402
- Application / Permit
- 23014-20000-02883
- Plan Check / Job No.
- B23VN09596
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 8'-11" X 25'-0" ADDITION TO & REMODEL OF (E) SINGLE FAMILY DWELLING. WORK DONE PER ENGINEERING.
- Permit Issued
- Issued on 8/4/2023
- Issuing Office
- Current Status
- CofO Issued on 5/18/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/19/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 7/24/2023 | JESSE ARELLANO |
| Corrections Issued | 7/25/2023 | JESSE ARELLANO |
| Building Plans Picked Up | 7/26/2023 | APPLICANT |
| Applicant returned to address corrections | 7/31/2023 | MIROOSH KHACHATOORIAN |
| Applicant returned to address corrections | 8/1/2023 | ALEC MOUSAKHANIAN |
| Plan Check Approved | 8/3/2023 | MADISON ODELL |
| Issued | 8/4/2023 | APPLICANT |
| CofO in Progress | 5/16/2024 | GREGG CUMMINGS |
| Permit Finaled | 5/18/2024 | RUBEN SALAS |
| CofO Issued | 5/18/2024 | RUBEN SALAS |
| Permit Finaled | 5/18/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 7/27/2023 | FERNANDO GIL |
| Eng Process Fee Ord 176,300 | Cleared | 7/31/2023 | FERNANDO GIL |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Grigoryan,, Souren; Lic. No.: C93320 | 6506 TEESDALE AVE NORTH HOLLYWOOD, CA 91606 |
Inspector Information
| OGANES TARAKHCHYAN, (818) 374-1162 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 8/14/2023 | Not Ready for Inspection | MATTHEW NELSON |
| Excavation/Setback/Form/Re-Bar | 8/16/2023 | Approved | GREGG CUMMINGS |
| Footing/Foundation/Slab | 8/16/2023 | Approved | GREGG CUMMINGS |
| PLUMBING-Rough | 9/8/2023 | Partial Approval | GREGG CUMMINGS |
| Sewer | 9/8/2023 | Approved | GREGG CUMMINGS |
| PLUMBING-Rough | 9/14/2023 | Partial Approval | CHRISTOPHER ROJAS |
| BUILDING-Rough-Frame | 9/15/2023 | Corrections Issued | CHRISTOPHER ROJAS |
| Green Building Rough | 9/15/2023 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| Floor/Roof Diaphrgm/Shear Wall | 9/18/2023 | Partial Approval | DAVID MATSON |
| Floor/Roof Diaphrgm/Shear Wall | 10/3/2023 | Partial Approval | GREGG CUMMINGS |
| Interior/Exterior Lathing | 10/3/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| Deputy Wood Construction | 10/10/2023 | Conditional Approval | DAVID MATSON |
| BUILDING-Rough-Frame | 10/18/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| ELECTRICAL-Rough | 10/18/2023 | Approved | GREGG CUMMINGS |
| Green Building Rough | 10/18/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| HVAC-Rough | 10/18/2023 | Corrections Issued | GREGG CUMMINGS |
| PLUMBING-Rough | 10/18/2023 | Approved | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 10/30/2023 | Approved | GREGG CUMMINGS |
| Green Building Rough | 10/30/2023 | Approved | GREGG CUMMINGS |
| HVAC-Rough | 10/30/2023 | Approved | GREGG CUMMINGS |
| Insulation | 11/8/2023 | Approved | GREGG CUMMINGS |
| Interior/Exterior Lathing | 11/8/2023 | Approved | GREGG CUMMINGS |
| Shower Pan | 11/8/2023 | Approved | GREGG CUMMINGS |
| Drywall Nailing | 11/22/2023 | Approved | GREGG CUMMINGS |
| Final | 1/22/2024 | Corrections Issued | GREGG CUMMINGS |
| Green Building Final | 1/22/2024 | Approved | GREGG CUMMINGS |
| SGSOV-Seismic Gas S/O Valve | 1/22/2024 | SGSOV Approved | GREGG CUMMINGS |
| Smoke Detectors | 1/22/2024 | Approved | GREGG CUMMINGS |
| ELECTRICAL-Final | 5/15/2024 | Approved | GREGG CUMMINGS |
| Final | 5/15/2024 | OK to Issue CofO | GREGG CUMMINGS |
| HVAC-Final | 5/15/2024 | Approved | GREGG CUMMINGS |
| PLUMBING-Final | 5/15/2024 | Approved | GREGG CUMMINGS |