5214 N NOBLE AVE 91411
Certificate Information: 5214 N NOBLE AVE 91411
- Application / Permit
- 23014-20000-02865
- Plan Check / Job No.
- B23VN09565
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- 18' X 19' IRREGULAR SHAPED ADDITION, EXTERIOR ALTERATION TO DEMO 13 SF PORTION AND CONVERT (E) DETACHED GARAGE TO (N) 625 SF ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d) ALL WORK PER ENG.
- Permit Issued
- Issued on 12/27/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 5/13/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/18/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 7/24/2023 | JEROME MAGAT PALMA |
| Corrections Issued | 7/25/2023 | JEROME MAGAT PALMA |
| Building Plans Picked Up | 7/26/2023 | APPLICANT |
| Applicant returned to address corrections | 12/15/2023 | ANGELICA DAVE |
| Issued | 12/27/2023 | APPLICANT |
| CofO in Progress | 4/17/2025 | JACK KARGODORIAN |
| Permit Finaled | 5/13/2025 | RUBEN SALAS |
| CofO Issued | 5/13/2025 | RUBEN SALAS |
| Permit Finaled | 5/13/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 8/2/2023 | ROMAN GUTIERREZ |
| Roof/Waste drainage to street | Cleared | 8/2/2023 | ROMAN GUTIERREZ |
| Eng Process Fee Ord 176,300 | Cleared | 8/4/2023 | ROMAN GUTIERREZ |
| Sewer availability | Cleared | 8/9/2023 | ROMAN GUTIERREZ |
| Construction near power lines | Cleared | 11/29/2023 | RIDWAN HARDY |
Contact Information
| Contractor | Seamless Construction Inc; Lic. No.: 1089475-B | 4343 VON KARMAN AVE 150F NEWPORT BEACH, CA 92660 |
| Engineer | Ramirez, Cid, Jose Carlos; Lic. No.: C91046 | 5164 N RATON CIR LONG BEACH, CA 90807 |
Inspector Information
| RAUL OLAGI, (818) 374-1166 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 6/18/2024 | No Access for Inspection | PETER FOLLING |
| Footing/Foundation/Slab | 6/18/2024 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Rough | 6/18/2024 | Partial Approval | JENNIFER RABUCHIN |
| Sewer | 6/18/2024 | Partial Approval | JENNIFER RABUCHIN |
| Deputy Drilled-In Anchors | 7/16/2024 | Conditional Approval | ROBERT GOLD |
| BUILDING-Rough-Frame | 8/16/2024 | Not Ready for Inspection | SALVADOR MARTINEZ |
| Floor/Roof Diaphrgm/Shear Wall | 8/16/2024 | Corrections Issued | SALVADOR MARTINEZ |
| Green Building Rough | 8/16/2024 | Not Ready for Inspection | SALVADOR MARTINEZ |
| PLUMBING-Rough | 8/16/2024 | Corrections Issued | SALVADOR MARTINEZ |
| Underground Mechanical | 8/16/2024 | Corrections Issued | SALVADOR MARTINEZ |
| ELECTRICAL-Rough | 9/3/2024 | Approved | JACK KARGODORIAN |
| Floor/Roof Diaphrgm/Shear Wall | 9/3/2024 | Partial Approval | JACK KARGODORIAN |
| PLUMBING-Rough | 9/3/2024 | Approved | JACK KARGODORIAN |
| Wood Frame | 9/3/2024 | Corrections Issued | JACK KARGODORIAN |
| BUILDING-Rough-Frame | 9/13/2024 | Approved | JACK KARGODORIAN |
| Green Building Rough | 9/13/2024 | Approved | JACK KARGODORIAN |
| HVAC-Rough | 9/13/2024 | Approved | JACK KARGODORIAN |
| Insulation | 9/19/2024 | Approved | JACK KARGODORIAN |
| Underground Mechanical | 9/19/2024 | Approved | JACK KARGODORIAN |
| Drywall Nailing | 9/26/2024 | Approved | JACK KARGODORIAN |
| Shower Pan | 10/10/2024 | Approved | MICHAEL CORTEZ |
| Interior/Exterior Lathing | 10/17/2024 | Approved | JACK KARGODORIAN |
| ELECTRICAL-Rough | 12/16/2024 | Corrections Issued | JACK KARGODORIAN |
| Final | 3/5/2025 | Corrections Issued | JACK KARGODORIAN |
| Green Building Final | 3/5/2025 | Not Ready for Inspection | JACK KARGODORIAN |
| SGSOV-Seismic Gas S/O Valve | 3/5/2025 | SGSOV Approved | JACK KARGODORIAN |
| Smoke Detectors | 3/5/2025 | Approved | JACK KARGODORIAN |
| Final | 4/16/2025 | OK to Issue CofO | JACK KARGODORIAN |
| Green Building Final | 4/16/2025 | Approved | JACK KARGODORIAN |
| Service/Power Release | 4/16/2025 | Approved | JACK KARGODORIAN |