7102 S ALVERSTONE AVE 90045

Certificate Information: 7102 S ALVERSTONE AVE 90045

Application / Permit
23014-20000-02864
Plan Check / Job No.
B23VN09562
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ADDITION TO AND CONVERT DETACHED RUMPUS ROOM TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d). FIRE SPRINKLER REQ NFPA-13D.
Permit Issued
Issued on 11/7/2023
Issuing Office
West Los Angeles
Current Status
CofO Issued on 8/6/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/18/2023 APPLICANT
Assigned to Plan Check Engineer 7/21/2023 HAYATO TSUCHIYA
Corrections Issued 7/22/2023 JEROME MAGAT PALMA
Building Plans Picked Up 8/2/2023 APPLICANT
Plan Check Approved 10/31/2023 SERGIO MUNIZ
Issued 11/7/2023 APPLICANT
CofO in Progress 8/1/2024 TEMISTOCLES CAAL
Permit Finaled 8/6/2024 DANIEL ORRANTE
CofO Issued 8/6/2024 DANIEL ORRANTE
Permit Finaled 8/6/2024 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 8/28/2023 DARIN LAM
Eng Process Fee Ord 176,300 Cleared 8/28/2023 DARIN LAM
Roof/Waste drainage to street Cleared 8/28/2023 DARIN LAM
Sewer availability Cleared 8/28/2023 DARIN LAM
Specific Plan Cleared 8/29/2023 EDUARDO HERMOSO
Construction near power lines Cleared 10/16/2023 RIDWAN HARDY
Grading Pre-Inspection Cleared 10/31/2023 AL GAMBLE

Contact Information

Contractor Local Construction Remodeling; Lic. No.: 966738-B 14901 TUBA STREET      MISSION HILLS, CA 91345

Inspector Information

MORRIS JACKSON, (310) 914-3885 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 12/15/2023 Approved TEMISTOCLES CAAL
Footing/Foundation/Slab 12/15/2023 Approved TEMISTOCLES CAAL
PLUMBING-Rough 12/15/2023 Not Ready for Inspection TEMISTOCLES CAAL
PLUMBING-Rough 12/19/2023 Partial Approval TEMISTOCLES CAAL
Floor/Roof Diaphrgm/Shear Wall 1/19/2024 Approved TEMISTOCLES CAAL
Interior/Exterior Lathing 3/11/2024 Partial Approval TEMISTOCLES CAAL
BUILDING-Rough-Frame 3/19/2024 Corrections Issued BOBBY KEY
ELECTRICAL-Rough 3/19/2024 Corrections Issued BOBBY KEY
HVAC-Final 3/19/2024 Corrections Issued BOBBY KEY
HVAC-Rough 3/19/2024 Approved BOBBY KEY
PLUMBING-Rough 3/19/2024 Corrections Issued BOBBY KEY
BUILDING-Rough-Frame 3/22/2024 Conditional Approval TEMISTOCLES CAAL
ELECTRICAL-Rough 3/22/2024 Approved TEMISTOCLES CAAL
Green Building Final 3/22/2024 Approved TEMISTOCLES CAAL
PLUMBING-Rough 3/22/2024 Approved TEMISTOCLES CAAL
Verify Sprinkler Sign Off 3/22/2024 Approved TEMISTOCLES CAAL
Sewer 3/28/2024 Approved TEMISTOCLES CAAL
Underground Mechanical 3/28/2024 Approved TEMISTOCLES CAAL
Insulation 3/29/2024 Approved TEMISTOCLES CAAL
Shower Pan 3/29/2024 Not Ready for Inspection TEMISTOCLES CAAL
Shower Pan 4/2/2024 Approved TEMISTOCLES CAAL
Interior/Exterior Lathing 4/3/2024 Approved TEMISTOCLES CAAL
Drywall Nailing 4/8/2024 Approved TEMISTOCLES CAAL
ELECTRICAL-Final 5/30/2024 Approved TEMISTOCLES CAAL
HVAC-Final 5/30/2024 Approved TEMISTOCLES CAAL
PLUMBING-Final 5/30/2024 Approved TEMISTOCLES CAAL
Gas Test 6/14/2024 Approved TEMISTOCLES CAAL
BUILDING-Rough-Frame 6/26/2024 Approved TEMISTOCLES CAAL
Final 6/26/2024 Corrections Issued TEMISTOCLES CAAL
Green Building Rough 6/26/2024 Approved TEMISTOCLES CAAL
SGSOV-Seismic Gas S/O Valve 6/26/2024 SGSOV Approved TEMISTOCLES CAAL
Smoke Detectors 6/26/2024 Approved TEMISTOCLES CAAL
Final 7/31/2024 OK to Issue CofO TEMISTOCLES CAAL