1324 S CARMONA AVE 90019
Certificate Information: 1324 S CARMONA AVE 90019
- Application / Permit
- 23014-20000-02857
- Plan Check / Job No.
- B23VN09536
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (N) 5'-8" X 8'-4" ADDITION TO (E) SINGLE-FAMILY DWELLING PER ENGINEER
- Permit Issued
- Issued on 7/20/2023
- Issuing Office
- Current Status
- CofO Issued on 12/22/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/18/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 7/18/2023 | ALEC MOUSAKHANIAN |
| Corrections Issued | 7/18/2023 | ALEC MOUSAKHANIAN |
| Plan Check Approved | 7/20/2023 | ISIS ARGUETA |
| Issued | 7/20/2023 | APPLICANT |
| CofO in Progress | 12/19/2023 | SCOTT FINNILA |
| CofO Issued | 12/22/2023 | DEROLD HAUFF |
| Permit Finaled | 12/22/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 7/19/2023 | JEANIE LAM |
| Roof/Waste drainage to street | Cleared | 7/19/2023 | JEANIE LAM |
Contact Information
| Contractor | Green Design Builders Inc; Lic. No.: 1058542-B | 1650 WESTWOOD BLVD #200 LOS ANGELES, CA 90024 |
| Engineer | Adzhemyan,, Arsen; Lic. No.: C89103 | 1010 RALEIGH ST APT 107 GLENDALE, CA 91205 |
Inspector Information
| DAVID WILLIAMS, (213) 202-3126 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 8/16/2023 | Conditional Approval | JOSE AVILA |
| Footing/Foundation/Slab | 8/25/2023 | Partial Approval | JOSE AVILA |
| METHANE-Barrier | 8/25/2023 | Approved | JOSE AVILA |
| METHANE-Subgrade | 8/25/2023 | Approved | JOSE AVILA |
| Floor/Roof Diaphrgm/Shear Wall | 9/6/2023 | Approved | JOSE AVILA |
| ELECTRICAL-Rough | 9/25/2023 | Partial Approval | JOSE AVILA |
| Green Building Rough | 9/25/2023 | Corrections Issued | JOSE AVILA |
| METHANE-Rough | 9/25/2023 | Approved | JOSE AVILA |
| PLUMBING-Rough | 9/25/2023 | Partial Approval | JOSE AVILA |
| Rough-Elec/Plmb/HVAC | 9/25/2023 | Corrections Issued | JOSE AVILA |
| BUILDING-Rough-Frame | 10/3/2023 | Approved | JOSE AVILA |
| Green Building Rough | 10/3/2023 | Approved | JOSE AVILA |
| HVAC-Rough | 10/3/2023 | Approved | JOSE AVILA |
| Interior/Exterior Lathing | 10/3/2023 | Approved | JOSE AVILA |
| PLUMBING-Rough | 10/3/2023 | Approved | JOSE AVILA |
| Drywall Nailing | 10/13/2023 | Approved | RONNIE MINDANAO |
| Final | 12/14/2023 | Corrections Issued | SCOTT FINNILA |
| Footing/Foundation/Slab | 12/14/2023 | Approved | SCOTT FINNILA |
| Green Building Final | 12/14/2023 | Approved | SCOTT FINNILA |
| Smoke Detectors | 12/14/2023 | Approved | SCOTT FINNILA |
| ELECTRICAL-Final | 12/20/2023 | Approved | SCOTT FINNILA |
| Final | 12/20/2023 | OK to Issue CofO | SCOTT FINNILA |
| HVAC-Final | 12/20/2023 | Approved | SCOTT FINNILA |
| PLUMBING-Final | 12/20/2023 | Approved | SCOTT FINNILA |