7548 N SHOUP AVE 91303

Certificate Information: 7548 N SHOUP AVE 91303

Application / Permit
23014-20000-02845
Plan Check / Job No.
B23VN09476
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
6' X 20' ADDITION TO AND CONVERT DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d)
Permit Issued
Issued on 8/22/2023
Issuing Office
Valley
Current Status
CofO Issued on 9/9/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/17/2023 APPLICANT
Assigned to Plan Check Engineer 7/21/2023 HAYATO TSUCHIYA
Corrections Issued 7/22/2023 JEROME MAGAT PALMA
Building Plans Picked Up 7/25/2023 APPLICANT
Plan Check Approved 8/17/2023 GIOVANNY CHAVEZ
Issued 8/22/2023 APPLICANT
CofO in Progress 9/3/2025 JEFFREY HARTLINE
Permit Finaled 9/9/2025 JOHN JANSON
CofO Issued 9/9/2025 JOHN JANSON
Permit Finaled 9/9/2025 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 7/25/2023 MEGAN GODINEZ
Eng Process Fee Ord 176,300 Cleared 7/25/2023 MEGAN GODINEZ
Roof/Waste drainage to street Cleared 7/25/2023 MEGAN GODINEZ
Sewer availability Cleared 7/25/2023 MEGAN GODINEZ

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JEFFREY HARTLINE, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI
CHRIS CHRISTENSEN, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 10/25/2023 Approved JEFFREY HARTLINE
Deputy Drilled-In Anchors 11/1/2023 Approved CHRIS CHRISTENSEN
Excavation/Setback/Form/Re-Bar 11/1/2023 Approved CHRIS CHRISTENSEN
BUILDING-Rough-Frame 3/11/2024 Not Ready for Inspection JEFFREY HARTLINE
ELECTRICAL-Rough 3/11/2024 Approved JEFFREY HARTLINE
Floor/Roof Diaphrgm/Shear Wall 3/11/2024 Approved JEFFREY HARTLINE
HVAC-Rough 3/11/2024 Approved JEFFREY HARTLINE
PLUMBING-Rough 3/11/2024 Approved JEFFREY HARTLINE
Rough-Elec/Plmb/HVAC 3/11/2024 Approved JEFFREY HARTLINE
Insulation 6/3/2024 Not Ready for Inspection JEFFREY HARTLINE
Interior/Exterior Lathing 6/3/2024 Partial Approval JEFFREY HARTLINE
BUILDING-Rough-Frame 7/8/2024 Approved JEFFREY HARTLINE
Green Building Rough 7/8/2024 Approved JEFFREY HARTLINE
Verify Sprinkler Sign Off 7/8/2024 Approved JEFFREY HARTLINE
Insulation 7/11/2024 Approved JEFFREY HARTLINE
Drywall Nailing 7/25/2024 Approved JEFFREY PARD
Shower Pan 7/25/2024 Approved JEFFREY PARD
Interior/Exterior Lathing 8/13/2024 Approved CHRIS CHRISTENSEN
SGSOV-Seismic Gas S/O Valve 7/31/2025 SGSOV Not Ready JEFFREY HARTLINE
Final 8/4/2025 Corrections Issued TROY SANDERS
Service/Power Release 8/4/2025 Approved TROY SANDERS
ELECTRICAL-Final 9/3/2025 Approved JEFFREY HARTLINE
Final 9/3/2025 OK to Issue CofO JEFFREY HARTLINE
Footing/Foundation/Slab 9/3/2025 Approved JEFFREY HARTLINE
Green Building Final 9/3/2025 Approved JEFFREY HARTLINE
HVAC-Final 9/3/2025 Approved JEFFREY HARTLINE
PLUMBING-Final 9/3/2025 Approved JEFFREY HARTLINE
SGSOV-Seismic Gas S/O Valve 9/3/2025 SGSOV Approved JEFFREY HARTLINE
Smoke Detectors 9/3/2025 Approved JEFFREY HARTLINE