5959 N WILBUR AVE 91356
Certificate Information: 5959 N WILBUR AVE 91356
- Application / Permit
- 23014-20000-02825
- Plan Check / Job No.
- B23VN09432
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ePlan Add a two story 32' x 21' addition to a single family residence with new family room, 4 new bathrooms and 5 new bedrooms. Remodel existing kitchen. NFPA 13D sprinkler is required throughout the whole building. All work done per engineering.
- Permit Issued
- Issued on 10/11/2023
- Issuing Office
- Current Status
- Issued on 10/11/2023
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 7/18/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 8/3/2023 | NAREG ATARIAN |
| Corrections Issued | 8/9/2023 | NAREG ATARIAN |
| Quality Review Completed | 8/11/2023 | OMID HEDAYAT |
| Applicant returned to address corrections | 9/13/2023 | NAREG ATARIAN |
| Plan Check Approved | 10/10/2023 | NAREG ATARIAN |
| Issued | 10/11/2023 | APPLICANT |
Permit Application Clearance Information
| Low Impact Development (LID) | Cleared | 9/6/2023 | SAMUEL LINN |
| Eng Process Fee Ord 176,300 | Cleared | 9/7/2023 | TAL SHEMEN |
| Miscellaneous | Cleared | 9/7/2023 | TAL SHEMEN |
| Roof/Waste drainage to street | Cleared | 9/7/2023 | TAL SHEMEN |
| Sewer availability | Cleared | 9/7/2023 | TAL SHEMEN |
| Watercourse | Cleared | 9/7/2023 | TAL SHEMEN |
Contact Information
| Contractor | Cloud Nine Builders; Lic. No.: 1005097-B | , |
| Engineer | Le,, Thang Huu; Lic. No.: NA4978 | , |
Inspector Information
| JON MCHUGH, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
| IVAN SARABIA, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 11/9/2023 | Corrections Issued | JON MCHUGH |
| Deputy Drilled-In Anchors | 11/16/2023 | Conditional Approval | JON MCHUGH |
| Floor/Roof Diaphrgm/Shear Wall | 11/20/2023 | Corrections Issued | JON MCHUGH |
| Footing/Foundation/Slab | 11/20/2023 | Approved | JON MCHUGH |
| BUILDING-Rough-Frame | 12/1/2023 | Partial Approval | JEFFREY PARD |
| Green Building Rough | 12/1/2023 | Not Ready for Inspection | JEFFREY PARD |
| Floor/Roof Diaphrgm/Shear Wall | 12/6/2023 | Corrections Issued | JON MCHUGH |
| Floor/Roof Diaphrgm/Shear Wall | 12/13/2023 | Partial Approval | JON MCHUGH |
| BUILDING-Rough-Frame | 12/28/2023 | Not Ready for Inspection | JON MCHUGH |
| Floor/Roof Diaphrgm/Shear Wall | 12/28/2023 | Approved | JON MCHUGH |
| Green Building Rough | 12/28/2023 | Approved | JON MCHUGH |
| Interior/Exterior Lathing | 12/28/2023 | Partial Approval | JON MCHUGH |
| Underground Mechanical | 1/16/2024 | Approved | VINCENT HANLEY |
| BUILDING-Rough-Frame | 1/23/2024 | Not Ready for Inspection | JON MCHUGH |
| ELECTRICAL-Rough | 1/23/2024 | Corrections Issued | JON MCHUGH |
| HVAC-Rough | 1/23/2024 | Corrections Issued | JON MCHUGH |
| BUILDING-Rough-Frame | 1/25/2024 | Corrections Issued | JON MCHUGH |
| Green Building Rough | 1/25/2024 | Approved | JON MCHUGH |
| PLUMBING-Rough | 1/25/2024 | Approved | JON MCHUGH |
| Verify Sprinkler Sign Off | 1/25/2024 | Approved | JON MCHUGH |
| Insulation | 1/31/2024 | Not Ready for Inspection | MORRIS JACKSON |
| Drywall Nailing | 2/2/2024 | Conditional Approval | JON MCHUGH |
| Interior/Exterior Lathing | 2/6/2024 | Not Ready for Inspection | JON MCHUGH |
| BUILDING-Rough-Frame | 2/9/2024 | Approved | JON MCHUGH |
| Drywall Nailing | 2/9/2024 | Approved | JON MCHUGH |
| HVAC-Rough | 2/9/2024 | Approved | JON MCHUGH |
| Insulation | 2/9/2024 | Approved | JON MCHUGH |
| Interior/Exterior Lathing | 2/9/2024 | Approved | JON MCHUGH |
| ELECTRICAL-Final | 3/13/2024 | Corrections Issued | JON MCHUGH |
| Final | 3/13/2024 | Corrections Issued | JON MCHUGH |
| Green Building Final | 3/13/2024 | Not Ready for Inspection | JON MCHUGH |
| HVAC-Final | 3/13/2024 | Corrections Issued | JON MCHUGH |
| PLUMBING-Final | 3/13/2024 | Corrections Issued | JON MCHUGH |
| SGSOV-Seismic Gas S/O Valve | 3/13/2024 | SGSOV Not Ready | JON MCHUGH |
| Smoke Detectors | 3/13/2024 | Not Ready for Inspection | JON MCHUGH |
| Final | 4/9/2024 | Corrections Issued | JON MCHUGH |
| Green Building Final | 4/9/2024 | Approved | JON MCHUGH |
| SGSOV-Seismic Gas S/O Valve | 4/9/2024 | SGSOV Not Ready | JON MCHUGH |
| Smoke Detectors | 4/9/2024 | Approved | JON MCHUGH |
| Final | 4/19/2024 | Not Ready for Inspection | JON MCHUGH |
| SGSOV-Seismic Gas S/O Valve | 4/19/2024 | SGSOV Approved | JON MCHUGH |