8540 N DE CELIS PL 91343

Certificate Information: 8540 N DE CELIS PL 91343

Application / Permit
23014-20000-02819
Plan Check / Job No.
B23VN09417
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) DETACHED RUMPUS ROOM TO (N) DETACHED ACCESSORY DWELLING UNIT WITH IRREGULAR SHAPED 48'-0" X 14'-8" ADDITION PER LAMC 12.22 A.33(c) AND (d)
Permit Issued
Issued on 10/10/2023
Issuing Office
Current Status
CofO Issued on 11/13/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/14/2023 APPLICANT
Assigned to Plan Check Engineer 7/20/2023 JESSE ARELLANO
Corrections Issued 7/20/2023 JESSE ARELLANO
Building Plans Picked Up 8/14/2023 APPLICANT
Plan Check Approved 10/10/2023 ALEC MOUSAKHANIAN
Issued 10/10/2023 APPLICANT
CofO in Progress 11/6/2025 GAREN HAYRAPETYAN
CofO Issued 11/13/2025 RUBEN SALAS
Permit Finaled 11/13/2025 RUBEN SALAS

Permit Application Clearance Information

Low Impact Development (LID) Cleared 8/4/2023 ANTHONY VARGAS
Eng Process Fee Ord 176,300 Cleared 8/14/2023 MEGAN GODINEZ
Roof/Waste drainage to street Cleared 8/14/2023 MEGAN GODINEZ
Miscellaneous Cleared 9/20/2023 MEGAN GODINEZ
Address approval Cleared 9/21/2023 MEGAN GODINEZ
Sewer availability Cleared 9/21/2023 MEGAN GODINEZ
Tract Map conditions Cleared 9/26/2023 BRENNEN OBETO

Contact Information

Contractor Owner-Builder       ,

Inspector Information

MICHAEL CORTEZ, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI
WILLIAM WREN, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 2/9/2024 Corrections Issued RAUL OLAGI
Underground Mechanical 2/15/2024 Partial Approval RAUL OLAGI
Deputy Drilled-In Anchors 2/29/2024 Conditional Approval ROBERT GOLD
Footing/Foundation/Slab 3/5/2024 Approved JOHN COLEMAN
Special/Order Compliance 3/14/2024 Corrections Issued RAUL OLAGI
Sewer 6/20/2024 Approved RAUL OLAGI
PLUMBING-Rough 7/5/2024 Partial Approval RAUL OLAGI
Special/Order Compliance 7/5/2024 Corrections Issued RAUL OLAGI
Excavation/Setback/Form/Re-Bar 7/26/2024 Corrections Issued SALVADOR MARTINEZ
Deputy Drilled-In Anchors 7/31/2024 Conditional Approval ROBERT GOLD
Excavation/Setback/Form/Re-Bar 8/5/2024 Approved SALVADOR MARTINEZ
Underground Mechanical 8/16/2024 Partial Approval RAUL OLAGI
BUILDING-Rough-Frame 10/11/2024 Not Ready for Inspection SALVADOR MARTINEZ
ELECTRICAL-Rough 10/11/2024 Corrections Issued SALVADOR MARTINEZ
Green Building Rough 10/11/2024 Not Ready for Inspection SALVADOR MARTINEZ
HVAC-Rough 10/11/2024 Corrections Issued SALVADOR MARTINEZ
PLUMBING-Rough 10/11/2024 Corrections Issued SALVADOR MARTINEZ
ELECTRICAL-Rough 10/22/2024 Corrections Issued SALVADOR MARTINEZ
Floor/Roof Diaphrgm/Shear Wall 10/22/2024 Partial Approval SALVADOR MARTINEZ
Green Building Rough 10/22/2024 Not Ready for Inspection SALVADOR MARTINEZ
HVAC-Rough 10/22/2024 Corrections Issued SALVADOR MARTINEZ
PLUMBING-Rough 10/22/2024 Corrections Issued SALVADOR MARTINEZ
ELECTRICAL-Rough 11/21/2024 Approved GAREN HAYRAPETYAN
HVAC-Rough 11/21/2024 Not Ready for Inspection GAREN HAYRAPETYAN
PLUMBING-Rough 11/21/2024 Approved GAREN HAYRAPETYAN
BUILDING-Rough-Frame 11/26/2024 Conditional Approval SALVADOR MARTINEZ
Green Building Rough 11/26/2024 Not Ready for Inspection SALVADOR MARTINEZ
HVAC-Rough 11/26/2024 Conditional Approval SALVADOR MARTINEZ
Insulation 12/10/2024 Partial Approval SALVADOR MARTINEZ
BUILDING-Rough-Frame 12/23/2024 Corrections Issued SALVADOR MARTINEZ
Drywall Nailing 12/23/2024 Conditional Approval SALVADOR MARTINEZ
BUILDING-Rough-Frame 1/21/2025 Approved SALVADOR MARTINEZ
Green Building Rough 1/21/2025 Approved SALVADOR MARTINEZ
Interior/Exterior Lathing 1/21/2025 Approved SALVADOR MARTINEZ
Shower Pan 1/21/2025 Approved SALVADOR MARTINEZ
Final 10/21/2025 Corrections Issued NICHOLAS TROWBRIDGE
Green Building Final 10/21/2025 Not Ready for Inspection NICHOLAS TROWBRIDGE
SGSOV-Seismic Gas S/O Valve 10/21/2025 SGSOV Not Ready NICHOLAS TROWBRIDGE
Smoke Detectors 10/21/2025 Approved NICHOLAS TROWBRIDGE
ELECTRICAL-Final 11/6/2025 Approved GAREN HAYRAPETYAN
Final 11/6/2025 OK to Issue CofO GAREN HAYRAPETYAN
Green Building Final 11/6/2025 Approved GAREN HAYRAPETYAN
HVAC-Final 11/6/2025 Approved GAREN HAYRAPETYAN
PLUMBING-Final 11/6/2025 Approved GAREN HAYRAPETYAN
SGSOV-Seismic Gas S/O Valve 11/6/2025 SGSOV Approved GAREN HAYRAPETYAN
Service/Power Release 11/6/2025 Approved GAREN HAYRAPETYAN