13552 W GAIN ST 91331

Certificate Information: 13552 W GAIN ST 91331

Application / Permit
23014-20000-02809
Plan Check / Job No.
B23VN09376
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ADDITION ( 26'-6" X 16'-4" ) TO AND CONVERT EX. DETACHED GARAGE INTO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d).
Permit Issued
Issued on 9/6/2023
Issuing Office
Valley
Current Status
CofO Issued on 10/23/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/14/2023 APPLICANT
Assigned to Plan Check Engineer 7/20/2023 ALEC MOUSAKHANIAN
Corrections Issued 7/21/2023 ALEC MOUSAKHANIAN
Building Plans Picked Up 7/27/2023 APPLICANT
Applicant returned to address corrections 8/31/2023 ALEC MOUSAKHANIAN
Plan Check Approved 9/6/2023 ROSENDO MEDINA
Plan Check Approved 9/6/2023 ROSENDO MEDINA
Issued 9/6/2023 APPLICANT
CofO in Progress 9/17/2024 MICHEL ABAJAN
Permit Finaled 10/23/2024 DANIEL ORRANTE
CofO Issued 10/23/2024 DANIEL ORRANTE
Permit Finaled 10/23/2024 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 8/31/2023 TAL SHEMEN
Roof/Waste drainage to street Cleared 8/31/2023 TAL SHEMEN
Eng Process Fee Ord 176,300 Cleared 9/5/2023 TAL SHEMEN
Sewer availability Cleared 9/6/2023 TAL SHEMEN

Contact Information

Contractor Owner-Builder       ,
Engineer Velasco,, Jose Luis; Lic. No.: C76091 7901 4TH ST. N STE 5086      ST. PETERSBURG, FL 33702

Inspector Information

MICHEL ABAJAN, (818) 374-9932 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 9/13/2023 Corrections Issued MICHEL ABAJAN
Deputy Drilled-In Anchors 9/19/2023 Conditional Approval ROBERT GOLD
Footing/Foundation/Slab 9/21/2023 Approved MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 10/16/2023 Partial Approval MICHEL ABAJAN
PLUMBING-Rough 10/16/2023 Approved MICHEL ABAJAN
BUILDING-Rough-Frame 11/27/2023 Corrections Issued MICHEL ABAJAN
ELECTRICAL-Rough 11/27/2023 Approved MICHEL ABAJAN
Green Building Rough 11/27/2023 Not Ready for Inspection MICHEL ABAJAN
HVAC-Rough 11/27/2023 Approved MICHEL ABAJAN
MERV13>=Rough 11/27/2023 Approved MICHEL ABAJAN
BUILDING-Rough-Frame 1/12/2024 Approved MICHEL ABAJAN
Green Building Rough 1/12/2024 Approved MICHEL ABAJAN
Insulation 1/31/2024 Approved MICHEL ABAJAN
Interior/Exterior Lathing 1/31/2024 Approved MICHEL ABAJAN
Drywall Nailing 2/9/2024 Approved MICHEL ABAJAN
Shower Pan 3/4/2024 Approved MICHEL ABAJAN
ELECTRICAL-Final 8/16/2024 Corrections Issued JENNIFER RABUCHIN
Final 8/16/2024 Corrections Issued JENNIFER RABUCHIN
Green Building Final 8/16/2024 Corrections Issued JENNIFER RABUCHIN
HVAC-Final 8/16/2024 Corrections Issued JENNIFER RABUCHIN
MERV13>=Final 8/16/2024 Approved JENNIFER RABUCHIN
PLUMBING-Final 8/16/2024 Corrections Issued JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 8/16/2024 SGSOV Approved JENNIFER RABUCHIN
Smoke Detectors 8/16/2024 Approved JENNIFER RABUCHIN
Final 8/30/2024 Corrections Issued MISAEL ESPARZA
Green Building Final 8/30/2024 Not Ready for Inspection MISAEL ESPARZA
ELECTRICAL-Final 9/17/2024 Approved MICHEL ABAJAN
Final 9/17/2024 OK to Issue CofO MICHEL ABAJAN
Green Building Final 9/17/2024 Approved MICHEL ABAJAN
HVAC-Final 9/17/2024 Approved MICHEL ABAJAN
PLUMBING-Final 9/17/2024 Approved MICHEL ABAJAN