10441-10443 W CALIFA ST 91601
Certificate Information: 10441-10443 W CALIFA ST 91601
- Application / Permit
- 23014-20000-02798
- Plan Check / Job No.
- B23VN09352
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 16'-10" x 13'-4" ADDITION TO (E) SINGLE FAMILY DWELLING AND REMODEL PORTION OF (E) SFD. ALL WORK DONE PER ENGINEERING.
- Permit Issued
- Issued on 10/25/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 7/17/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/13/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 7/20/2023 | KAMYAR EMAMI |
| Corrections Issued | 7/21/2023 | KAMYAR EMAMI |
| Building Plans Picked Up | 7/24/2023 | APPLICANT |
| Plan Check Approved | 8/28/2023 | GIOVANNY CHAVEZ |
| No Progress | 10/6/2023 | JESSE ARELLANO |
| Issued | 10/25/2023 | APPLICANT |
| CofO in Progress | 6/3/2024 | JOSE AVILA |
| Permit Finaled | 7/17/2024 | RUBEN SALAS |
| CofO Issued | 7/17/2024 | RUBEN SALAS |
| Permit Finaled | 7/17/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 7/27/2023 | MEGAN GODINEZ |
| Eng Process Fee Ord 176,300 | Cleared | 8/1/2023 | MEGAN GODINEZ |
| Sewer availability | Cleared | 8/14/2023 | MEGAN GODINEZ |
Contact Information
| Contractor | Gold Star Remodeling Inc; Lic. No.: 1044362-B | 5053 FAIR AVE UNIT 404 NORTH HOLLYWOOD, CA 91601 |
| Engineer | Standley,, Craig Erick; Lic. No.: C87675 | 60 VIA CARATAMA SAN CLEMENTE, CA 92673 |
Inspector Information
| GAREN HAYRAPETYAN, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERTO PALACIOS-LOPEZ, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 11/13/2023 | Not Ready for Inspection | JOHN HAYES |
| Footing/Foundation/Slab | 11/13/2023 | Corrections Issued | JOHN HAYES |
| Excavation/Setback/Form/Re-Bar | 12/26/2023 | Approved | RYAN SALAZAR |
| Footing/Foundation/Slab | 12/26/2023 | Approved | RYAN SALAZAR |
| BUILDING-Rough-Frame | 2/2/2024 | Corrections Issued | JOHN HAYES |
| ELECTRICAL-Rough | 2/2/2024 | Not Ready for Inspection | JOHN HAYES |
| Green Building Rough | 2/2/2024 | Not Ready for Inspection | JOHN HAYES |
| HVAC-Rough | 2/2/2024 | Not Ready for Inspection | JOHN HAYES |
| PLUMBING-Rough | 2/2/2024 | Not Ready for Inspection | JOHN HAYES |
| Wood Frame | 2/2/2024 | Not Ready for Inspection | JOHN HAYES |
| BUILDING-Rough-Frame | 3/5/2024 | Approved | JOHN HAYES |
| ELECTRICAL-Rough | 3/5/2024 | Approved | JOHN HAYES |
| Green Building Rough | 3/5/2024 | Approved | JOHN HAYES |
| HVAC-Rough | 3/5/2024 | Approved | JOHN HAYES |
| PLUMBING-Rough | 3/5/2024 | Approved | JOHN HAYES |
| Interior/Exterior Lathing | 3/8/2024 | Partial Approval | JOHN HAYES |
| Shower Pan | 3/8/2024 | Approved | JOHN HAYES |
| Insulation | 3/22/2024 | Approved | JOHN HAYES |
| Interior/Exterior Lathing | 3/22/2024 | Approved | JOHN HAYES |
| Drywall Nailing | 4/15/2024 | Approved | RYAN SALAZAR |
| Final | 5/14/2024 | Corrections Issued | JOSE AVILA |
| Final | 5/28/2024 | OK to Issue CofO | JOSE AVILA |
| Green Building Final | 5/28/2024 | Approved | JOSE AVILA |
| SGSOV-Seismic Gas S/O Valve | 5/28/2024 | SGSOV Approved | JOSE AVILA |
| Smoke Detectors | 5/28/2024 | Approved | JOSE AVILA |