10342 W MARGATE ST 91601
Certificate Information: 10342 W MARGATE ST 91601
- Application / Permit
- 23014-20000-02783
- Plan Check / Job No.
- B23VN09316
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) GARAGE INTO (N) ACCESSORY DWELLING UNIT PER LAMC 12.21A33(c)(d) & ADD 1ST/2ND FLOOR **ePlan**
- Permit Issued
- Issued on 12/3/2023
- Issuing Office
- Current Status
- CofO Issued on 7/24/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/13/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 7/20/2023 | NILOOFAR MEHRAIN |
| Corrections Issued | 7/23/2023 | NILOOFAR MEHRAIN |
| Quality Review Completed | 7/26/2023 | STEVEN KIM |
| Applicant returned to address corrections | 11/2/2023 | NILOOFAR MEHRAIN |
| Applicant returned to address corrections | 11/14/2023 | NILOOFAR MEHRAIN |
| Applicant returned to address corrections | 11/30/2023 | NILOOFAR MEHRAIN |
| Plan Check Approved | 12/1/2023 | NILOOFAR MEHRAIN |
| Issued | 12/3/2023 | APPLICANT |
| CofO in Progress | 7/3/2024 | ROBERTO PALACIOS-LOPEZ |
| Permit Finaled | 7/24/2024 | RUBEN SALAS |
| CofO Issued | 7/24/2024 | RUBEN SALAS |
| Permit Finaled | 7/24/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 8/1/2023 | TAL SHEMEN |
| Eng Process Fee Ord 176,300 | Cleared | 8/1/2023 | TAL SHEMEN |
| Sewer availability | Cleared | 8/1/2023 | TAL SHEMEN |
| Hydrant and Access approval | Cleared | 9/15/2023 | KURT CORRAL |
| Construction near power lines | Cleared | 10/3/2023 | RIDWAN HARDY |
| Construction within easement | Cleared | 10/3/2023 | RIDWAN HARDY |
| Low Impact Development (LID) | Cleared | 10/31/2023 | MELINEH AGHAKHABIAN |
| Roof/Waste drainage to street | Cleared | 10/31/2023 | COLIN LOREDO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Manoukian,, Krikor Kerop; Lic. No.: C87010 | 2310 W MAGNOLIA BLVD STE A BURBANK, CA 91506 |
Inspector Information
| GAREN HAYRAPETYAN, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERTO PALACIOS-LOPEZ, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 1/10/2024 | Corrections Issued | JENNIFER RABUCHIN |
| PLUMBING-Rough | 1/17/2024 | Corrections Issued | JOHN HAYES |
| Underground Mechanical | 1/17/2024 | Partial Approval | JOHN HAYES |
| Excavation/Setback/Form/Re-Bar | 1/18/2024 | Approved | JOHN COLEMAN |
| Floor/Roof Diaphrgm/Shear Wall | 2/2/2024 | Approved | CRAIG DAVIS |
| Deputy Wood Construction | 2/7/2024 | No Access for Inspection | JOHN HAYES |
| Floor/Roof Diaphrgm/Shear Wall | 2/23/2024 | Corrections Issued | RYAN SALAZAR |
| Sewer | 3/1/2024 | Approved | RAUL OLAGI |
| PLUMBING-Rough | 3/5/2024 | Partial Approval | JOHN HAYES |
| Floor/Roof Diaphrgm/Shear Wall | 3/11/2024 | Partial Approval | JOHN HAYES |
| ELECTRICAL-Rough | 3/19/2024 | Approved | JOHN COLEMAN |
| HVAC-Rough | 3/19/2024 | Approved | JOHN COLEMAN |
| BUILDING-Rough-Frame | 3/20/2024 | Approved | JOHN HAYES |
| Green Building Rough | 3/20/2024 | Approved | JOHN HAYES |
| Interior/Exterior Lathing | 3/20/2024 | Partial Approval | JOHN HAYES |
| Insulation | 3/27/2024 | Approved | KIRK SANDERS |
| Drywall Nailing | 3/29/2024 | Approved | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 4/1/2024 | Corrections Issued | JOHN HAYES |
| Shower Pan | 4/1/2024 | Approved | JOHN HAYES |
| Interior/Exterior Lathing | 4/3/2024 | Approved | JOHN HAYES |
| Gas Test | 5/20/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 5/20/2024 | SGSOV Not Ready | ROBERTO PALACIOS-LOPEZ |
| Underground Mechanical | 5/20/2024 | Partial Approval | ROBERTO PALACIOS-LOPEZ |
| Underground Mechanical | 5/23/2024 | Partial Approval | JOSE AVILA |
| ELECTRICAL-Final | 6/10/2024 | Corrections Issued | JOSE AVILA |
| PLUMBING-Final | 6/12/2024 | Corrections Issued | JOSE AVILA |
| ELECTRICAL-Final | 6/21/2024 | Approved | JOSE AVILA |
| Footing/Foundation/Slab | 6/21/2024 | Approved | JOSE AVILA |
| HVAC-Final | 6/21/2024 | Approved | JOSE AVILA |
| SGSOV-Seismic Gas S/O Valve | 6/21/2024 | SGSOV Approved | JOSE AVILA |
| Final | 6/26/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Green Building Final | 6/26/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| HVAC-Final | 6/26/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| PLUMBING-Final | 6/26/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| Smoke Detectors | 6/26/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| Final | 7/2/2024 | OK to Issue CofO | ROBERTO PALACIOS-LOPEZ |
| Service/Power Release | 7/2/2024 | Approved | ROBERTO PALACIOS-LOPEZ |