13740 W ERWIN ST 91401
Certificate Information: 13740 W ERWIN ST 91401
- Application / Permit
- 23014-20000-02743
- Plan Check / Job No.
- B23VN09178
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- eplan Addition and remodel (E) SFD and attached garage. Per engineering design.
- Permit Issued
- Issued on 8/3/2023
- Issuing Office
- Current Status
- CofO in Progress on 4/17/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 7/11/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 7/14/2023 | ALFREDO JARA |
| Corrections Issued | 7/16/2023 | ALFREDO JARA |
| Plan Check Approved | 8/3/2023 | ALFREDO JARA |
| Issued | 8/3/2023 | APPLICANT |
| CofO in Progress | 3/27/2024 | RYAN SALAZAR |
| No Progress | 4/17/2024 | RYAN SALAZAR |
| CofO in Progress | 4/17/2024 | RYAN SALAZAR |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 7/20/2023 | NIKKI ZULUETA |
| Eng Process Fee Ord 176,300 | Cleared | 7/28/2023 | DAGOVERTO GUERRERO |
Contact Information
| Contractor | Golan Remodeling Inc; Lic. No.: 868800-B | , |
| Engineer | Barakat,, Fouad Chafic; Lic. No.: C67449 | 11 CEDARWOOD DR POMONA, CA 91766 |
Inspector Information
| JOSE AVILA, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
| VINCENT HANLEY, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 8/15/2023 | Approved | RYAN SALAZAR |
| Floor/Roof Diaphrgm/Shear Wall | 8/22/2023 | Partial Approval | RYAN SALAZAR |
| Green Building Rough | 8/22/2023 | Not Ready for Inspection | RYAN SALAZAR |
| PLUMBING-Rough | 8/22/2023 | Partial Approval | RYAN SALAZAR |
| BUILDING-Rough-Frame | 9/12/2023 | Approved | RYAN SALAZAR |
| ELECTRICAL-Rough | 9/12/2023 | Approved | RYAN SALAZAR |
| Green Building Rough | 9/12/2023 | Approved | RYAN SALAZAR |
| PLUMBING-Rough | 9/12/2023 | Approved | RYAN SALAZAR |
| Insulation | 9/15/2023 | Approved | RYAN SALAZAR |
| Interior/Exterior Lathing | 9/15/2023 | Partial Approval | RYAN SALAZAR |
| Drywall Nailing | 9/25/2023 | Approved | RYAN SALAZAR |
| Interior/Exterior Lathing | 10/10/2023 | Approved | RYAN SALAZAR |
| Final | 3/26/2024 | OK to Issue CofO | RYAN SALAZAR |
| Green Building Final | 3/26/2024 | Approved | RYAN SALAZAR |
| SGSOV-Seismic Gas S/O Valve | 3/26/2024 | SGSOV Approved | RYAN SALAZAR |
| Smoke Detectors | 3/26/2024 | Approved | RYAN SALAZAR |
| Special/Order Compliance | 4/18/2024 | Corrections Issued | RYAN SALAZAR |
| Special/Order Compliance | 10/10/2024 | Corrections Issued | RYAN SALAZAR |