6156 N COSTELLO AVE 91401
Certificate Information: 6156 N COSTELLO AVE 91401
- Application / Permit
- 23014-20000-02742
- Plan Check / Job No.
- B23VN09177
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- eplan (N) 13'-5" X 28'-0" ADDITION TO (E) SINGLE-FAMILY DWELLING , all work per wfpp
- Permit Issued
- Issued on 5/17/2024
- Issuing Office
- Current Status
- CofO Issued on 10/29/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/7/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 8/11/2023 | ALEC MOUSAKHANIAN |
| Corrections Issued | 8/14/2023 | ALEC MOUSAKHANIAN |
| Applicant returned to address corrections | 8/19/2023 | ALEC MOUSAKHANIAN |
| Applicant returned to address corrections | 9/11/2023 | KAMYAR EMAMI |
| Plan Check Approved | 2/10/2024 | MOHAMMAD ESMAILI |
| Issued | 5/17/2024 | APPLICANT |
| CofO in Progress | 10/28/2024 | RYAN SALAZAR |
| Permit Finaled | 10/29/2024 | DANIEL ORRANTE |
| CofO Issued | 10/29/2024 | DANIEL ORRANTE |
| Permit Finaled | 10/29/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 8/17/2023 | MEGAN GODINEZ |
| Sewer availability | Cleared | 8/17/2023 | MEGAN GODINEZ |
| Eng Process Fee Ord 176,300 | Cleared | 8/23/2023 | MEGAN GODINEZ |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JOSE AVILA, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
| VINCENT HANLEY, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 5/30/2024 | Approved | RYAN SALAZAR |
| Footing/Foundation/Slab | 5/30/2024 | Approved | RYAN SALAZAR |
| Floor/Roof Diaphrgm/Shear Wall | 6/5/2024 | Partial Approval | RYAN SALAZAR |
| Floor/Roof Diaphrgm/Shear Wall | 6/21/2024 | No Access for Inspection | JOHN COLEMAN |
| Wood Frame | 6/21/2024 | Corrections Issued | JOHN COLEMAN |
| Floor/Roof Diaphrgm/Shear Wall | 6/25/2024 | Partial Approval | RYAN SALAZAR |
| ELECTRICAL-Rough | 7/23/2024 | Approved | RYAN SALAZAR |
| Floor/Roof Diaphrgm/Shear Wall | 7/23/2024 | Approved | RYAN SALAZAR |
| Service/Power Release | 7/23/2024 | Approved | RYAN SALAZAR |
| Insulation | 7/29/2024 | Approved | MICHEL ABAJAN |
| Interior/Exterior Lathing | 7/29/2024 | Approved | MICHEL ABAJAN |
| Shower Pan | 7/29/2024 | Approved | MICHEL ABAJAN |
| Drywall Nailing | 8/2/2024 | Approved | RYAN SALAZAR |
| Floor/Roof Diaphrgm/Shear Wall | 8/2/2024 | Approved | RYAN SALAZAR |
| Interior/Exterior Lathing | 8/2/2024 | Approved | RYAN SALAZAR |
| BUILDING-Rough-Frame | 9/19/2024 | Approved | JENNIFER RABUCHIN |
| Final | 9/19/2024 | Corrections Issued | JENNIFER RABUCHIN |
| Green Building Final | 9/19/2024 | Approved | JENNIFER RABUCHIN |
| Green Building Rough | 9/19/2024 | Approved | JENNIFER RABUCHIN |
| Smoke Detectors | 9/19/2024 | Corrections Issued | JENNIFER RABUCHIN |
| Final | 10/7/2024 | Corrections Issued | RYAN SALAZAR |
| SGSOV-Seismic Gas S/O Valve | 10/7/2024 | SGSOV Approved | RYAN SALAZAR |
| Smoke Detectors | 10/7/2024 | Approved | RYAN SALAZAR |
| Final | 10/28/2024 | OK to Issue CofO | RYAN SALAZAR |