6156 N COSTELLO AVE 91401

Certificate Information: 6156 N COSTELLO AVE 91401

Application / Permit
23014-20000-02742
Plan Check / Job No.
B23VN09177
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
eplan (N) 13'-5" X 28'-0" ADDITION TO (E) SINGLE-FAMILY DWELLING , all work per wfpp
Permit Issued
Issued on 5/17/2024
Issuing Office
Current Status
CofO Issued on 10/29/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/7/2023 APPLICANT
Assigned to Plan Check Engineer 8/11/2023 ALEC MOUSAKHANIAN
Corrections Issued 8/14/2023 ALEC MOUSAKHANIAN
Applicant returned to address corrections 8/19/2023 ALEC MOUSAKHANIAN
Applicant returned to address corrections 9/11/2023 KAMYAR EMAMI
Plan Check Approved 2/10/2024 MOHAMMAD ESMAILI
Issued 5/17/2024 APPLICANT
CofO in Progress 10/28/2024 RYAN SALAZAR
Permit Finaled 10/29/2024 DANIEL ORRANTE
CofO Issued 10/29/2024 DANIEL ORRANTE
Permit Finaled 10/29/2024 DANIEL ORRANTE

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 8/17/2023 MEGAN GODINEZ
Sewer availability Cleared 8/17/2023 MEGAN GODINEZ
Eng Process Fee Ord 176,300 Cleared 8/23/2023 MEGAN GODINEZ

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JOSE AVILA, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI
VINCENT HANLEY, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 5/30/2024 Approved RYAN SALAZAR
Footing/Foundation/Slab 5/30/2024 Approved RYAN SALAZAR
Floor/Roof Diaphrgm/Shear Wall 6/5/2024 Partial Approval RYAN SALAZAR
Floor/Roof Diaphrgm/Shear Wall 6/21/2024 No Access for Inspection JOHN COLEMAN
Wood Frame 6/21/2024 Corrections Issued JOHN COLEMAN
Floor/Roof Diaphrgm/Shear Wall 6/25/2024 Partial Approval RYAN SALAZAR
ELECTRICAL-Rough 7/23/2024 Approved RYAN SALAZAR
Floor/Roof Diaphrgm/Shear Wall 7/23/2024 Approved RYAN SALAZAR
Service/Power Release 7/23/2024 Approved RYAN SALAZAR
Insulation 7/29/2024 Approved MICHEL ABAJAN
Interior/Exterior Lathing 7/29/2024 Approved MICHEL ABAJAN
Shower Pan 7/29/2024 Approved MICHEL ABAJAN
Drywall Nailing 8/2/2024 Approved RYAN SALAZAR
Floor/Roof Diaphrgm/Shear Wall 8/2/2024 Approved RYAN SALAZAR
Interior/Exterior Lathing 8/2/2024 Approved RYAN SALAZAR
BUILDING-Rough-Frame 9/19/2024 Approved JENNIFER RABUCHIN
Final 9/19/2024 Corrections Issued JENNIFER RABUCHIN
Green Building Final 9/19/2024 Approved JENNIFER RABUCHIN
Green Building Rough 9/19/2024 Approved JENNIFER RABUCHIN
Smoke Detectors 9/19/2024 Corrections Issued JENNIFER RABUCHIN
Final 10/7/2024 Corrections Issued RYAN SALAZAR
SGSOV-Seismic Gas S/O Valve 10/7/2024 SGSOV Approved RYAN SALAZAR
Smoke Detectors 10/7/2024 Approved RYAN SALAZAR
Final 10/28/2024 OK to Issue CofO RYAN SALAZAR