6636 N ALCOVE AVE 91606

Certificate Information: 6636 N ALCOVE AVE 91606

Application / Permit
23014-20000-02738
Plan Check / Job No.
B23VN09144
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
eplan. convert and add to (e) detached garage into an ADUper GCS 65852.2(e)(1)(B) and LAMC 12.22 A.33(c)1, (d)1, and (g)
Permit Issued
Issued on 10/16/2023
Issuing Office
Current Status
CofO Issued on 6/22/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/12/2023 APPLICANT
Assigned to Plan Check Engineer 7/19/2023 AMY GUEVARRA
Corrections Issued 7/26/2023 AMY GUEVARRA
Plan Check Approved 10/13/2023 JASON JANGADA
Issued 10/16/2023 APPLICANT
CofO in Progress 5/15/2024 JOSE AVILA
Permit Finaled 6/22/2024 RUBEN SALAS
CofO Issued 6/22/2024 RUBEN SALAS
Permit Finaled 6/22/2024 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 7/26/2023 RYAN KIM
Roof/Waste drainage to street Cleared 7/26/2023 RYAN KIM
Eng Process Fee Ord 176,300 Cleared 8/8/2023 RYAN KIM
Sewer availability Cleared 8/8/2023 RYAN KIM
Construction within easement Cleared 10/10/2023 RIDWAN HARDY

Contact Information

Architect Dembsky,, Amit; Lic. No.: NA30383       ,
Contractor Lightning Construction & Design Inc; Lic. No.: 951122-B       ,

Inspector Information

WAYNE REGESTER, (818) 374-1164 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 11/1/2023 Corrections Issued CHRISTOPHER ROJAS
Underground Mechanical 11/6/2023 Partial Approval KIRK SANDERS
Footing/Foundation/Slab 11/15/2023 Approved KIRK SANDERS
Floor/Roof Diaphrgm/Shear Wall 11/30/2023 Approved KIRK SANDERS
ELECTRICAL-Rough 1/8/2024 Corrections Issued JOSE AVILA
Floor/Roof Diaphrgm/Shear Wall 1/8/2024 Corrections Issued JOSE AVILA
HVAC-Rough 1/8/2024 Approved JOSE AVILA
PLUMBING-Rough 1/8/2024 Corrections Issued JOSE AVILA
Underground Mechanical 1/8/2024 Approved JOSE AVILA
BUILDING-Rough-Frame 1/16/2024 Not Ready for Inspection CRAIG DAVIS
ELECTRICAL-Rough 1/16/2024 Corrections Issued CRAIG DAVIS
HVAC-Rough 1/16/2024 Corrections Issued CRAIG DAVIS
PLUMBING-Rough 1/16/2024 Partial Approval CRAIG DAVIS
BUILDING-Rough-Frame 1/22/2024 Partial Approval JOSE AVILA
ELECTRICAL-Rough 1/22/2024 Approved JOSE AVILA
HVAC-Rough 1/22/2024 Conditional Approval JOSE AVILA
PLUMBING-Rough 1/22/2024 Approved JOSE AVILA
BUILDING-Rough-Frame 1/24/2024 Approved JOSE AVILA
Insulation 1/24/2024 Approved JOSE AVILA
Drywall Nailing 1/29/2024 Approved KIRK SANDERS
Interior/Exterior Lathing 2/6/2024 Approved CRAIG DAVIS
ELECTRICAL-Final 4/4/2024 Corrections Issued JOSE AVILA
HVAC-Final 4/4/2024 Corrections Issued JOSE AVILA
PLUMBING-Final 4/4/2024 Corrections Issued JOSE AVILA
ELECTRICAL-Final 4/12/2024 Approved JOSE AVILA
Final 4/12/2024 Corrections Issued JOSE AVILA
HVAC-Final 4/12/2024 Approved JOSE AVILA
PLUMBING-Final 4/12/2024 Approved JOSE AVILA
SGSOV-Seismic Gas S/O Valve 4/12/2024 SGSOV Not Ready JOSE AVILA
Smoke Detectors 4/12/2024 Approved JOSE AVILA
Final 4/16/2024 Corrections Issued JOSE AVILA
SGSOV-Seismic Gas S/O Valve 4/16/2024 SGSOV Approved JOSE AVILA
Final 4/26/2024 OK to Issue CofO JOSE AVILA
Final 5/15/2024 Partial Inspection JOSE AVILA