6029 N BUFFALO AVE 91401
Certificate Information: 6029 N BUFFALO AVE 91401
- Application / Permit
- 23014-20000-02711
- Plan Check / Job No.
- B23VN09052
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADDITION IRREGULAR SHAPED TO EX. SFD FOR BEDROOM EXTENSION, NEW DINING ROOM, BATHROOM, AND ENTRY. INTERIOR REMODEL TO EX. BATHROOMM. WORK PER ENGINEERING.
- Permit Issued
- Issued on 9/26/2023
- Issuing Office
- Current Status
- CofO Issued on 9/10/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/14/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 7/24/2023 | ISIS ARGUETA |
| Corrections Issued | 7/25/2023 | ISIS ARGUETA |
| Applicant returned to address corrections | 9/16/2023 | ISIS ARGUETA |
| Plan Check Approved | 9/26/2023 | ROSENDO MEDINA |
| Issued | 9/26/2023 | APPLICANT |
| CofO in Progress | 8/15/2024 | JENNIFER RABUCHIN |
| CofO Issued | 9/10/2024 | DANIEL ORRANTE |
| Permit Finaled | 9/10/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 9/13/2023 | TAL SHEMEN |
| Roof/Waste drainage to street | Cleared | 9/13/2023 | TAL SHEMEN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Lobana,, Singh Maninder Pa; Lic. No.: C50989 | 885 PATRIOT DR #G MOORPARK, CA 93021 |
Inspector Information
| WAYNE REGESTER, (818) 374-1164 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 12/13/2023 | Conditional Approval | JOSE AVILA |
| Footing/Foundation/Slab | 12/19/2023 | Corrections Issued | JOSE AVILA |
| Footing/Foundation/Slab | 12/29/2023 | Approved | JOSE AVILA |
| BUILDING-Rough-Frame | 1/8/2024 | Corrections Issued | CHRISTOPHE COCHRAN |
| Floor/Roof Diaphrgm/Shear Wall | 1/11/2024 | Approved | JOSE AVILA |
| Deputy Wood Construction | 2/13/2024 | Conditional Approval | JUAN VALENZUELA |
| Floor/Roof Diaphrgm/Shear Wall | 2/16/2024 | Approved | JENNIFER RABUCHIN |
| Green Building Rough | 2/16/2024 | Not Ready for Inspection | JENNIFER RABUCHIN |
| PLUMBING-Rough | 2/16/2024 | Corrections Issued | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 2/23/2024 | Corrections Issued | JOSE AVILA |
| PLUMBING-Rough | 2/23/2024 | Approved | JOSE AVILA |
| ELECTRICAL-Rough | 3/8/2024 | Approved | JOSE AVILA |
| Interior/Exterior Lathing | 3/8/2024 | Approved | JOSE AVILA |
| BUILDING-Rough-Frame | 3/13/2024 | Corrections Issued | JOSE AVILA |
| Green Building Rough | 3/13/2024 | Approved | JOSE AVILA |
| HVAC-Rough | 3/13/2024 | Approved | JOSE AVILA |
| BUILDING-Rough-Frame | 3/20/2024 | Approved | JOSE AVILA |
| Drywall Nailing | 4/2/2024 | Approved | JOSE AVILA |
| Insulation | 4/2/2024 | Approved | JOSE AVILA |
| Shower Pan | 4/25/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| HVAC-Final | 5/1/2024 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| Interior/Exterior Lathing | 5/1/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| PLUMBING-Final | 6/10/2024 | Approved | OGANES TARAKHCHYAN |
| ELECTRICAL-Final | 8/6/2024 | Approved | OGANES TARAKHCHYAN |
| Green Building Final | 8/6/2024 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| SGSOV-Seismic Gas S/O Valve | 8/6/2024 | SGSOV Approved | OGANES TARAKHCHYAN |
| Smoke Detectors | 8/6/2024 | Approved | OGANES TARAKHCHYAN |
| Final | 8/15/2024 | OK to Issue CofO | JENNIFER RABUCHIN |
| Green Building Final | 8/15/2024 | Approved | JENNIFER RABUCHIN |
| HVAC-Final | 8/15/2024 | Approved | JENNIFER RABUCHIN |