15751 W ROMAR ST 91343
Certificate Information: 15751 W ROMAR ST 91343
- Application / Permit
- 23014-20000-02675
- Plan Check / Job No.
- B23VN08910
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EPLAN. PROPOSED 21' X 42' ADDITION OF 882 SF. 1-STORY ADU TO (E) GARAGE PER LAMC 12.22 A.33 (c), (d) AND (g). ALL WORK PER ENG.
- Permit Issued
- Issued on 4/22/2024
- Issuing Office
- Current Status
- Issued on 4/22/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 7/6/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 7/11/2023 | LUISANGEL VALENZUELA |
| Corrections Issued | 7/12/2023 | LUISANGEL VALENZUELA |
| Applicant returned to address corrections | 3/26/2024 | PINANK PATEL |
| Plan Check Approved | 3/29/2024 | PINANK PATEL |
| Issued | 4/22/2024 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 7/13/2023 | RYAN KIM |
| Eng Process Fee Ord 176,300 | Cleared | 7/13/2023 | RYAN KIM |
| Sewer availability | Cleared | 7/13/2023 | RYAN KIM |
| Construction near power lines | Cleared | 10/10/2023 | RIDWAN HARDY |
| Low Impact Development (LID) | Cleared | 2/23/2024 | SAMUEL LINN |
| Roof/Waste drainage to street | Cleared | 2/24/2024 | JOHN LIN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Kiledjian,, George Zohrab; Lic. No.: C74761 | , |
Inspector Information
| CHRISTOPHER ROJAS, (818) 374-1160 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 8/1/2024 | Corrections Issued | JENNIFER RABUCHIN |
| PLUMBING-Rough | 8/1/2024 | Corrections Issued | JENNIFER RABUCHIN |
| Excavation/Setback/Form/Re-Bar | 8/13/2024 | Partial Approval | JAVIER RAMOS JR |
| PLUMBING-Rough | 8/13/2024 | Partial Inspection | JAVIER RAMOS JR |
| Excavation/Setback/Form/Re-Bar | 9/6/2024 | Approved | JENNIFER RABUCHIN |
| Wood Frame | 3/4/2025 | Corrections Issued | JACK KARGODORIAN |
| Floor/Roof Diaphrgm/Shear Wall | 3/14/2025 | Partial Approval | MICHEL ABAJAN |
| ELECTRICAL-Rough | 3/20/2025 | Corrections Issued | JENNIFER RABUCHIN |
| PLUMBING-Rough | 3/20/2025 | Corrections Issued | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 4/21/2025 | Corrections Issued | NICHOLAS TROWBRIDGE |
| Interior/Exterior Lathing | 4/21/2025 | Corrections Issued | NICHOLAS TROWBRIDGE |
| PLUMBING-Rough | 4/21/2025 | Approved | NICHOLAS TROWBRIDGE |
| ELECTRICAL-Rough | 5/7/2025 | Approved | CHRISTOPHER ROJAS |
| HVAC-Rough | 5/7/2025 | Approved | CHRISTOPHER ROJAS |
| Interior/Exterior Lathing | 5/7/2025 | Partial Approval | CHRISTOPHER ROJAS |
| Interior/Exterior Lathing | 6/11/2025 | Approved | NICHOLAS TROWBRIDGE |
| Sewer | 6/11/2025 | Corrections Issued | NICHOLAS TROWBRIDGE |
| ELECTRICAL-Rough | 6/23/2025 | Approved | NICHOLAS TROWBRIDGE |
| PLUMBING-Rough | 6/23/2025 | Approved | NICHOLAS TROWBRIDGE |
| Sewer | 6/23/2025 | Approved | NICHOLAS TROWBRIDGE |
| Deputy Wood Construction | 2/27/2026 | Conditional Approval | JOSE AVILA |
| BUILDING-Rough-Frame | 4/3/2026 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| BUILDING-Rough-Frame | 4/13/2026 | Approved | KEVIN BERBERYAN |
| MERV13>=Rough | 4/13/2026 | Approved | KEVIN BERBERYAN |
| Insulation | 4/22/2026 | Approved | CHRISTOPHER ROJAS |
| Special/Order Compliance | 4/22/2026 | Corrections Issued | CHRISTOPHER ROJAS |
| BUILDING-Rough-Frame | 6/4/2026 | Approved | CHRISTOPHER ROJAS |