10644 N VANALDEN AVE 91326
Certificate Information: 10644 N VANALDEN AVE 91326
- Application / Permit
- 23014-20000-02668
- Plan Check / Job No.
- B23VN08895
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- TWO STORY ADDITION TO EXISTING SINGLE FAMILY DWELLING; CONVERT GARAGE AS PART OF SFD
- Permit Issued
- Issued on 9/6/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 1/17/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/5/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 7/13/2023 | SELLA BENYAMIN |
| Corrections Issued | 7/18/2023 | SELLA BENYAMIN |
| Quality Review Completed | 7/18/2023 | STEVEN KIM |
| Building Plans Picked Up | 7/20/2023 | APPLICANT |
| Plan Check Approved | 9/6/2023 | SELLA BENYAMIN |
| Issued | 9/6/2023 | APPLICANT |
| CofO in Progress | 12/10/2025 | DAVID SCANTLIN |
| CofO in Progress | 12/10/2025 | DAVID SCANTLIN |
| CofO in Progress | 12/29/2025 | DAVID SCANTLIN |
| Permit Finaled | 1/17/2026 | MICHAEL PELHAM |
| CofO Issued | 1/17/2026 | MICHAEL PELHAM |
| Permit Finaled | 1/17/2026 | MICHAEL PELHAM |
Permit Application Clearance Information
| BHO/Hillside ordinance | Cleared | 7/24/2023 | DAGOVERTO GUERRERO |
| BHO/Hillside ordinance | Cleared | 7/24/2023 | DAGOVERTO GUERRERO |
| BHO/Hillside ordinance | Cleared | 7/24/2023 | DAGOVERTO GUERRERO |
| BHO/Hillside ordinance | Cleared | 7/24/2023 | DAGOVERTO GUERRERO |
| Eng Process Fee Ord 176,300 | Cleared | 7/24/2023 | DAGOVERTO GUERRERO |
| Roof/Waste drainage to street | Cleared | 7/24/2023 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 7/24/2023 | DAGOVERTO GUERRERO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Garcia,, Eddy Alexander; Lic. No.: S6159 | 17958 LULL ST RESEDA, CA 91335 |
Inspector Information
| JACK KARGODORIAN, (818) 774-4319 | Office Hours: 7:00-8:00 AM MON-FRI |
| KRISTEN CAUSEY, (818) 774-4319 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 2/6/2024 | Partial Inspection | KRISTEN CAUSEY |
| Excavation/Setback/Form/Re-Bar | 4/23/2024 | Partial Approval | DAVID SCANTLIN |
| Footing/Foundation/Slab | 4/23/2024 | Approved | DAVID SCANTLIN |
| Excavation/Setback/Form/Re-Bar | 5/31/2024 | Approved | DAVID SCANTLIN |
| Sewer | 10/24/2024 | Approved | KRISTEN CAUSEY |
| Wood Frame | 2/5/2025 | Partial Inspection | KRISTEN CAUSEY |
| BUILDING-Rough-Frame | 3/10/2025 | Not Ready for Inspection | DAVID SCANTLIN |
| ELECTRICAL-Rough | 3/10/2025 | Partial Approval | DAVID SCANTLIN |
| Floor/Roof Diaphrgm/Shear Wall | 3/10/2025 | Approved | DAVID SCANTLIN |
| Green Building Rough | 3/10/2025 | Not Ready for Inspection | DAVID SCANTLIN |
| PLUMBING-Rough | 3/10/2025 | Approved | DAVID SCANTLIN |
| BUILDING-Rough-Frame | 3/21/2025 | Approved | KRISTEN CAUSEY |
| ELECTRICAL-Rough | 3/21/2025 | Approved | KRISTEN CAUSEY |
| Green Building Rough | 3/21/2025 | Approved | KRISTEN CAUSEY |
| HVAC-Rough | 3/21/2025 | Approved | KRISTEN CAUSEY |
| Interior/Exterior Lathing | 3/21/2025 | Partial Approval | KRISTEN CAUSEY |
| Insulation | 3/25/2025 | Approved | DAVID SCANTLIN |
| Drywall Nailing | 4/4/2025 | Approved | KRISTEN CAUSEY |
| Final | 6/6/2025 | Corrections Issued | DAVID SCANTLIN |
| Green Building Final | 6/6/2025 | Not Ready for Inspection | DAVID SCANTLIN |
| SGSOV-Seismic Gas S/O Valve | 6/6/2025 | SGSOV Approved | DAVID SCANTLIN |
| Smoke Detectors | 6/6/2025 | Approved | DAVID SCANTLIN |
| Final | 12/10/2025 | Not Ready for Inspection | DAVID SCANTLIN |
| Green Building Final | 12/10/2025 | Approved | DAVID SCANTLIN |
| Final | 12/24/2025 | OK to Issue CofO | DAVID SCANTLIN |