9738 N LEMONA AVE 91343
Certificate Information: 9738 N LEMONA AVE 91343
- Application / Permit
- 23014-20000-02665
- Plan Check / Job No.
- B23VN08864
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- REMOVE (E) CARPORT. (N) 16'6" X 30'10" ADDITION TO AND CONVERT (E) SECOND DWELLING UNIT PER ZA 120 INTO (N) ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d). WORK DONE PER ENGINEER DESIGN.
- Permit Issued
- Issued on 12/19/2023
- Issuing Office
- Current Status
- CofO Issued on 4/8/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/5/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 7/7/2023 | JEROME MAGAT PALMA |
| Corrections Issued | 7/11/2023 | JEROME MAGAT PALMA |
| Building Plans Picked Up | 7/18/2023 | APPLICANT |
| Issued | 12/19/2023 | APPLICANT |
| CofO in Progress | 3/21/2025 | JENNIFER RABUCHIN |
| Permit Finaled | 4/8/2025 | RUBEN SALAS |
| CofO Issued | 4/8/2025 | RUBEN SALAS |
| Permit Finaled | 4/8/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 8/19/2023 | NIKKI ZULUETA |
| Eng Process Fee Ord 176,300 | Cleared | 8/22/2023 | NIKKI ZULUETA |
| Miscellaneous | Cleared | 8/22/2023 | STEVEN WECHSLER |
| Low Impact Development (LID) | Cleared | 10/23/2023 | SHAHIN KHAZEY |
| Roof/Waste drainage to street | Cleared | 10/24/2023 | LEE GUILBEAUX |
| Sewer availability | Cleared | 10/24/2023 | LEE GUILBEAUX |
| Public Works-Highway Ded. | Cleared | 10/24/2023 | LEE GUILBEAUX |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Ni,, Zhang Yuan; Lic. No.: C68149 | 8232 GARVEY AVE 203 ROSEMEAD, CA 91770 |
Inspector Information
| JOHN COLEMAN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
| JENNIFER RABUCHIN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 2/14/2024 | Corrections Issued | CHRISTOPHER ROJAS |
| Sewer | 2/16/2024 | Approved | JENNIFER RABUCHIN |
| Underground Mechanical | 2/16/2024 | Partial Approval | JENNIFER RABUCHIN |
| Deputy Drilled-In Anchors | 2/21/2024 | Approved | JENNIFER RABUCHIN |
| Footing/Foundation/Slab | 2/21/2024 | Approved | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 3/1/2024 | Partial Approval | JOHN COLEMAN |
| BUILDING-Rough-Frame | 3/22/2024 | Corrections Issued | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 3/22/2024 | Corrections Issued | JENNIFER RABUCHIN |
| Green Building Rough | 3/22/2024 | Not Ready for Inspection | JENNIFER RABUCHIN |
| HVAC-Rough | 3/22/2024 | Corrections Issued | JENNIFER RABUCHIN |
| PLUMBING-Rough | 3/22/2024 | Approved | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 3/29/2024 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 3/29/2024 | Approved | JENNIFER RABUCHIN |
| Green Building Rough | 3/29/2024 | Approved | JENNIFER RABUCHIN |
| HVAC-Rough | 3/29/2024 | Approved | JENNIFER RABUCHIN |
| Insulation | 3/29/2024 | Approved | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 3/29/2024 | Partial Approval | JENNIFER RABUCHIN |
| PLUMBING-Rough | 3/29/2024 | Approved | JENNIFER RABUCHIN |
| Wood Frame | 3/29/2024 | Approved | JENNIFER RABUCHIN |
| Drywall Nailing | 4/4/2024 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 4/4/2024 | Approved | JENNIFER RABUCHIN |
| Green Building Rough | 4/4/2024 | Approved | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 4/4/2024 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Rough | 4/4/2024 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Final | 6/24/2024 | Corrections Issued | JENNIFER RABUCHIN |
| Green Building Final | 6/24/2024 | Approved | JENNIFER RABUCHIN |
| HVAC-Final | 6/24/2024 | Corrections Issued | JENNIFER RABUCHIN |
| PLUMBING-Final | 6/24/2024 | Corrections Issued | JENNIFER RABUCHIN |
| ELECTRICAL-Final | 3/6/2025 | Approved | KEVIN BERBERYAN |
| Final | 3/6/2025 | Partial Approval | KEVIN BERBERYAN |
| HVAC-Final | 3/6/2025 | Approved | KEVIN BERBERYAN |
| PLUMBING-Final | 3/6/2025 | Approved | KEVIN BERBERYAN |
| SGSOV-Seismic Gas S/O Valve | 3/6/2025 | SGSOV Approved | KEVIN BERBERYAN |
| Smoke Detectors | 3/6/2025 | Approved | KEVIN BERBERYAN |
| Final | 3/21/2025 | OK to Issue CofO | JENNIFER RABUCHIN |