11212 N HERRICK AVE 91331
Certificate Information: 11212 N HERRICK AVE 91331
- Application / Permit
- 23014-20000-02658
- Plan Check / Job No.
- B23VN08845
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePLAN. CONVERT EXISTING DETACHED CARPORT AND REC ROOM WITH (N) ADDITION TO ADU PER LAMC 12.22 A.33 (c)-(d)
- Permit Issued
- Issued on 11/17/2023
- Issuing Office
- Current Status
- CofO Issued on 4/16/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/11/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 7/17/2023 | WEIJIAN HUANG |
| Corrections Issued | 7/18/2023 | WEIJIAN HUANG |
| Applicant returned to address corrections | 9/19/2023 | HANS SANTIAGO |
| Plan Check Approved | 11/9/2023 | KEVIN MORALES |
| Issued | 11/17/2023 | APPLICANT |
| CofO in Progress | 4/11/2024 | MICHEL ABAJAN |
| Permit Finaled | 4/16/2024 | RUBEN SALAS |
| CofO Issued | 4/16/2024 | RUBEN SALAS |
| Permit Finaled | 4/16/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 8/22/2023 | DARIN LAM |
| Roof/Waste drainage to street | Cleared | 9/5/2023 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 9/5/2023 | DAGOVERTO GUERRERO |
| ZA Case | Cleared | 9/5/2023 | RYAN LY |
| ZA Case | Cleared | 9/5/2023 | RYAN LY |
| ZA Case | Cleared | 9/5/2023 | RYAN LY |
| ZA Case | Cleared | 9/5/2023 | RYAN LY |
| ZA Case | Cleared | 9/5/2023 | RYAN LY |
| ZA Case | Cleared | 9/5/2023 | RYAN LY |
| Eng Process Fee Ord 176,300 | Cleared | 9/11/2023 | DAGOVERTO GUERRERO |
| Clean Up Green Up | Cleared | 10/30/2023 | DANIEL CORONADO |
Contact Information
| Contractor | Teddys Fine Builders; Lic. No.: 1100422-B | , |
Inspector Information
| MICHEL ABAJAN, (818) 374-9932 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 1/9/2024 | Conditional Approval | DAVID MATSON |
| PLUMBING-Rough | 1/11/2024 | Partial Approval | MICHEL ABAJAN |
| Underground Mechanical | 1/11/2024 | Partial Approval | MICHEL ABAJAN |
| Excavation/Setback/Form/Re-Bar | 1/16/2024 | Approved | MICHEL ABAJAN |
| Footing/Foundation/Slab | 1/16/2024 | Approved | MICHEL ABAJAN |
| METHANE-Barrier | 1/16/2024 | Approved | MICHEL ABAJAN |
| METHANE-Subgrade | 1/16/2024 | Approved | MICHEL ABAJAN |
| Floor/Roof Diaphrgm/Shear Wall | 2/12/2024 | Partial Approval | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 2/20/2024 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Rough | 2/20/2024 | Approved | MICHEL ABAJAN |
| HVAC-Rough | 2/20/2024 | Approved | MICHEL ABAJAN |
| PLUMBING-Rough | 2/20/2024 | Approved | MICHEL ABAJAN |
| Deputy Wood Construction | 2/21/2024 | Conditional Approval | ROBERT GOLD |
| Insulation | 2/26/2024 | Approved | MICHEL ABAJAN |
| Interior/Exterior Lathing | 2/26/2024 | Approved | MICHEL ABAJAN |
| Insulation | 2/27/2024 | Approved | MICHEL ABAJAN |
| Drywall Nailing | 3/1/2024 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Final | 4/11/2024 | Approved | MICHEL ABAJAN |
| Final | 4/11/2024 | OK to Issue CofO | MICHEL ABAJAN |
| HVAC-Final | 4/11/2024 | Approved | MICHEL ABAJAN |
| PLUMBING-Final | 4/11/2024 | Approved | MICHEL ABAJAN |
| SGSOV-Seismic Gas S/O Valve | 4/11/2024 | SGSOV Approved | MICHEL ABAJAN |
| Service/Power Release | 4/11/2024 | Approved | MICHEL ABAJAN |
| Smoke Detectors | 4/11/2024 | Approved | MICHEL ABAJAN |