20304 W MOBILE ST 91306

Certificate Information: 20304 W MOBILE ST 91306

Application / Permit
23014-20000-02654
Plan Check / Job No.
B23VN08831
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
13'-6" X 18'-2" ADDITION TO AND CONVERT (E) DETACHED GARAGE INTO A (N) IRREGULAR SHAPED DETACHED 13'-6" x 39'-3" ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d) PER ENGINEERING
Permit Issued
Issued on 11/16/2023
Issuing Office
Valley
Current Status
CofO Issued on 5/2/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/5/2023 APPLICANT
Assigned to Plan Check Engineer 7/7/2023 JEROME MAGAT PALMA
Corrections Issued 7/8/2023 JEROME MAGAT PALMA
Building Plans Picked Up 7/14/2023 APPLICANT
Plan Check Approved 11/14/2023 ALFRED RAMIREZ
Issued 11/16/2023 APPLICANT
CofO in Progress 4/26/2024 ARUTYUN MADATYAN
Permit Finaled 5/2/2024 JOHN JANSON
CofO Issued 5/2/2024 JOHN JANSON
Permit Finaled 5/2/2024 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 7/31/2023 MEGAN GODINEZ
Roof/Waste drainage to street Cleared 7/31/2023 MEGAN GODINEZ
Eng Process Fee Ord 176,300 Cleared 8/14/2023 MEGAN GODINEZ
Sewer availability Cleared 9/13/2023 MARKOS PEREZ-BRAN
ZI Cleared 9/13/2023 BRENNEN OBETO
Construction near power lines Cleared 11/13/2023 RIDWAN HARDY
Construction within easement Cleared 11/13/2023 RIDWAN HARDY

Contact Information

Contractor Nextdoor Construction And Remodeling Inc; Lic. No.: 1061320-B 18653 VENTURA BLVD #393      TARZANA, CA 91356
Engineer Mourad,, Daniel; Lic. No.: C83387 542 N FULLER AVE      LOS ANGELES, CA 90036

Inspector Information

DAVID FASTIGGI, (818) 774-4317 Office Hours: 7:00-8:00 AM MON-FRI
ALEXANDER HANDY, (818) 774-4317 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 12/29/2023 Conditional Approval ALEXANDER HANDY
Excavation/Setback/Form/Re-Bar 1/10/2024 Not Ready for Inspection ALEXANDER HANDY
PLUMBING-Rough 1/10/2024 Corrections Issued ALEXANDER HANDY
Footing/Foundation/Slab 1/12/2024 Corrections Issued ALEXANDER HANDY
PLUMBING-Rough 1/12/2024 Partial Approval ALEXANDER HANDY
BUILDING-Rough-Frame 2/7/2024 Partial Approval JOHN KIDWELL
Floor/Roof Diaphrgm/Shear Wall 2/7/2024 Partial Approval JOHN KIDWELL
Green Building Rough 2/7/2024 Not Ready for Inspection JOHN KIDWELL
Wood Frame 2/7/2024 Partial Approval JOHN KIDWELL
ELECTRICAL-Rough 2/13/2024 Not Ready for Inspection ARUTYUN MADATYAN
Floor/Roof Diaphrgm/Shear Wall 2/13/2024 Partial Approval ARUTYUN MADATYAN
HVAC-Rough 2/13/2024 Not Ready for Inspection ARUTYUN MADATYAN
Deputy Wood Construction 2/14/2024 Conditional Approval ARUTYUN MADATYAN
BUILDING-Rough-Frame 2/23/2024 Conditional Approval ARUTYUN MADATYAN
ELECTRICAL-Rough 2/23/2024 Approved ARUTYUN MADATYAN
HVAC-Rough 2/23/2024 Corrections Issued ARUTYUN MADATYAN
Interior/Exterior Lathing 2/23/2024 Approved ARUTYUN MADATYAN
PLUMBING-Rough 2/23/2024 Approved ARUTYUN MADATYAN
BUILDING-Rough-Frame 2/27/2024 Approved ARUTYUN MADATYAN
Green Building Rough 2/27/2024 Approved ARUTYUN MADATYAN
HVAC-Rough 2/27/2024 Approved ARUTYUN MADATYAN
Insulation 3/4/2024 Approved ARUTYUN MADATYAN
Drywall Nailing 3/6/2024 Approved ARUTYUN MADATYAN
Interior/Exterior Lathing 3/6/2024 Approved ARUTYUN MADATYAN
Rough-Elec/Plmb/HVAC 3/19/2024 Corrections Issued ARUTYUN MADATYAN
Rough-Elec/Plmb/HVAC 3/27/2024 Partial Approval ARUTYUN MADATYAN
ELECTRICAL-Final 4/17/2024 Approved ARUTYUN MADATYAN
Final 4/17/2024 Corrections Issued ARUTYUN MADATYAN
Footing/Foundation/Slab 4/17/2024 Approved ARUTYUN MADATYAN
Green Building Final 4/17/2024 Not Ready for Inspection ARUTYUN MADATYAN
HVAC-Final 4/17/2024 Approved ARUTYUN MADATYAN
PLUMBING-Final 4/17/2024 Approved ARUTYUN MADATYAN
SGSOV-Seismic Gas S/O Valve 4/17/2024 SGSOV Approved ARUTYUN MADATYAN
Service/Power Release 4/17/2024 Approved ARUTYUN MADATYAN
Smoke Detectors 4/17/2024 Approved ARUTYUN MADATYAN
Final 4/25/2024 OK to Issue CofO ARUTYUN MADATYAN
Green Building Final 4/25/2024 Approved ARUTYUN MADATYAN