5500 N BABCOCK AVE 91607

Certificate Information: 5500 N BABCOCK AVE 91607

Application / Permit
23014-20000-02653
Plan Check / Job No.
B23VN08826
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ePLAN. MAJOR REMODEL WITH NEW GROUND FLOOR AND 2ND FLOOR ADDITION TO (E) SINGLE FAMILY DWELLING. NEW ATTACHED TRELLIS.
Permit Issued
Issued on 1/31/2024
Issuing Office
Current Status
CofO Issued on 5/28/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/12/2023 APPLICANT
Assigned to Plan Check Engineer 7/27/2023 SUNMIN LEE
Corrections Issued 8/2/2023 SUNMIN LEE
Quality Review Completed 8/4/2023 GARO TELMI
Applicant returned to address corrections 1/2/2024 SUNMIN LEE
Applicant returned to address corrections 1/10/2024 SUNMIN LEE
Applicant returned to address corrections 1/19/2024 SUNMIN LEE
Plan Check Approved 1/29/2024 SUNMIN LEE
Issued 1/31/2024 APPLICANT
CofO in Progress 1/8/2026 WAYNE REGESTER
No Progress 3/26/2026 RAUL OLAGI
CofO in Progress 3/26/2026 RAUL OLAGI
CofO in Progress 3/26/2026 RAUL OLAGI
CofO in Progress 5/18/2026 RAUL OLAGI
Permit Finaled 5/28/2026 RUBEN SALAS
CofO Issued 5/28/2026 RUBEN SALAS
Permit Finaled 5/28/2026 RUBEN SALAS

Permit Application Clearance Information

Specific Plan Cleared 9/5/2023 CHRISTIAN PEARSON
ZI Cleared 9/5/2023 CHRISTIAN PEARSON
Miscellaneous Cleared 9/12/2023 NELSON RODRIGUEZ
Low Impact Development (LID) Cleared 12/18/2023 PATRICK LOPEZ
Roof/Waste drainage to street Cleared 12/18/2023 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 12/19/2023 CARLOS AGUILERA
Sewer availability Cleared 12/19/2023 CARLOS AGUILERA

Contact Information

Architect Song,, Michael; Lic. No.: C32566 821 LIME AVENUE      LONG BEACH, CA 90813
Contractor Inspire Concepts Inc ; Lic. No.: 1037765-B       ,
Engineer Alson,, Ken; Lic. No.: C41697 9744 MAPLE ST 201      BELLFLOWER, CA 90706
Engineer Alson,, Ken; Lic. No.: NA41697       ,

Inspector Information

WAYNE REGESTER, (818) 374-1164 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 4/18/2024 Conditional Approval JOSE AVILA
Pre-Inspection 4/22/2024 Partial Inspection JOSE AVILA
Underground Mechanical 4/22/2024 Partial Approval JOSE AVILA
Deputy Drilled-In Anchors 5/2/2024 Conditional Approval JUAN VALENZUELA
Excavation/Setback/Form/Re-Bar 5/7/2024 Corrections Issued MISAEL ESPARZA
Excavation/Setback/Form/Re-Bar 5/9/2024 Approved MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 6/10/2024 Partial Approval OGANES TARAKHCHYAN
Deputy Drilled-In Anchors 8/29/2024 Partial Approval OGANES TARAKHCHYAN
ELECTRICAL-Rough 9/4/2024 Approved CHRISTOPHE COCHRAN
Gas Test 9/4/2024 No Access for Inspection CHRISTOPHE COCHRAN
Floor/Roof Diaphrgm/Shear Wall 9/9/2024 Corrections Issued OGANES TARAKHCHYAN
HVAC-Rough 9/9/2024 Not Ready for Inspection OGANES TARAKHCHYAN
PLUMBING-Rough 9/9/2024 Approved OGANES TARAKHCHYAN
Floor/Roof Diaphrgm/Shear Wall 9/23/2024 Partial Approval OGANES TARAKHCHYAN
Deputy Wood Construction 9/24/2024 Conditional Approval ROBERT GOLD
Floor/Roof Diaphrgm/Shear Wall 9/25/2024 Approved OGANES TARAKHCHYAN
Interior/Exterior Lathing 11/8/2024 Approved GAREN HAYRAPETYAN
Service/Power Release 11/8/2024 Not Ready for Inspection GAREN HAYRAPETYAN
Shower Pan 11/8/2024 Approved GAREN HAYRAPETYAN
BUILDING-Rough-Frame 11/13/2024 Approved OGANES TARAKHCHYAN
Wood Frame 11/13/2024 Approved OGANES TARAKHCHYAN
Insulation 12/4/2024 Approved GAREN HAYRAPETYAN
Interior/Exterior Lathing 12/4/2024 Approved GAREN HAYRAPETYAN
Drywall Nailing 12/19/2024 Approved GAREN HAYRAPETYAN
Pre-Inspection 1/29/2025 Approved GAREN HAYRAPETYAN
Gas Test 5/19/2025 Approved GAREN HAYRAPETYAN
Sewer 5/19/2025 Approved GAREN HAYRAPETYAN
Underground Mechanical 5/23/2025 Approved OGANES TARAKHCHYAN
ELECTRICAL-Final 8/20/2025 Not Ready for Inspection GAREN HAYRAPETYAN
HVAC-Final 8/20/2025 Not Ready for Inspection GAREN HAYRAPETYAN
PLUMBING-Final 8/20/2025 Not Ready for Inspection GAREN HAYRAPETYAN
Service/Power Release 8/20/2025 Not Ready for Inspection GAREN HAYRAPETYAN
ELECTRICAL-Final 9/9/2025 Approved OGANES TARAKHCHYAN
Footing/Foundation/Slab 9/9/2025 Approved OGANES TARAKHCHYAN
HVAC-Final 9/9/2025 Approved OGANES TARAKHCHYAN
PLUMBING-Final 9/9/2025 Approved OGANES TARAKHCHYAN
SGSOV-Seismic Gas S/O Valve 9/9/2025 SGSOV Approved OGANES TARAKHCHYAN
Service/Power Release 9/9/2025 Approved OGANES TARAKHCHYAN
Smoke Detectors 9/9/2025 Approved OGANES TARAKHCHYAN
Final 1/8/2026 OK to Issue CofO WAYNE REGESTER
Special/Order Compliance 3/26/2026 Corrections Issued RAUL OLAGI