7862-7864 N CLEARFIELD AVE 91402
Certificate Information: 7862-7864 N CLEARFIELD AVE 91402
- Application / Permit
- 23014-20000-02638
- Plan Check / Job No.
- B23VN08796
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Eplan: (N) 14'11" X 25'2" IRREGULARLY SHAPED ADDITION (120 SF) TO (E) SINGLE FAMILY DWELLING TO BECOME NEW LIVING, DINING, KITCHEN AREA. CONVERT (E) 18'-3" X 31'-2" IRREGULARLY SHAPED ATTACHED GARAGE INTO (N) ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A). WORK DONE PER ENGINEERING.
- Permit Issued
- Issued on 8/25/2023
- Issuing Office
- Current Status
- CofO Issued on 4/11/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/5/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 7/10/2023 | MADISON ODELL |
| Corrections Issued | 7/11/2023 | MADISON ODELL |
| Applicant returned to address corrections | 8/11/2023 | DAVID CASTILLO |
| Plan Check Approved | 8/25/2023 | DAVID CASTILLO |
| Issued | 8/25/2023 | APPLICANT |
| Permit Finaled | 4/11/2024 | RUBEN SALAS |
| CofO Issued | 4/11/2024 | RUBEN SALAS |
| Permit Finaled | 4/11/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 7/11/2023 | RYAN KIM |
| CPC | Cleared | 7/11/2023 | STEVEN WECHSLER |
| Roof/Waste drainage to street | Cleared | 7/11/2023 | RYAN KIM |
| Sewer availability | Cleared | 7/11/2023 | RYAN KIM |
| Eng Process Fee Ord 176,300 | Cleared | 7/12/2023 | RYAN KIM |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Li,, Dacheng D; Lic. No.: C58075 | 1400 N KRAEMER BLVD #712 PLACENTIA, CA 92781 |
Inspector Information
| OGANES TARAKHCHYAN, (818) 374-1162 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 10/3/2023 | Conditional Approval | DAVID MATSON |
| Footing/Foundation/Slab | 10/3/2023 | Corrections Issued | GREGG CUMMINGS |
| PLUMBING-Rough | 10/3/2023 | Corrections Issued | GREGG CUMMINGS |
| Excavation/Setback/Form/Re-Bar | 10/6/2023 | Approved | CHRISTOPHER ROJAS |
| PLUMBING-Rough | 10/6/2023 | Partial Approval | CHRISTOPHER ROJAS |
| Floor/Roof Diaphrgm/Shear Wall | 11/7/2023 | Partial Approval | GREGG CUMMINGS |
| Deputy Reinf. Concrete | 11/22/2023 | Conditional Approval | DAVID MATSON |
| Deputy Drilled-In Anchors | 11/27/2023 | Conditional Approval | DAVID MATSON |
| Deputy Wood Construction | 11/27/2023 | Conditional Approval | DAVID MATSON |
| ELECTRICAL-Rough | 11/30/2023 | Approved | GREGG CUMMINGS |
| HVAC-Rough | 11/30/2023 | Approved | GREGG CUMMINGS |
| PLUMBING-Rough | 11/30/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 12/14/2023 | Approved | GREGG CUMMINGS |
| Green Building Rough | 12/14/2023 | Approved | GREGG CUMMINGS |
| PLUMBING-Rough | 12/14/2023 | Approved | GREGG CUMMINGS |
| Shower Pan | 12/14/2023 | Approved | GREGG CUMMINGS |
| Insulation | 12/26/2023 | Corrections Issued | GREGG CUMMINGS |
| Interior/Exterior Lathing | 12/26/2023 | Partial Approval | GREGG CUMMINGS |
| Drywall Nailing | 12/29/2023 | Approved | ROBERT GOLD |
| Interior/Exterior Lathing | 1/16/2024 | Partial Approval | GREGG CUMMINGS |
| Underground Mechanical | 2/2/2024 | Corrections Issued | GREGG CUMMINGS |
| Underground Mechanical | 2/8/2024 | Approved | CHRISTOPHER ROJAS |
| ELECTRICAL-Final | 2/20/2024 | Not Ready for Inspection | GREGG CUMMINGS |
| HVAC-Final | 2/20/2024 | Not Ready for Inspection | GREGG CUMMINGS |
| PLUMBING-Final | 2/20/2024 | Not Ready for Inspection | GREGG CUMMINGS |
| Final | 3/7/2024 | Corrections Issued | GREGG CUMMINGS |
| Footing/Foundation/Slab | 3/7/2024 | Approved | GREGG CUMMINGS |
| SGSOV-Seismic Gas S/O Valve | 3/7/2024 | SGSOV Not Ready | GREGG CUMMINGS |
| Smoke Detectors | 3/7/2024 | Approved | GREGG CUMMINGS |
| ELECTRICAL-Final | 3/15/2024 | Approved | GREGG CUMMINGS |
| Final | 3/15/2024 | Corrections Issued | GREGG CUMMINGS |
| PLUMBING-Final | 3/15/2024 | Approved | GREGG CUMMINGS |
| SGSOV-Seismic Gas S/O Valve | 3/15/2024 | SGSOV Approved | GREGG CUMMINGS |
| Final | 3/22/2024 | Conditional Approval | GREGG CUMMINGS |
| HVAC-Final | 3/22/2024 | Approved | GREGG CUMMINGS |
| Service/Power Release | 3/22/2024 | Approved | GREGG CUMMINGS |