1485 S CARDIFF AVE 90035
Certificate Information: 1485 S CARDIFF AVE 90035
- Application / Permit
- 23014-20000-02634
- Plan Check / Job No.
- B23VN08772
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- MAJOR REMODEL AND 2-STORY ADDITION TO ERECT AN IRR. SHAPED 2-STORY 34'-6" x 72'-3" SINGLE FAMILY DWELLING W/ ATT. OPEN TRELLIS; NFPA-13D THRU-OUT
- Permit Issued
- Issued on 1/15/2025
- Issuing Office
- Current Status
- Issued on 1/15/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 6/30/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 7/6/2023 | SEAN SHAHMIRI |
| Corrections Issued | 7/10/2023 | SEAN SHAHMIRI |
| Quality Review Completed | 7/12/2023 | OMID HEDAYAT |
| Building Plans Picked Up | 7/14/2023 | APPLICANT |
| Applicant returned to address corrections | 12/17/2024 | SEAN SHAHMIRI |
| Plan Check Approved | 1/3/2025 | SEAN SHAHMIRI |
| Issued | 1/15/2025 | APPLICANT |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 10/15/2024 | STEVE MELGAR |
| Sewer availability | Cleared | 10/15/2024 | STEVE MELGAR |
| Grading Pre-Inspection | Cleared | 10/31/2024 | VASIL MIHALEV |
| Roof/Waste drainage to street | Cleared | 12/10/2024 | WALLIE JONG |
Contact Information
| Contractor | David Elliot Builders Inc; Lic. No.: 1021000-B | 5979 W 3RD ST SUITE #203 LOS ANGELES, CA 90036 |
| Engineer | Sivushenka,, Mikita; Lic. No.: C87698 | 22814 DOLOROSA ST WOODLAND HILLS, CA 91367 |
Inspector Information
| ASHLEY THOMPSON, (310) 914-3897 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 6/11/2025 | Approved | EVAN COOPER |
| METHANE-Subgrade | 6/11/2025 | Approved | EVAN COOPER |
| Underground Mechanical | 6/11/2025 | Not Ready for Inspection | EVAN COOPER |
| Deputy Other (see comments) | 6/13/2025 | Conditional Approval | ARAM AVEDISIAN |
| Floor/Roof Diaphrgm/Shear Wall | 7/2/2025 | Partial Approval | EVAN COOPER |
| PLUMBING-Rough | 7/2/2025 | Partial Approval | EVAN COOPER |
| Sewer | 7/2/2025 | Partial Approval | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 7/8/2025 | Corrections Issued | ASHLEY THOMPSON |
| Floor/Roof Diaphrgm/Shear Wall | 7/25/2025 | Corrections Issued | ASHLEY THOMPSON |
| Floor/Roof Diaphrgm/Shear Wall | 10/9/2025 | Partial Approval | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 10/17/2025 | Partial Approval | EVAN COOPER |
| Deputy Reinf. Concrete | 12/2/2025 | Conditional Approval | ANDREW NAVE |
| HVAC-Rough | 12/12/2025 | Approved | EVAN COOPER |
| PLUMBING-Rough | 12/12/2025 | Approved | EVAN COOPER |
| ELECTRICAL-Rough | 12/30/2025 | Approved | ASHLEY THOMPSON |
| BUILDING-Rough-Frame | 1/2/2026 | Partial Approval | ASHLEY THOMPSON |
| Green Building Rough | 1/2/2026 | Approved | ASHLEY THOMPSON |
| METHANE-Rough | 1/2/2026 | Approved | ASHLEY THOMPSON |
| Special/Order Compliance | 1/2/2026 | Partial Inspection | DAVID FASTIGGI |
| BUILDING-Rough-Frame | 3/13/2026 | Approved | ASHLEY THOMPSON |
| Final | 3/13/2026 | Corrections Issued | ASHLEY THOMPSON |
| Insulation | 3/13/2026 | Approved | ASHLEY THOMPSON |
| Shower Pan | 3/13/2026 | Approved | ASHLEY THOMPSON |
| Drywall Nailing | 3/24/2026 | Approved | ASHLEY THOMPSON |
| Interior/Exterior Lathing | 3/24/2026 | Approved | ASHLEY THOMPSON |