13815 W MAGNOLIA BLVD 91423

Certificate Information: 13815 W MAGNOLIA BLVD 91423

Application / Permit
23014-20000-02631
Plan Check / Job No.
B23VN08759
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
IRR SHAPED ADDITION (2,458 SF) AT REAR OF (E) ONE-STORY SINGLE FAMILY DWELLING, CONVERT (E) CARPORT TO HABITABLE AREA, ENLARGE (E) ATT ONE CAR GARAGE TO 2-CAR GARAGE, ADD NEW OPEN TRELLIS AT REAR, AND REMODEL; NFPA-13D THRU-OUT
Permit Issued
Issued on 10/23/2025
Issuing Office
Valley
Current Status
Issued on 10/23/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 6/30/2023 APPLICANT
Assigned to Plan Check Engineer 7/6/2023 SEAN SHAHMIRI
Corrections Issued 7/10/2023 SEAN SHAHMIRI
Quality Review Completed 7/12/2023 OMID HEDAYAT
Building Plans Picked Up 7/14/2023 APPLICANT
Applicant returned to address corrections 8/28/2024 SEAN SHAHMIRI
Plan Check Approved 9/15/2025 SEAN SHAHMIRI
Issued 10/23/2025 APPLICANT

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 9/5/2025 CINDY QI
Sewer availability Cleared 9/5/2025 CINDY QI
Roof/Waste drainage to street Cleared 9/16/2025 CINDY QI

Contact Information

Contractor Quality First Builders Inc; Lic. No.: 990316-B 15250 VENTURA BLVD SUITE 601      SHERMAN OAKS, CA 91403
Engineer Farag,, Amgad N; Lic. No.: C74076 27050 MAPLE TREE CT      VALENCIA, CA 91381

Inspector Information

JOSE AVILA, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI
VINCENT HANLEY, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Sewer 12/17/2025 Approved RYAN SALAZAR
Deputy Drilled-In Anchors 12/19/2025 Conditional Approval JOAQUIN GREENOUGH
Footing/Foundation/Slab 12/19/2025 Approved RYAN SALAZAR
Floor/Roof Diaphrgm/Shear Wall 1/7/2026 Partial Approval RYAN SALAZAR
Floor/Roof Diaphrgm/Shear Wall 1/9/2026 Partial Approval RYAN SALAZAR
Deputy Drilled-In Anchors 1/29/2026 Conditional Approval JOAQUIN GREENOUGH
Deputy Wood Construction 1/29/2026 Conditional Approval JOAQUIN GREENOUGH
BUILDING-Rough-Frame 1/30/2026 Corrections Issued KIRK SANDERS
Floor/Roof Diaphrgm/Shear Wall 1/30/2026 Corrections Issued KIRK SANDERS
Floor/Roof Diaphrgm/Shear Wall 2/4/2026 Partial Approval OGANES TARAKHCHYAN
Rough-Elec/Plmb/HVAC 3/18/2026 Approved VINCENT HANLEY
BUILDING-Rough-Frame 4/7/2026 Partial Approval VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 4/23/2026 Approved VINCENT HANLEY
Interior/Exterior Lathing 4/23/2026 Partial Approval VINCENT HANLEY
BUILDING-Rough-Frame 4/27/2026 Partial Approval VINCENT HANLEY
Green Building Rough 4/27/2026 Approved VINCENT HANLEY
Interior/Exterior Lathing 4/27/2026 Partial Approval VINCENT HANLEY
BUILDING-Rough-Frame 5/14/2026 Approved VINCENT HANLEY
Green Building Rough 5/14/2026 Approved VINCENT HANLEY
Insulation 5/14/2026 Approved VINCENT HANLEY
Verify Sprinkler Sign Off 5/14/2026 Approved VINCENT HANLEY
Drywall Nailing 5/21/2026 Approved VINCENT HANLEY
Shower Pan 6/15/2026 Approved VINCENT HANLEY
Interior/Exterior Lathing 7/28/2026 Approved VINCENT HANLEY