11305 N GLENOAKS BLVD 91331
Certificate Information: 11305 N GLENOAKS BLVD 91331
- Application / Permit
- 23014-20000-02626
- Plan Check / Job No.
- B23VN08740
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- 31' X 24' IRREGULAR SHAPED ADDITION TO AND CONVERT 20' X 18' DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d)
- Permit Issued
- Issued on 9/25/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 4/8/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/30/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 7/7/2023 | KAMYAR EMAMI |
| Corrections Issued | 7/7/2023 | KAMYAR EMAMI |
| Building Plans Picked Up | 7/11/2023 | APPLICANT |
| Plan Check Approved | 9/14/2023 | ALEC MOUSAKHANIAN |
| Issued | 9/25/2023 | APPLICANT |
| CofO in Progress | 3/27/2025 | MICHEL ABAJAN |
| Permit Finaled | 4/8/2025 | RUBEN SALAS |
| CofO Issued | 4/8/2025 | RUBEN SALAS |
| Permit Finaled | 4/8/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 7/17/2023 | ROMAN GUTIERREZ |
| Clean Up Green Up | Cleared | 7/18/2023 | ASHLEY RODARTE |
| Eng Process Fee Ord 176,300 | Cleared | 7/19/2023 | ROMAN GUTIERREZ |
| Sewer availability | Cleared | 8/14/2023 | ROMAN GUTIERREZ |
| Low Impact Development (LID) | Cleared | 8/30/2023 | SAMUEL LINN |
| Roof/Waste drainage to street | Cleared | 9/1/2023 | JOHN LIN |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| MICHEL ABAJAN, (818) 374-9932 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 12/29/2023 | Partial Approval | MICHEL ABAJAN |
| Footing/Foundation/Slab | 1/17/2024 | Approved | MICHEL ABAJAN |
| METHANE-Barrier | 1/17/2024 | Approved | MICHEL ABAJAN |
| METHANE-Subgrade | 1/17/2024 | Approved | MICHEL ABAJAN |
| Floor/Roof Diaphrgm/Shear Wall | 2/9/2024 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Rough | 3/6/2024 | Approved | MICHEL ABAJAN |
| PLUMBING-Rough | 3/6/2024 | Approved | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 3/11/2024 | Corrections Issued | KEVIN BERBERYAN |
| Green Building Rough | 3/11/2024 | Not Ready for Inspection | KEVIN BERBERYAN |
| HVAC-Rough | 3/11/2024 | Corrections Issued | KEVIN BERBERYAN |
| BUILDING-Rough-Frame | 3/21/2024 | Corrections Issued | JOHN COLEMAN |
| Green Building Rough | 3/21/2024 | Approved | JOHN COLEMAN |
| BUILDING-Rough-Frame | 4/2/2024 | Approved | MICHEL ABAJAN |
| Insulation | 4/9/2024 | Approved | MICHEL ABAJAN |
| Drywall Nailing | 5/1/2024 | Approved | MICHEL ABAJAN |
| PLUMBING-Rough | 5/16/2024 | Partial Approval | JOHN COLEMAN |
| Underground Mechanical | 8/19/2024 | Corrections Issued | JENNIFER RABUCHIN |
| PLUMBING-Rough | 9/3/2024 | Approved | MATTHEW NELSON |
| ELECTRICAL-Rough | 9/16/2024 | Corrections Issued | MICHEL ABAJAN |
| ELECTRICAL-Rough | 11/4/2024 | Partial Approval | MICHEL ABAJAN |
| Final | 12/17/2024 | Corrections Issued | MICHEL ABAJAN |
| Green Building Final | 12/17/2024 | Approved | MICHEL ABAJAN |
| SGSOV-Seismic Gas S/O Valve | 12/17/2024 | SGSOV Not Ready | MICHEL ABAJAN |
| Smoke Detectors | 12/17/2024 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Final | 1/24/2025 | Approved | MICHEL ABAJAN |
| Final | 1/24/2025 | Corrections Issued | MICHEL ABAJAN |
| HVAC-Final | 1/24/2025 | Approved | MICHEL ABAJAN |
| PLUMBING-Final | 1/24/2025 | Approved | MICHEL ABAJAN |
| SGSOV-Seismic Gas S/O Valve | 1/24/2025 | SGSOV Approved | MICHEL ABAJAN |
| Final | 3/26/2025 | OK to Issue CofO | MICHEL ABAJAN |