Work Description
INTERIOR REMODEL, 6'-6" X 29'-2" ADDITION TO (E) SFD, NEW 19'-6" x 11'-6" ATTACHED COVERED PATIO ADDITION TO (E) SFD PER ENGINEERING.
Permit Issued
Issued on 8/1/2023
Issuing Office
Valley
Current Status
CofO Issued on 4/23/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/30/2023 APPLICANT
Assigned to Plan Check Engineer 7/5/2023 ARTIN ZARUKIAN
Corrections Issued 7/5/2023 ARTIN ZARUKIAN
Building Plans Picked Up 7/11/2023 APPLICANT
Applicant returned to address corrections 7/20/2023 OMAR GARNICA
Plan Check Approved 8/1/2023 GIOVANNY CHAVEZ
Issued 8/1/2023 APPLICANT
CofO in Progress 2/15/2024 ALEXANDER HANDY
Permit Finaled 4/23/2024 JOHN JANSON
CofO Issued 4/23/2024 JOHN JANSON
Permit Finaled 4/23/2024 JOHN JANSON

Permit Application Clearance Information

ZA Case Cleared 7/21/2023 NATHAN ROMINE
Eng Process Fee Ord 176,300 Cleared 7/24/2023 TAL SHEMEN
Public Works-Highway Ded. Cleared 7/24/2023 TAL SHEMEN
Roof/Waste drainage to street Cleared 7/24/2023 TAL SHEMEN
Public Works-Sewers Cleared 7/24/2023 TAL SHEMEN
Grading Pre-Inspection Cleared 7/26/2023 MICHAEL TEMPLE
Public Works-Open Permits Cleared 7/28/2023 TAL SHEMEN

Contact Information

Contractor Owner-Builder       ,
Engineer Melchor,, Oscar Elias; Lic. No.: C76828 21243 VENTURA BLVD SUITE 119      WOODLAND HILLS, CA 91364

Inspector Information

DAVID FASTIGGI, (818) 774-4317 Office Hours: 7:00-8:00 AM MON-FRI
ALEXANDER HANDY, (818) 774-4317 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 8/28/2023 Approved ALEXANDER HANDY
Footing/Foundation/Slab 8/28/2023 Approved ALEXANDER HANDY
BUILDING-Rough-Frame 9/22/2023 Partial Approval ALEXANDER HANDY
Green Building Rough 9/22/2023 Not Ready for Inspection ALEXANDER HANDY
BUILDING-Rough-Frame 10/12/2023 Not Ready for Inspection JEFFREY PARD
ELECTRICAL-Rough 10/12/2023 Approved JEFFREY PARD
Green Building Rough 10/12/2023 Not Ready for Inspection JEFFREY PARD
PLUMBING-Rough 10/12/2023 Approved JEFFREY PARD
BUILDING-Rough-Frame 10/17/2023 Approved ALEXANDER HANDY
Green Building Rough 10/17/2023 Approved ALEXANDER HANDY
HVAC-Rough 10/17/2023 Approved ALEXANDER HANDY
PLUMBING-Rough 10/17/2023 Approved ALEXANDER HANDY
Insulation 10/20/2023 Approved ALEXANDER HANDY
Drywall Nailing 10/27/2023 Approved JEFFREY BULL
Interior/Exterior Lathing 11/3/2023 Partial Approval JOHN KIDWELL
Shower Pan 11/7/2023 Approved ALEXANDER HANDY
ELECTRICAL-Final 1/17/2024 Corrections Issued HENRY KIM
Final 1/17/2024 Not Ready for Inspection HENRY KIM
Green Building Final 1/17/2024 Corrections Issued HENRY KIM
HVAC-Final 1/17/2024 Corrections Issued HENRY KIM
PLUMBING-Final 1/17/2024 Corrections Issued HENRY KIM
SGSOV-Seismic Gas S/O Valve 1/17/2024 SGSOV Approved HENRY KIM
Smoke Detectors 1/17/2024 Approved HENRY KIM
ELECTRICAL-Final 2/14/2024 Approved ALEXANDER HANDY
Final 2/14/2024 OK to Issue CofO ALEXANDER HANDY
Green Building Final 2/14/2024 Approved ALEXANDER HANDY
HVAC-Final 2/14/2024 Approved ALEXANDER HANDY
PLUMBING-Final 2/14/2024 Approved ALEXANDER HANDY