1507 S WALGROVE AVE 90066

Certificate Information: 1507 S WALGROVE AVE 90066

Application / Permit
23014-20000-02623
Plan Check / Job No.
B23VN08733
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
REMOVE ENTIRE SINGLE FAMILY DWELLING EXCEPT FOR 9'-0" OF WALL PORTION OF DINING ROOM AND BUILD NEW 2-STORY (3182 SQFT) SINGLE FAMILY DWELLING AND ATTACHED 2-CAR GARAGE (475 SQFT) W/NFPA 13D SPRINKLERS THROUGHOUT
Permit Issued
Issued on 3/22/2024
Issuing Office
Current Status
Issued on 3/22/2024
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 6/30/2023 APPLICANT
Assigned to Plan Check Engineer 7/6/2023 PETER MOSESIAN
Corrections Issued 7/9/2023 PETER MOSESIAN
Quality Review Completed 7/12/2023 OMID HEDAYAT
Building Plans Picked Up 7/18/2023 APPLICANT
Plan Check Approved 3/22/2024 PETER MOSESIAN
Issued 3/22/2024 APPLICANT

Permit Application Clearance Information

ZA Case Cleared 11/13/2023 ALEX VELA
Eng Process Fee Ord 176,300 Cleared 1/30/2024 DARIN LAM
Permit Cleared 1/30/2024 DARIN LAM
Sewer availability Cleared 1/30/2024 DARIN LAM
Grading Pre-Inspection Cleared 2/14/2024 VASIL MIHALEV
Trees in Parkway Cleared 2/15/2024 ADALBERTO VERA
Specific Plan Cleared 2/20/2024 FREDDY GARCIA
Hydrant and Access approval Cleared 2/24/2024 JOHN CONNEALLY
Low Impact Development (LID) Cleared 2/26/2024 SAMUEL LINN
Roof/Waste drainage to street Cleared 2/26/2024 DARIN LAM

Contact Information

Contractor Owner-Builder       ,
Engineer Galbreath,, Sean; Lic. No.: S5653 600 SOUTH LAKE AVE STE 308      PASADENA, CA 91106

Inspector Information

RUBEN RIVAS, (310) 914-3981 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

PLUMBING-Final 6/8/2026   
ELECTRICAL-Final 6/10/2026   

Inspection Request History

Pre-Inspection 8/5/2024 Partial Inspection HERBERT GIRON
Footing/Foundation/Slab 10/17/2024 Corrections Issued HERBERT GIRON
Footing/Foundation/Slab 10/22/2024 Partial Approval JESUS PINEDA
Footing/Foundation/Slab 11/8/2024 Not Ready for Inspection HERBERT GIRON
Excavation/Setback/Form/Re-Bar 11/9/2024 Approved BOBBY KEY
Footing/Foundation/Slab 11/9/2024 Approved BOBBY KEY
Deputy Wood Construction 11/15/2024 Approved HERBERT GIRON
Floor/Roof Diaphrgm/Shear Wall 11/15/2024 Corrections Issued HERBERT GIRON
PLUMBING-Rough 11/22/2024 Not Ready for Inspection HERBERT GIRON
Gas Test 11/25/2024 Partial Approval HERBERT GIRON
BUILDING-Rough-Frame 12/3/2024 Partial Approval HERBERT GIRON
PLUMBING-Rough 12/3/2024 Partial Approval HERBERT GIRON
Deputy Drilled-In Anchors 12/4/2024 Approved JESUS PINEDA
Floor/Roof Diaphrgm/Shear Wall 12/4/2024 Corrections Issued JESUS PINEDA
Deputy Steel/Welding 12/11/2024 Conditional Approval HERBERT GIRON
Floor/Roof Diaphrgm/Shear Wall 12/20/2024 Corrections Issued HERBERT GIRON
Floor/Roof Diaphrgm/Shear Wall 12/24/2024 Approved BOBBY KEY
Deputy Wood Construction 2/14/2025 Conditional Approval HERBERT GIRON
Floor/Roof Diaphrgm/Shear Wall 3/3/2025 Corrections Issued HERBERT GIRON
Floor/Roof Diaphrgm/Shear Wall 3/11/2025 Partial Approval JESUS RODRIGUEZ
Interior/Exterior Lathing 9/9/2025 Approved JESUS RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 10/9/2025 Approved RUBEN RIVAS
Insulation 10/9/2025 Approved RUBEN RIVAS
BUILDING-Rough-Frame 10/17/2025 Conditional Approval JESUS RODRIGUEZ
Drywall Nailing 10/17/2025 Conditional Approval JESUS RODRIGUEZ
Green Building Rough 10/17/2025 Conditional Approval JESUS RODRIGUEZ
Verify Sprinkler Sign Off 10/17/2025 Approved JESUS RODRIGUEZ
Shower Pan 12/16/2025 Corrections Issued RUBEN RIVAS
Shower Pan 12/19/2025 Approved RUBEN RIVAS
Interior/Exterior Lathing 1/6/2026 Partial Approval RUBEN RIVAS