ePlan Addition to enlarge 2 bedrooms, add master Bath at rear of building. Interior remodel per plan
Permit Issued
Issued on 7/20/2023
Issuing Office
Current Status
Issued on 7/20/2023
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 7/10/2023 APPLICANT
Assigned to Plan Check Engineer 7/10/2023 KHUONG TRUONG
Corrections Issued 7/11/2023 KHUONG TRUONG
Plan Check Approved 7/20/2023 KHUONG TRUONG
Issued 7/20/2023 APPLICANT

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 7/12/2023 FERNANDO GIL
Sewer availability Cleared 7/12/2023 FERNANDO GIL
Eng Process Fee Ord 176,300 Cleared 7/13/2023 FERNANDO GIL

Contact Information

Architect Dembsky,, Amit; Lic. No.: NA30383       ,
Contractor Preferred Home Builders Inc; Lic. No.: 773147-B       ,

Inspector Information

JEFFREY HARTLINE, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI
CHRIS CHRISTENSEN, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 8/14/2023 Approved CHRIS CHRISTENSEN
Footing/Foundation/Slab 8/14/2023 Approved CHRIS CHRISTENSEN
BUILDING-Rough-Frame 8/23/2023 Partial Approval CHRIS CHRISTENSEN
PLUMBING-Rough 8/23/2023 Partial Approval CHRIS CHRISTENSEN
Sewer 8/23/2023 Partial Approval CHRIS CHRISTENSEN
Floor/Roof Diaphrgm/Shear Wall 8/25/2023 Partial Approval CHRIS CHRISTENSEN
Insulation 8/25/2023 Partial Approval CHRIS CHRISTENSEN
Floor/Roof Diaphrgm/Shear Wall 9/5/2023 Approved JEFFREY HARTLINE
BUILDING-Rough-Frame 9/7/2023 Conditional Approval CHRIS CHRISTENSEN
ELECTRICAL-Rough 9/7/2023 Approved CHRIS CHRISTENSEN
Green Building Rough 9/7/2023 Not Ready for Inspection CHRIS CHRISTENSEN
HVAC-Rough 9/7/2023 Approved CHRIS CHRISTENSEN
PLUMBING-Rough 9/7/2023 Approved CHRIS CHRISTENSEN
Insulation 9/11/2023 Not Ready for Inspection CHRIS CHRISTENSEN
Interior/Exterior Lathing 9/11/2023 Partial Approval CHRIS CHRISTENSEN
BUILDING-Rough-Frame 9/12/2023 Approved CHRIS CHRISTENSEN
Green Building Rough 9/12/2023 Approved CHRIS CHRISTENSEN
Insulation 9/12/2023 Approved CHRIS CHRISTENSEN
Drywall Nailing 9/18/2023 Approved CHRIS CHRISTENSEN
Interior/Exterior Lathing 9/21/2023 Not Ready for Inspection CHRIS CHRISTENSEN
Shower Pan 9/21/2023 Approved CHRIS CHRISTENSEN
Interior/Exterior Lathing 9/27/2023 Approved CHRIS CHRISTENSEN
Final 10/16/2023 Corrections Issued CHRIS CHRISTENSEN
Green Building Final 10/16/2023 Not Ready for Inspection CHRIS CHRISTENSEN
SGSOV-Seismic Gas S/O Valve 10/16/2023 SGSOV Approved CHRIS CHRISTENSEN
Smoke Detectors 10/16/2023 Approved CHRIS CHRISTENSEN
Final 10/19/2023 Not Ready for Inspection CHRIS CHRISTENSEN
Green Building Final 10/19/2023 Approved CHRIS CHRISTENSEN